Rahees P
Date: 04/01/2024

Work in progress | 99% Completed

100.00% regulator|100% Completed

100.00% mechanical works|100% Completed

100.00% electrical works|100% Completed

100.00% generator room with guard room|100% Completed

100.00% bank protection works|100% Completed

Due to requests from locals shutter downed and stored the water 1.5 m level. Work completed

Rahees P
Date: 19/06/2023

Work in progress | 99% Completed

100.00% bank protection works|100% Completed

100.00% mechanical works|100% Completed

100.00% electrical works|100% Completed

100.00% generator room with guard room|100% Completed

100.00% regulator|100% Completed

Work completed, RE progressing

Rahees P
Date: 10/06/2023

Work in progress | 99% Completed

100.00% bank protection works|100% Completed

100.00% mechanical works|100% Completed

100.00% electrical works|100% Completed

100.00% generator room with guard room|100% Completed

100.00% regulator|100% Completed

RE-2 Work progressing.measuring scale order placed.Raining at site.

Rahees P
Date: 22/05/2023

Work in progress | 99% Completed

100.00% bank protection works|100% Completed

100.00% mechanical works|100% Completed

100.00% electrical works|100% Completed

100.00% generator room with guard room|100% Completed

100.00% regulator|100% Completed

Work completed additional work suggested by KIIFB fixing handrail is completed.Chief engineer Terrance sir visited our site.

Rahees P
Date: 17/05/2023

Work in progress | 99% Completed

100.00% bank protection works|100% Completed

100.00% mechanical works|100% Completed

100.00% electrical works|100% Completed

100.00% generator room with guard room|100% Completed

100.00% regulator|100% Completed

All major works are completed

Rahees P
Date: 09/05/2023

Work in progress | 99% Completed

100.00% bank protection works|100% Completed

100.00% mechanical works|100% Completed

100.00% electrical works|100% Completed

100.00% generator room with guard room|100% Completed

100.00% regulator|100% Completed

Work completed and water stored with closing shutter.

Rahees P
Date: 28/04/2023

Work in progress | 99% Completed

100.00% bank protection works|100% Completed

100.00% mechanical works|100% Completed

100.00% electrical works|100% Completed

100.00% generator room with guard room|100% Completed

100.00% regulator|100% Completed

Works are completed.KIIFB final inspection completed.

Rahees P
Date: 11/04/2023

Work in progress | 99% Completed

100.00% bank protection works|100% Completed

100.00% mechanical works|100% Completed

100.00% electrical works|100% Completed

100.00% generator room with guard room|100% Completed

100.00% regulator|100% Completed

Work completed, and final inspection confirmed on 12/4/23

Rahees P
Date: 27/03/2023

Work in progress | 99% Completed

100.00% regulator|100% Completed

100.00% mechanical works|100% Completed

100.00% electrical works|100% Completed

100.00% generator room with guard room|100% Completed

100.00% bank protection works|100% Completed

Pre final bill 12 is preparing, Jamal sir and Sethumadavan sir visited at site .D/s L/S stopped RR work completed

Rahees P
Date: 21/03/2023

Work in progress | 99% Completed

100.00% regulator|100% Completed

100.00% mechanical works|100% Completed

100.00% electrical works|100% Completed

100.00% generator room with guard room|100% Completed

100.00% bank protection works|100% Completed

Work almost completed ,solar lights fixed back filling and compacting completed, RR work of stopper D/s completed

Rahees P
Date: 13/03/2023

Work in progress | 99% Completed

100.00% bank protection works|100% Completed

100.00% mechanical works|100% Completed

100.00% electrical works|100% Completed

100.00% generator room with guard room|100% Completed

100.00% regulator|100% Completed

Tiling on bathroom finished, Back filling completed ,Ramp concreted,stair finished

Rahees P
Date: 01/03/2023

Work in progress | 99% Completed

100.00% bank protection works|100% Completed

100.00% mechanical works|100% Completed

100.00% electrical works|100% Completed

100.00% generator room with guard room|100% Completed

100.00% regulator|100% Completed

Retaining wall completed and painting and finishing also completed.removing of earth from river is progressing

Rahees P
Date: 20/02/2023

Work in progress | 97% Completed

100.00% bank protection works|100% Completed

100.00% mechanical works|100% Completed

100.00% electrical works|100% Completed

100.00% generator room with guard room|100% Completed

100.00% regulator|100% Completed

Painting work ongoing,rubble retaining wall work progressing, shutter sealant checking completed

Rahees P
Date: 13/02/2023

Work in progress | 97% Completed

100.00% electrical works|100% Completed

100.00% mechanical works|100% Completed

100.00% generator room with guard room|100% Completed

100.00% bank protection works|100% Completed

100.00% regulator|100% Completed

Retaining wall with rubble work progressing,painting work ongoing RE work started

Rahees P
Date: 06/02/2023

Work in progress | 97% Completed

100.00% regulator|100% Completed

100.00% mechanical works|100% Completed

100.00% electrical works|100% Completed

100.00% generator room with guard room|100% Completed

100.00% bank protection works|100% Completed

Retaining wall RR work progressing.painting work just started. Mechanical and electrical work progressing

