Rahees P |
Date: 04/01/2024 |
Work in progress | 99% Completed
regulator|100% Completed
mechanical works|100% Completed
electrical works|100% Completed
generator room with guard room|100% Completed
bank protection works|100% Completed
Due to requests from locals shutter downed and stored the water 1.5 m level. Work completed
Rahees P |
Date: 19/06/2023 |
Work in progress | 99% Completed
bank protection works|100% Completed
mechanical works|100% Completed
electrical works|100% Completed
generator room with guard room|100% Completed
regulator|100% Completed
Work completed, RE progressing
Rahees P |
Date: 10/06/2023 |
Work in progress | 99% Completed
bank protection works|100% Completed
mechanical works|100% Completed
electrical works|100% Completed
generator room with guard room|100% Completed
regulator|100% Completed
RE-2 Work progressing.measuring scale order placed.Raining at site.
Rahees P |
Date: 22/05/2023 |
Work in progress | 99% Completed
bank protection works|100% Completed
mechanical works|100% Completed
electrical works|100% Completed
generator room with guard room|100% Completed
regulator|100% Completed
Work completed additional work suggested by KIIFB fixing handrail is completed.Chief engineer Terrance sir visited our site.
Rahees P |
Date: 17/05/2023 |
Work in progress | 99% Completed
bank protection works|100% Completed
mechanical works|100% Completed
electrical works|100% Completed
generator room with guard room|100% Completed
regulator|100% Completed
All major works are completed
Rahees P |
Date: 09/05/2023 |
Work in progress | 99% Completed
bank protection works|100% Completed
mechanical works|100% Completed
electrical works|100% Completed
generator room with guard room|100% Completed
regulator|100% Completed
Work completed and water stored with closing shutter.
Rahees P |
Date: 28/04/2023 |
Work in progress | 99% Completed
bank protection works|100% Completed
mechanical works|100% Completed
electrical works|100% Completed
generator room with guard room|100% Completed
regulator|100% Completed
Works are completed.KIIFB final inspection completed.
Rahees P |
Date: 11/04/2023 |
Work in progress | 99% Completed
bank protection works|100% Completed
mechanical works|100% Completed
electrical works|100% Completed
generator room with guard room|100% Completed
regulator|100% Completed
Work completed, and final inspection confirmed on 12/4/23
Rahees P |
Date: 27/03/2023 |
Work in progress | 99% Completed
regulator|100% Completed
mechanical works|100% Completed
electrical works|100% Completed
generator room with guard room|100% Completed
bank protection works|100% Completed
Pre final bill 12 is preparing, Jamal sir and Sethumadavan sir visited at site .D/s L/S stopped RR work completed
Rahees P |
Date: 21/03/2023 |
Work in progress | 99% Completed
regulator|100% Completed
mechanical works|100% Completed
electrical works|100% Completed
generator room with guard room|100% Completed
bank protection works|100% Completed
Work almost completed ,solar lights fixed back filling and compacting completed, RR work of stopper D/s completed
Rahees P |
Date: 13/03/2023 |
Work in progress | 99% Completed
bank protection works|100% Completed
mechanical works|100% Completed
electrical works|100% Completed
generator room with guard room|100% Completed
regulator|100% Completed
Tiling on bathroom finished, Back filling completed ,Ramp concreted,stair finished
Rahees P |
Date: 01/03/2023 |
Work in progress | 99% Completed
bank protection works|100% Completed
mechanical works|100% Completed
electrical works|100% Completed
generator room with guard room|100% Completed
regulator|100% Completed
Retaining wall completed and painting and finishing also completed.removing of earth from river is progressing
Rahees P |
Date: 20/02/2023 |
Work in progress | 97% Completed
bank protection works|100% Completed
mechanical works|100% Completed
electrical works|100% Completed
generator room with guard room|100% Completed
regulator|100% Completed
Painting work ongoing,rubble retaining wall work progressing, shutter sealant checking completed
Rahees P |
Date: 13/02/2023 |
Work in progress | 97% Completed
electrical works|100% Completed
mechanical works|100% Completed
generator room with guard room|100% Completed
bank protection works|100% Completed
regulator|100% Completed
Retaining wall with rubble work progressing,painting work ongoing RE work started
Rahees P |
Date: 06/02/2023 |
Work in progress | 97% Completed
regulator|100% Completed
mechanical works|100% Completed