Rahees P
Date: 30/01/2023

Work in progress | 96% Completed

100.00% bank protection works|100% Completed

100.00% mechanical works|100% Completed

100.00% electrical works|100% Completed

100.00% generator room with guard room|100% Completed

100.00% regulator|100% Completed

Balance 22 m of retaining wall work started,first 11m Dry Rubble masonry work finished and belt work ongoing.also painting work and finishing works ongoing

Rahees P
Date: 23/01/2023

Work in progress | 96% Completed

100.00% bank protection works|100% Completed

100.00% mechanical works|100% Completed

100.00% electrical works|100% Completed

100.00% generator room with guard room|100% Completed

100.00% regulator|100% Completed

Balance retaining wall foundation work ongoing,Backfilling progressing, Electrical work progressing

Rahees P
Date: 15/01/2023

Work in progress | 96% Completed

100.00% generator room with guard room|100% Completed

100.00% mechanical works|100% Completed

100.00% regulator|100% Completed

100.00% electrical works|100% Completed

100.00% bank protection works|100% Completed

Balance 20 m retaining work- ring bund Constructed.shutter painting ongoing.guard room finishing work ongoing

Rahees P
Date: 06/01/2023

Work in progress | 96% Completed

100.00% regulator|100% Completed

100.00% bank protection works|100% Completed

100.00% generator room with guard room|100% Completed

100.00% electrical works|100% Completed

100.00% mechanical works|100% Completed

Painting on shutter ongoing,Guard room doors and windows fixed also Gabion box fixing ongoing

Rahees P
Date: 03/01/2023

Work in progress | 96% Completed

100.00% regulator|100% Completed

100.00% mechanical works|100% Completed

100.00% electrical works|100% Completed

100.00% generator room with guard room|100% Completed

100.00% bank protection works|100% Completed

Painting work started and electrical work is ongoing. Alignment clearing of hoisting bridge is progressing.

Rahees P
Date: 26/12/2022

Work in progress | 95% Completed

100.00% bank protection works|100% Completed

100.00% mechanical works|100% Completed

100.00% electrical works|100% Completed

100.00% generator room with guard room|100% Completed

100.00% regulator|100% Completed

Gate erection completed (4/4)

Rahees P
Date: 19/12/2022

Work in progress | 93% Completed

100.00% bank protection works|100% Completed

100.00% mechanical works|100% Completed

100.00% electrical works|100% Completed

100.00% generator room with guard room|100% Completed

100.00% regulator|100% Completed

Erecting ramp work ongoing and finished the platform end.

Rahees P
Date: 16/12/2022

Work in progress | 93% Completed

100.00% bank protection works|100% Completed

100.00% mechanical works|100% Completed

100.00% electrical works|100% Completed

100.00% generator room with guard room|100% Completed

100.00% regulator|100% Completed

Ramp work almost completed and platform creating for the smooth erection purpose

Rahees P
Date: 15/12/2022

Work in progress | 93% Completed

100.00% electrical works|100% Completed

100.00% mechanical works|100% Completed

100.00% generator room with guard room|100% Completed

100.00% bank protection works|100% Completed

100.00% regulator|100% Completed

Guard room flooring finished by cement concrete flooring.Ramp work progressing for erection of shutter

Rahees P
Date: 12/12/2022

Work in progress | 93% Completed

100.00% regulator|100% Completed

100.00% mechanical works|100% Completed

100.00% electrical works|100% Completed

100.00% generator room with guard room|100% Completed

100.00% bank protection works|100% Completed

Ramp construction for erection of gate is ongoing And also heavy raining ocured

Rahees P
Date: 12/12/2022

Work in progress | 93% Completed

100.00% mechanical works|100% Completed

100.00% electrical works|100% Completed

100.00% generator room with guard room|100% Completed

100.00% bank protection works|100% Completed

100.00% regulator|100% Completed

Due to heavy rain at site ring bund and ramp for erecting work destroyed

Rahees P
Date: 02/12/2022

Work in progress | 93% Completed

100.00% bank protection works|100% Completed

100.00% mechanical works|100% Completed

100.00% electrical works|100% Completed

100.00% generator room with guard room|100% Completed

100.00% regulator|100% Completed

River flow just diverted on two sill beam for construction of ring bund for mechanical shutter erection

Rahees P
Date: 24/11/2022

Work in progress | 93% Completed

100.00% generator room with guard room|100% Completed

100.00% mechanical works|100% Completed

100.00% regulator|100% Completed

100.00% electrical works|100% Completed

100.00% bank protection works|100% Completed

for constructing gravity wall left side upstream side balance 22m work ring bund started.but due to some issues rised by the nearest land owner ,work temporarily stopped.

Rahees P
Date: 01/11/2022

Work in progress | 93% Completed

100.00% electrical works|100% Completed

100.00% mechanical works|100% Completed

100.00% generator room with guard room|100% Completed

100.00% bank protection works|100% Completed

100.00% regulator|100% Completed

Plastering work front and two sides completed KIIFB inspection carried out on29th October

Rahees P
Date: 25/10/2022

Work in progress | 93% Completed

100.00% regulator|100% Completed

100.00% mechanical works|100% Completed

100.00% electrical works|100% Completed

100.00% generator room with guard room|100% Completed

100.00% bank protection works|100% Completed

eft side upstream side 20m balance work will start only after the water level decrease in river.