electrical works|100% Completed
generator room with guard room|100% Completed
bank protection works|100% Completed
Retaining wall RR work progressing.painting work just started. Mechanical and electrical work progressing
Rahees P |
Date: 30/01/2023 |
Work in progress | 96% Completed
bank protection works|100% Completed
mechanical works|100% Completed
electrical works|100% Completed
generator room with guard room|100% Completed
regulator|100% Completed
Balance 22 m of retaining wall work started,first 11m Dry Rubble masonry work finished and belt work ongoing.also painting work and finishing works ongoing
Rahees P |
Date: 23/01/2023 |
Work in progress | 96% Completed
bank protection works|100% Completed
mechanical works|100% Completed
electrical works|100% Completed
generator room with guard room|100% Completed
regulator|100% Completed
Balance retaining wall foundation work ongoing,Backfilling progressing, Electrical work progressing
Rahees P |
Date: 15/01/2023 |
Work in progress | 96% Completed
generator room with guard room|100% Completed
mechanical works|100% Completed
regulator|100% Completed
electrical works|100% Completed
bank protection works|100% Completed
Balance 20 m retaining work- ring bund Constructed.shutter painting ongoing.guard room finishing work ongoing
Rahees P |
Date: 06/01/2023 |
Work in progress | 96% Completed
regulator|100% Completed
bank protection works|100% Completed
generator room with guard room|100% Completed
electrical works|100% Completed
mechanical works|100% Completed
Painting on shutter ongoing,Guard room doors and windows fixed also Gabion box fixing ongoing
Rahees P |
Date: 03/01/2023 |
Work in progress | 96% Completed
regulator|100% Completed
mechanical works|100% Completed
electrical works|100% Completed
generator room with guard room|100% Completed
bank protection works|100% Completed
Painting work started and electrical work is ongoing. Alignment clearing of hoisting bridge is progressing.
Rahees P |
Date: 26/12/2022 |
Work in progress | 95% Completed
bank protection works|100% Completed
mechanical works|100% Completed
electrical works|100% Completed
generator room with guard room|100% Completed
regulator|100% Completed
Gate erection completed (4/4)
Rahees P |
Date: 19/12/2022 |
Work in progress | 93% Completed
bank protection works|100% Completed
mechanical works|100% Completed
electrical works|100% Completed
generator room with guard room|100% Completed
regulator|100% Completed
Erecting ramp work ongoing and finished the platform end.
Rahees P |
Date: 16/12/2022 |
Work in progress | 93% Completed
bank protection works|100% Completed
mechanical works|100% Completed
electrical works|100% Completed
generator room with guard room|100% Completed
regulator|100% Completed
Ramp work almost completed and platform creating for the smooth erection purpose
Rahees P |
Date: 15/12/2022 |
Work in progress | 93% Completed
electrical works|100% Completed
mechanical works|100% Completed
generator room with guard room|100% Completed
bank protection works|100% Completed
regulator|100% Completed
Guard room flooring finished by cement concrete flooring.Ramp work progressing for erection of shutter
Rahees P |
Date: 12/12/2022 |
Work in progress | 93% Completed
regulator|100% Completed
mechanical works|100% Completed
electrical works|100% Completed
generator room with guard room|100% Completed
bank protection works|100% Completed
Ramp construction for erection of gate is ongoing And also heavy raining ocured
Rahees P |
Date: 12/12/2022 |
Work in progress | 93% Completed
mechanical works|100% Completed
electrical works|100% Completed
generator room with guard room|100% Completed
bank protection works|100% Completed
regulator|100% Completed
Due to heavy rain at site ring bund and ramp for erecting work destroyed
Rahees P |
Date: 02/12/2022 |
Work in progress | 93% Completed
bank protection works|100% Completed
mechanical works|100% Completed
electrical works|100% Completed
generator room with guard room|100% Completed
regulator|100% Completed
River flow just diverted on two sill beam for construction of ring bund for mechanical shutter erection
Rahees P |
Date: 24/11/2022 |
Work in progress | 93% Completed
generator room with guard room|100% Completed
mechanical works|100% Completed
regulator|100% Completed
electrical works|100% Completed
bank protection works|100% Completed
for constructing gravity wall left side upstream side balance 22m work ring bund started.but due to some issues rised by the nearest land owner ,work temporarily stopped.