Rahees P
Date: 25/10/2022

Work in progress | 92% Completed

100.00% bank protection works|100% Completed

100.00% mechanical works|100% Completed

100.00% electrical works|100% Completed

100.00% generator room with guard room|100% Completed

100.00% regulator|100% Completed

only erection and fixing of shutter and hoisting platform work pending

Rahees P
Date: 25/10/2022

Work in progress | 70% Completed

100.00% bank protection works|100% Completed

100.00% mechanical works|100% Completed

100.00% electrical works|100% Completed

100.00% generator room with guard room|100% Completed

100.00% regulator|100% Completed

left side upstream side 20m balance work will start only after the water level decrease in river.

Rahees P
Date: 25/10/2022

Work in progress | 23% Completed

100.00% bank protection works|100% Completed

100.00% mechanical works|100% Completed

100.00% electrical works|100% Completed

100.00% generator room with guard room|100% Completed

100.00% regulator|100% Completed

only P4- Secondary concrete pending.

Rahees P
Date: 25/10/2022

Work in progress | 1% Completed

100.00% electrical works|100% Completed

100.00% mechanical works|100% Completed

100.00% generator room with guard room|100% Completed

100.00% bank protection works|100% Completed

100.00% regulator|100% Completed

plastering work ongoing -50% completed

Rahees P
Date: 10/10/2022

Work in progress | 95% Completed

100.00% regulator|100% Completed

100.00% mechanical works|100% Completed

100.00% electrical works|100% Completed

100.00% generator room with guard room|100% Completed

100.00% bank protection works|100% Completed

Heavy rain occurred at site.water level increased 30 cm rised. guard room electrical work started.

Rahees P
Date: 03/10/2022

Work in progress | 95% Completed

100.00% bank protection works|100% Completed

100.00% mechanical works|100% Completed

100.00% electrical works|100% Completed

100.00% generator room with guard room|100% Completed

100.00% regulator|100% Completed

NO OTHER PROGRESS IN WORK DUE TO WATER LEVEL NOT REDUCED.SECURITY ROOM WORK STOPPED, ELECTRICAL CONDUIT CONCEALED WORK WILL START NEXT WEEK ONWARDS.REVISED ESTIMATE IS UNDER APPROVAL AT OFFICE.

Rahees P
Date: 29/09/2022

Work in progress | 95% Completed

100.00% bank protection works|100% Completed

100.00% mechanical works|100% Completed

100.00% electrical works|100% Completed

100.00% generator room with guard room|100% Completed

100.00% regulator|100% Completed

no further work is done at site.water level reduced only 10 cm in river.plastering of guard room will start after the completion of concealed electrical pipe fitting.arranged a meeting of electrical engineers on after 30/9/22.total station carried for the level checking which already established BM at site.(from payyanad stadium to site).

Anu IT Admin
Date: 22/09/2022

Work in progress | 95% Completed

100.00% generator room with guard room|100% Completed

100.00% bank protection works|100% Completed

100.00% mechanical works|100% Completed

100.00% regulator|100% Completed

100.00% electrical works|100% Completed

Regulator portion civil work completed. only P1 secondary concrete pending. Right side retaining wall fully completed (160m/160m). Left side retaining wall 20m out of 163m is pending. Regulator portion and retaining wall work paused due to heavy flow of water in river. Guard room construction civil structural work completed. laid roof sheet and plastering work to be started. Electrical drawing finalised, work will start after completion of guardroom plastering. Mechanical shutters are constructed and ready to erect.

Rahees P
Date: 04/01/2024

Work in progress | 0% Completed

Due to requests from locals shutter downed and stored the water 1.5 m level. Work completed

Rahees P
Date: 04/01/2024

Work in progress | 0% Completed

Due to requests from locals shutter downed and stored the water 1.5 m level. Work completed

Rahees P
Date: 04/01/2024

Work in progress | 0% Completed

Due to requests from locals shutter downed and stored the water 1.5 m level. Work completed

Rahees P
Date: 04/01/2024

Work in progress | 0% Completed

Due to requests from locals shutter downed and stored the water 1.5 m level. Work completed

Rahees P
Date: 04/01/2024

Work in progress | 0% Completed

Due to requests from locals shutter downed and stored the water 1.5 m level. Work completed

Rahees P
Date: 19/06/2023

Work in progress | 0% Completed

Work completed, RE progressing

Rahees P
Date: 19/06/2023

Work in progress | 0% Completed

Work completed, RE progressing

Rahees P
Date: 19/06/2023

Work in progress | 0% Completed

Work completed, RE progressing

Rahees P
Date: 19/06/2023

Work in progress | 0% Completed

Work completed, RE progressing

Rahees P
Date: 19/06/2023

Work in progress | 0% Completed

Work completed, RE progressing

Rahees P
Date: 10/06/2023

Work in progress | 0% Completed

RE-2 Work progressing.measuring scale order placed.Raining at site.

Rahees P
Date: 10/06/2023

Work in progress | 0% Completed

RE-2 Work progressing.measuring scale order placed.Raining at site.

Rahees P
Date: 10/06/2023

Work in progress | 0% Completed

RE-2 Work progressing.measuring scale order placed.Raining at site.

Rahees P
Date: 10/06/2023

Work in progress | 0% Completed

RE-2 Work progressing.measuring scale order placed.Raining at site.

Rahees P
Date: 10/06/2023

Work in progress | 0% Completed

RE-2 Work progressing.measuring scale order placed.Raining at site.

Rahees P
Date: 22/05/2023

Work in progress | 0% Completed

Work completed additional work suggested by KIIFB fixing handrail is completed.Chief engineer Terrance sir visited our site.

Rahees P
Date: 22/05/2023

Work in progress | 0% Completed

Work completed additional work suggested by KIIFB fixing handrail is completed.Chief engineer Terrance sir visited our site.

Rahees P
Date: 22/05/2023

Work in progress | 0% Completed

Work completed additional work suggested by KIIFB fixing handrail is completed.Chief engineer Terrance sir visited our site.

Rahees P
Date: 22/05/2023

Work in progress | 0% Completed

Work completed additional work suggested by KIIFB fixing handrail is completed.Chief engineer Terrance sir visited our site.

Rahees P
Date: 22/05/2023

Work in progress | 0% Completed

Work completed additional work suggested by KIIFB fixing handrail is completed.Chief engineer Terrance sir visited our site.

Rahees P
Date: 17/05/2023

Work in progress | 0% Completed

All major works are completed

Rahees P
Date: 17/05/2023

Work in progress | 0% Completed

All major works are completed

Rahees P
Date: 17/05/2023

Work in progress | 0% Completed

All major works are completed

Rahees P
Date: 17/05/2023

Work in progress | 0% Completed

All major works are completed

Rahees P
Date: 17/05/2023

Work in progress | 0% Completed

All major works are completed

Rahees P
Date: 09/05/2023

Work in progress | 0% Completed

Work completed and water stored with closing shutter.

Rahees P
Date: 09/05/2023

Work in progress | 0% Completed

Work completed and water stored with closing shutter.

Rahees P
Date: 09/05/2023

Work in progress | 0% Completed

Work completed and water stored with closing shutter.

Rahees P
Date: 09/05/2023

Work in progress | 0% Completed

Work completed and water stored with closing shutter.

Rahees P
Date: 09/05/2023

Work in progress | 0% Completed

Work completed and water stored with closing shutter.

Rahees P
Date: 28/04/2023

Work in progress | 0% Completed

Works are completed.KIIFB final inspection completed.

Rahees P
Date: 28/04/2023

Work in progress | 0% Completed

Works are completed.KIIFB final inspection completed.

Rahees P
Date: 28/04/2023

Work in progress | 0% Completed

Works are completed.KIIFB final inspection completed.

Rahees P
Date: 28/04/2023

Work in progress | 0% Completed

Works are completed.KIIFB final inspection completed.

Rahees P
Date: 28/04/2023

Work in progress | 0% Completed

Works are completed.KIIFB final inspection completed.

Rahees P
Date: 11/04/2023

Work in progress | 0% Completed

Work completed, and final inspection confirmed on 12/4/23

Rahees P
Date: 11/04/2023

Work in progress | 0% Completed

Work completed, and final inspection confirmed on 12/4/23

Rahees P
Date: 11/04/2023

Work in progress | 0% Completed

Work completed, and final inspection confirmed on 12/4/23

Rahees P
Date: 11/04/2023

Work in progress | 0% Completed

Work completed, and final inspection confirmed on 12/4/23

Rahees P
Date: 11/04/2023

Work in progress | 0% Completed

Work completed, and final inspection confirmed on 12/4/23

Rahees P
Date: 27/03/2023

Work in progress | 0% Completed

Pre final bill 12 is preparing, Jamal sir and Sethumadavan sir visited at site .D/s L/S stopped RR work completed

Rahees P
Date: 27/03/2023

Work in progress | 0% Completed

Pre final bill 12 is preparing, Jamal sir and Sethumadavan sir visited at site .D/s L/S stopped RR work completed

Rahees P
Date: 27/03/2023

Work in progress | 0% Completed

Pre final bill 12 is preparing, Jamal sir and Sethumadavan sir visited at site .D/s L/S stopped RR work completed

Rahees P
Date: 27/03/2023

Work in progress | 0% Completed

Pre final bill 12 is preparing, Jamal sir and Sethumadavan sir visited at site .D/s L/S stopped RR work completed

Rahees P
Date: 27/03/2023

Work in progress | 0% Completed

Pre final bill 12 is preparing, Jamal sir and Sethumadavan sir visited at site .D/s L/S stopped RR work completed

Rahees P
Date: 21/03/2023

Work in progress | 0% Completed

Work almost completed ,solar lights fixed back filling and compacting completed, RR work of stopper D/s completed

Rahees P
Date: 21/03/2023

Work in progress | 0% Completed

Work almost completed ,solar lights fixed back filling and compacting completed, RR work of stopper D/s completed

Rahees P
Date: 21/03/2023

Work in progress | 0% Completed

Work almost completed ,solar lights fixed back filling and compacting completed, RR work of stopper D/s completed

Rahees P
Date: 21/03/2023

Work in progress | 0% Completed

Work almost completed ,solar lights fixed back filling and compacting completed, RR work of stopper D/s completed

Rahees P
Date: 21/03/2023

Work in progress | 0% Completed

Work almost completed ,solar lights fixed back filling and compacting completed, RR work of stopper D/s completed

Rahees P
Date: 13/03/2023

Work in progress | 0% Completed

Tiling on bathroom finished, Back filling completed ,Ramp concreted,stair finished

Rahees P
Date: 13/03/2023

Work in progress | 0% Completed

Tiling on bathroom finished, Back filling completed ,Ramp concreted,stair finished