Rahees P |
Date: 01/11/2022 |
Work in progress | 93% Completed
electrical works|100% Completed
mechanical works|100% Completed
generator room with guard room|100% Completed
bank protection works|100% Completed
regulator|100% Completed
Plastering work front and two sides completed KIIFB inspection carried out on29th October
Rahees P |
Date: 25/10/2022 |
Work in progress | 93% Completed
regulator|100% Completed
mechanical works|100% Completed
electrical works|100% Completed
generator room with guard room|100% Completed
bank protection works|100% Completed
eft side upstream side 20m balance work will start only after the water level decrease in river.
Rahees P |
Date: 25/10/2022 |
Work in progress | 92% Completed
bank protection works|100% Completed
mechanical works|100% Completed
electrical works|100% Completed
generator room with guard room|100% Completed
regulator|100% Completed
only erection and fixing of shutter and hoisting platform work pending
Rahees P |
Date: 25/10/2022 |
Work in progress | 70% Completed
bank protection works|100% Completed
mechanical works|100% Completed
electrical works|100% Completed
generator room with guard room|100% Completed
regulator|100% Completed
left side upstream side 20m balance work will start only after the water level decrease in river.
Rahees P |
Date: 25/10/2022 |
Work in progress | 23% Completed
bank protection works|100% Completed
mechanical works|100% Completed
electrical works|100% Completed
generator room with guard room|100% Completed
regulator|100% Completed
only P4- Secondary concrete pending.
Rahees P |
Date: 25/10/2022 |
Work in progress | 1% Completed
electrical works|100% Completed
mechanical works|100% Completed
generator room with guard room|100% Completed
bank protection works|100% Completed
regulator|100% Completed
plastering work ongoing -50% completed
Rahees P |
Date: 10/10/2022 |
Work in progress | 95% Completed
regulator|100% Completed
mechanical works|100% Completed
electrical works|100% Completed
generator room with guard room|100% Completed
bank protection works|100% Completed
Heavy rain occurred at site.water level increased 30 cm rised. guard room electrical work started.
Rahees P |
Date: 03/10/2022 |
Work in progress | 95% Completed
bank protection works|100% Completed
mechanical works|100% Completed
electrical works|100% Completed
generator room with guard room|100% Completed
regulator|100% Completed
NO OTHER PROGRESS IN WORK DUE TO WATER LEVEL NOT REDUCED.SECURITY ROOM WORK STOPPED, ELECTRICAL CONDUIT CONCEALED WORK WILL START NEXT WEEK ONWARDS.REVISED ESTIMATE IS UNDER APPROVAL AT OFFICE.
Rahees P |
Date: 29/09/2022 |
Work in progress | 95% Completed
bank protection works|100% Completed
mechanical works|100% Completed
electrical works|100% Completed
generator room with guard room|100% Completed
regulator|100% Completed
no further work is done at site.water level reduced only 10 cm in river.plastering of guard room will start after the completion of concealed electrical pipe fitting.arranged a meeting of electrical engineers on after 30/9/22.total station carried for the level checking which already established BM at site.(from payyanad stadium to site).
Anu IT Admin |
Date: 22/09/2022 |
Work in progress | 95% Completed
generator room with guard room|100% Completed
bank protection works|100% Completed
mechanical works|100% Completed
regulator|100% Completed
electrical works|100% Completed
Regulator portion civil work completed. only P1 secondary concrete pending. Right side retaining wall fully completed (160m/160m). Left side retaining wall 20m out of 163m is pending. Regulator portion and retaining wall work paused due to heavy flow of water in river. Guard room construction civil structural work completed. laid roof sheet and plastering work to be started. Electrical drawing finalised, work will start after completion of guardroom plastering. Mechanical shutters are constructed and ready to erect.