Rahees P
Date: 13/03/2023

Work in progress | 0% Completed

Tiling on bathroom finished, Back filling completed ,Ramp concreted,stair finished

Rahees P
Date: 13/03/2023

Work in progress | 0% Completed

Tiling on bathroom finished, Back filling completed ,Ramp concreted,stair finished

Rahees P
Date: 13/03/2023

Work in progress | 0% Completed

Tiling on bathroom finished, Back filling completed ,Ramp concreted,stair finished

Rahees P
Date: 01/03/2023

Work in progress | 0% Completed

Retaining wall completed and painting and finishing also completed.removing of earth from river is progressing

Rahees P
Date: 01/03/2023

Work in progress | 0% Completed

Retaining wall completed and painting and finishing also completed.removing of earth from river is progressing

Rahees P
Date: 01/03/2023

Work in progress | 0% Completed

Retaining wall completed and painting and finishing also completed.removing of earth from river is progressing

Rahees P
Date: 01/03/2023

Work in progress | 0% Completed

Retaining wall completed and painting and finishing also completed.removing of earth from river is progressing

Rahees P
Date: 01/03/2023

Work in progress | 0% Completed

Retaining wall completed and painting and finishing also completed.removing of earth from river is progressing

Rahees P
Date: 20/02/2023

Work in progress | 0% Completed

Painting work ongoing,rubble retaining wall work progressing, shutter sealant checking completed

Rahees P
Date: 20/02/2023

Work in progress | 0% Completed

Painting work ongoing,rubble retaining wall work progressing, shutter sealant checking completed

Rahees P
Date: 20/02/2023

Work in progress | 0% Completed

Painting work ongoing,rubble retaining wall work progressing, shutter sealant checking completed

Rahees P
Date: 20/02/2023

Work in progress | 0% Completed

Painting work ongoing,rubble retaining wall work progressing, shutter sealant checking completed

Rahees P
Date: 20/02/2023

Work in progress | 0% Completed

Painting work ongoing,rubble retaining wall work progressing, shutter sealant checking completed

Rahees P
Date: 13/02/2023

Work in progress | 0% Completed

Retaining wall with rubble work progressing,painting work ongoing RE work started

Rahees P
Date: 13/02/2023

Work in progress | 0% Completed

Retaining wall with rubble work progressing,painting work ongoing RE work started

Rahees P
Date: 13/02/2023

Work in progress | 0% Completed

Retaining wall with rubble work progressing,painting work ongoing RE work started

Rahees P
Date: 13/02/2023

Work in progress | 0% Completed

Retaining wall with rubble work progressing,painting work ongoing RE work started

Rahees P
Date: 13/02/2023

Work in progress | 0% Completed

Retaining wall with rubble work progressing,painting work ongoing RE work started

Rahees P
Date: 06/02/2023

Work in progress | 0% Completed

Retaining wall RR work progressing.painting work just started. Mechanical and electrical work progressing

Rahees P
Date: 06/02/2023

Work in progress | 0% Completed

Retaining wall RR work progressing.painting work just started. Mechanical and electrical work progressing

Rahees P
Date: 06/02/2023

Work in progress | 0% Completed

Retaining wall RR work progressing.painting work just started. Mechanical and electrical work progressing

Rahees P
Date: 06/02/2023

Work in progress | 0% Completed

Retaining wall RR work progressing.painting work just started. Mechanical and electrical work progressing

Rahees P
Date: 06/02/2023

Work in progress | 0% Completed

Retaining wall RR work progressing.painting work just started. Mechanical and electrical work progressing

Rahees P
Date: 30/01/2023

Work in progress | 0% Completed

Balance 22 m of retaining wall work started,first 11m Dry Rubble masonry work finished and belt work ongoing.also painting work and finishing works ongoing

Rahees P
Date: 30/01/2023

Work in progress | 0% Completed

Balance 22 m of retaining wall work started,first 11m Dry Rubble masonry work finished and belt work ongoing.also painting work and finishing works ongoing

Rahees P
Date: 30/01/2023

Work in progress | 0% Completed

Balance 22 m of retaining wall work started,first 11m Dry Rubble masonry work finished and belt work ongoing.also painting work and finishing works ongoing

Rahees P
Date: 30/01/2023

Work in progress | 0% Completed

Balance 22 m of retaining wall work started,first 11m Dry Rubble masonry work finished and belt work ongoing.also painting work and finishing works ongoing

Rahees P
Date: 30/01/2023

Work in progress | 0% Completed

Balance 22 m of retaining wall work started,first 11m Dry Rubble masonry work finished and belt work ongoing.also painting work and finishing works ongoing

Rahees P
Date: 23/01/2023

Work in progress | 0% Completed

Balance retaining wall foundation work ongoing,Backfilling progressing, Electrical work progressing

Rahees P
Date: 23/01/2023

Work in progress | 0% Completed

Balance retaining wall foundation work ongoing,Backfilling progressing, Electrical work progressing

Rahees P
Date: 23/01/2023

Work in progress | 0% Completed

Balance retaining wall foundation work ongoing,Backfilling progressing, Electrical work progressing

Rahees P
Date: 23/01/2023

Work in progress | 0% Completed

Balance retaining wall foundation work ongoing,Backfilling progressing, Electrical work progressing

Rahees P
Date: 23/01/2023

Work in progress | 0% Completed

Balance retaining wall foundation work ongoing,Backfilling progressing, Electrical work progressing

Rahees P
Date: 15/01/2023

Work in progress | 0% Completed

Balance 20 m retaining work- ring bund Constructed.shutter painting ongoing.guard room finishing work ongoing

Rahees P
Date: 15/01/2023

Work in progress | 0% Completed

Balance 20 m retaining work- ring bund Constructed.shutter painting ongoing.guard room finishing work ongoing

Rahees P
Date: 15/01/2023

Work in progress | 0% Completed

Balance 20 m retaining work- ring bund Constructed.shutter painting ongoing.guard room finishing work ongoing

Rahees P
Date: 15/01/2023

Work in progress | 0% Completed

Balance 20 m retaining work- ring bund Constructed.shutter painting ongoing.guard room finishing work ongoing

Rahees P
Date: 15/01/2023

Work in progress | 0% Completed

Balance 20 m retaining work- ring bund Constructed.shutter painting ongoing.guard room finishing work ongoing

Rahees P
Date: 06/01/2023

Work in progress | 0% Completed

Painting on shutter ongoing,Guard room doors and windows fixed also Gabion box fixing ongoing

Rahees P
Date: 06/01/2023

Work in progress | 0% Completed

Painting on shutter ongoing,Guard room doors and windows fixed also Gabion box fixing ongoing

Rahees P
Date: 06/01/2023

Work in progress | 0% Completed

Painting on shutter ongoing,Guard room doors and windows fixed also Gabion box fixing ongoing

Rahees P
Date: 06/01/2023

Work in progress | 0% Completed

Painting on shutter ongoing,Guard room doors and windows fixed also Gabion box fixing ongoing

Rahees P
Date: 06/01/2023

Work in progress | 0% Completed

Painting on shutter ongoing,Guard room doors and windows fixed also Gabion box fixing ongoing

Rahees P
Date: 03/01/2023

Work in progress | 0% Completed

Painting work started and electrical work is ongoing. Alignment clearing of hoisting bridge is progressing.

Rahees P
Date: 03/01/2023

Work in progress | 0% Completed

Painting work started and electrical work is ongoing. Alignment clearing of hoisting bridge is progressing.

Rahees P
Date: 03/01/2023

Work in progress | 0% Completed

Painting work started and electrical work is ongoing. Alignment clearing of hoisting bridge is progressing.

Rahees P
Date: 03/01/2023

Work in progress | 0% Completed

Painting work started and electrical work is ongoing. Alignment clearing of hoisting bridge is progressing.

Rahees P
Date: 03/01/2023

Work in progress | 0% Completed

Painting work started and electrical work is ongoing. Alignment clearing of hoisting bridge is progressing.

Rahees P
Date: 26/12/2022

Work in progress | 0% Completed

Gate erection completed (4/4)

Rahees P
Date: 26/12/2022

Work in progress | 0% Completed

Gate erection completed (4/4)

Rahees P
Date: 26/12/2022

Work in progress | 0% Completed

Gate erection completed (4/4)

Rahees P
Date: 26/12/2022

Work in progress | 0% Completed

Gate erection completed (4/4)

Rahees P
Date: 26/12/2022

Work in progress | 0% Completed

Gate erection completed (4/4)

Rahees P
Date: 19/12/2022

Work in progress | 0% Completed

Erecting ramp work ongoing and finished the platform end.

Rahees P
Date: 19/12/2022

Work in progress | 0% Completed

Erecting ramp work ongoing and finished the platform end.

Rahees P
Date: 19/12/2022

Work in progress | 0% Completed

Erecting ramp work ongoing and finished the platform end.

Rahees P
Date: 19/12/2022

Work in progress | 0% Completed

Erecting ramp work ongoing and finished the platform end.

Rahees P
Date: 19/12/2022

Work in progress | 0% Completed

Erecting ramp work ongoing and finished the platform end.

Rahees P
Date: 16/12/2022

Work in progress | 0% Completed

Ramp work almost completed and platform creating for the smooth erection purpose

Rahees P
Date: 16/12/2022

Work in progress | 0% Completed

Ramp work almost completed and platform creating for the smooth erection purpose

Rahees P
Date: 16/12/2022

Work in progress | 0% Completed

Ramp work almost completed and platform creating for the smooth erection purpose

Rahees P
Date: 16/12/2022

Work in progress | 0% Completed

Ramp work almost completed and platform creating for the smooth erection purpose

Rahees P
Date: 16/12/2022

Work in progress | 0% Completed

Ramp work almost completed and platform creating for the smooth erection purpose

Rahees P
Date: 15/12/2022

Work in progress | 0% Completed

Guard room flooring finished by cement concrete flooring.Ramp work progressing for erection of shutter

Rahees P
Date: 15/12/2022

Work in progress | 0% Completed

Guard room flooring finished by cement concrete flooring.Ramp work progressing for erection of shutter

Rahees P
Date: 15/12/2022

Work in progress | 0% Completed

Guard room flooring finished by cement concrete flooring.Ramp work progressing for erection of shutter

Rahees P
Date: 15/12/2022

Work in progress | 0% Completed

Guard room flooring finished by cement concrete flooring.Ramp work progressing for erection of shutter

Rahees P
Date: 15/12/2022

Work in progress | 0% Completed

Guard room flooring finished by cement concrete flooring.Ramp work progressing for erection of shutter

Rahees P
Date: 12/12/2022

Work in progress | 0% Completed

Ramp construction for erection of gate is ongoing And also heavy raining ocured

Rahees P
Date: 12/12/2022

Work in progress | 0% Completed

Due to heavy rain at site ring bund and ramp for erecting work destroyed

Rahees P
Date: 12/12/2022

Work in progress | 0% Completed

Due to heavy rain at site ring bund and ramp for erecting work destroyed

Rahees P
Date: 12/12/2022

Work in progress | 0% Completed

Due to heavy rain at site ring bund and ramp for erecting work destroyed

Rahees P
Date: 12/12/2022

Work in progress | 0% Completed

Due to heavy rain at site ring bund and ramp for erecting work destroyed

Rahees P
Date: 12/12/2022

Work in progress | 0% Completed

Due to heavy rain at site ring bund and ramp for erecting work destroyed

Rahees P
Date: 12/12/2022

Work in progress | 0% Completed

Ramp construction for erection of gate is ongoing And also heavy raining ocured

Rahees P
Date: 12/12/2022

Work in progress | 0% Completed

Ramp construction for erection of gate is ongoing And also heavy raining ocured

Rahees P
Date: 12/12/2022

Work in progress | 0% Completed

Ramp construction for erection of gate is ongoing And also heavy raining ocured

Rahees P
Date: 12/12/2022

Work in progress | 0% Completed

Ramp construction for erection of gate is ongoing And also heavy raining ocured

Rahees P
Date: 02/12/2022

Work in progress | 0% Completed

River flow just diverted on two sill beam for construction of ring bund for mechanical shutter erection

Rahees P
Date: 02/12/2022

Work in progress | 0% Completed

River flow just diverted on two sill beam for construction of ring bund for mechanical shutter erection

Rahees P
Date: 02/12/2022

Work in progress | 0% Completed

River flow just diverted on two sill beam for construction of ring bund for mechanical shutter erection

Rahees P
Date: 02/12/2022

Work in progress | 0% Completed

River flow just diverted on two sill beam for construction of ring bund for mechanical shutter erection

Rahees P
Date: 02/12/2022

Work in progress | 0% Completed

River flow just diverted on two sill beam for construction of ring bund for mechanical shutter erection

Rahees P
Date: 24/11/2022

Work in progress | 95% Completed

for constructing gravity wall left side upstream side balance 22m work ring bund started.but due to some issues rised by the nearest land owner ,work temporarily stopped.

Rahees P
Date: 24/11/2022

Work in progress | 95% Completed

for constructing gravity wall left side upstream side balance 22m work ring bund started.but due to some issues rised by the nearest land owner ,work temporarily stopped.

Rahees P
Date: 24/11/2022

Work in progress | 95% Completed

for constructing gravity wall left side upstream side balance 22m work ring bund started.but due to some issues rised by the nearest land owner ,work temporarily stopped.

Rahees P
Date: 24/11/2022

Work in progress | 95% Completed

for constructing gravity wall left side upstream side balance 22m work ring bund started.but due to some issues rised by the nearest land owner ,work temporarily stopped.

Rahees P
Date: 24/11/2022

Work in progress | 95% Completed

for constructing gravity wall left side upstream side balance 22m work ring bund started.but due to some issues rised by the nearest land owner ,work temporarily stopped.

Rahees P
Date: 01/11/2022

Work in progress | 82% Completed

Plastering work front and two sides completed KIIFB inspection carried out on29th October

Rahees P
Date: 01/11/2022

Work in progress | 82% Completed

Plastering work front and two sides completed KIIFB inspection carried out on29th October

Rahees P
Date: 01/11/2022

Work in progress | 82% Completed

Plastering work front and two sides completed KIIFB inspection carried out on29th October

Rahees P
Date: 01/11/2022

Work in progress | 82% Completed

Plastering work front and two sides completed KIIFB inspection carried out on29th October

Rahees P
Date: 01/11/2022

Work in progress | 82% Completed

Plastering work front and two sides completed KIIFB inspection carried out on29th October

Rahees P
Date: 25/10/2022

Work in progress | 95% Completed

eft side upstream side 20m balance work will start only after the water level decrease in river.

Rahees P
Date: 25/10/2022

Work in progress | 95% Completed

eft side upstream side 20m balance work will start only after the water level decrease in river.

Rahees P
Date: 25/10/2022

Work in progress | 95% Completed

eft side upstream side 20m balance work will start only after the water level decrease in river.

Rahees P
Date: 25/10/2022

Work in progress | 95% Completed

eft side upstream side 20m balance work will start only after the water level decrease in river.

Rahees P
Date: 25/10/2022

Work in progress | 95% Completed

eft side upstream side 20m balance work will start only after the water level decrease in river.

Rahees P
Date: 25/10/2022

Work in progress | 90% Completed

only erection and fixing of shutter and hoisting platform work pending

Rahees P
Date: 25/10/2022

Work in progress | 90% Completed

only erection and fixing of shutter and hoisting platform work pending

Rahees P
Date: 25/10/2022

Work in progress | 90% Completed

only erection and fixing of shutter and hoisting platform work pending

Rahees P
Date: 25/10/2022

Work in progress | 90% Completed

only erection and fixing of shutter and hoisting platform work pending

Rahees P
Date: 25/10/2022

Work in progress | 90% Completed

only erection and fixing of shutter and hoisting platform work pending

Rahees P
Date: 25/10/2022

Work in progress | 93% Completed

left side upstream side 20m balance work will start only after the water level decrease in river.

Rahees P
Date: 25/10/2022

Work in progress | 93% Completed

left side upstream side 20m balance work will start only after the water level decrease in river.

Rahees P
Date: 25/10/2022

Work in progress | 93% Completed

left side upstream side 20m balance work will start only after the water level decrease in river.

Rahees P
Date: 25/10/2022

Work in progress | 93% Completed

left side upstream side 20m balance work will start only after the water level decrease in river.

Rahees P
Date: 25/10/2022

Work in progress | 93% Completed

left side upstream side 20m balance work will start only after the water level decrease in river.

Rahees P
Date: 25/10/2022

Work in progress | 98% Completed

only P4- Secondary concrete pending.

Rahees P
Date: 25/10/2022

Work in progress | 98% Completed

only P4- Secondary concrete pending.

Rahees P
Date: 25/10/2022

Work in progress | 98% Completed

only P4- Secondary concrete pending.

Rahees P
Date: 25/10/2022

Work in progress | 98% Completed

only P4- Secondary concrete pending.

Rahees P
Date: 25/10/2022

Work in progress | 98% Completed

only P4- Secondary concrete pending.

Rahees P
Date: 25/10/2022

Work in progress | 80% Completed

plastering work ongoing -50% completed

Rahees P
Date: 25/10/2022

Work in progress | 80% Completed

plastering work ongoing -50% completed

Rahees P
Date: 25/10/2022

Work in progress | 80% Completed

plastering work ongoing -50% completed

Rahees P
Date: 25/10/2022

Work in progress | 80% Completed

plastering work ongoing -50% completed

Rahees P
Date: 25/10/2022

Work in progress | 80% Completed

plastering work ongoing -50% completed

Rahees P
Date: 10/10/2022

Work in progress | 0% Completed

Heavy rain occurred at site.water level increased 30 cm rised. guard room electrical work started.

Rahees P
Date: 10/10/2022

Work in progress | 0% Completed

Heavy rain occurred at site.water level increased 30 cm rised. guard room electrical work started.

Rahees P
Date: 10/10/2022

Work in progress | 0% Completed

Heavy rain occurred at site.water level increased 30 cm rised. guard room electrical work started.

Rahees P
Date: 10/10/2022

Work in progress | 0% Completed

Heavy rain occurred at site.water level increased 30 cm rised. guard room electrical work started.

Rahees P
Date: 10/10/2022

Work in progress | 0% Completed

Heavy rain occurred at site.water level increased 30 cm rised. guard room electrical work started.

Rahees P
Date: 03/10/2022

Work in progress | 0% Completed

NO OTHER PROGRESS IN WORK DUE TO WATER LEVEL NOT REDUCED.SECURITY ROOM WORK STOPPED, ELECTRICAL CONDUIT CONCEALED WORK WILL START NEXT WEEK ONWARDS.REVISED ESTIMATE IS UNDER APPROVAL AT OFFICE.

Rahees P
Date: 03/10/2022

Work in progress | 0% Completed

NO OTHER PROGRESS IN WORK DUE TO WATER LEVEL NOT REDUCED.SECURITY ROOM WORK STOPPED, ELECTRICAL CONDUIT CONCEALED WORK WILL START NEXT WEEK ONWARDS.REVISED ESTIMATE IS UNDER APPROVAL AT OFFICE.

Rahees P
Date: 03/10/2022

Work in progress | 0% Completed

NO OTHER PROGRESS IN WORK DUE TO WATER LEVEL NOT REDUCED.SECURITY ROOM WORK STOPPED, ELECTRICAL CONDUIT CONCEALED WORK WILL START NEXT WEEK ONWARDS.REVISED ESTIMATE IS UNDER APPROVAL AT OFFICE.

Rahees P
Date: 03/10/2022

Work in progress | 0% Completed

NO OTHER PROGRESS IN WORK DUE TO WATER LEVEL NOT REDUCED.SECURITY ROOM WORK STOPPED, ELECTRICAL CONDUIT CONCEALED WORK WILL START NEXT WEEK ONWARDS.REVISED ESTIMATE IS UNDER APPROVAL AT OFFICE.

Rahees P
Date: 03/10/2022

Work in progress | 0% Completed

NO OTHER PROGRESS IN WORK DUE TO WATER LEVEL NOT REDUCED.SECURITY ROOM WORK STOPPED, ELECTRICAL CONDUIT CONCEALED WORK WILL START NEXT WEEK ONWARDS.REVISED ESTIMATE IS UNDER APPROVAL AT OFFICE.

Rahees P
Date: 29/09/2022

Work in progress | 0% Completed

no further work is done at site.water level reduced only 10 cm in river.plastering of guard room will start after the completion of concealed electrical pipe fitting.arranged a meeting of electrical engineers on after 30/9/22.total station carried for the level checking which already established BM at site.(from payyanad stadium to site).

Rahees P
Date: 29/09/2022

Work in progress | 0% Completed

no further work is done at site.water level reduced only 10 cm in river.plastering of guard room will start after the completion of concealed electrical pipe fitting.arranged a meeting of electrical engineers on after 30/9/22.total station carried for the level checking which already established BM at site.(from payyanad stadium to site).

Rahees P
Date: 29/09/2022

Work in progress | 0% Completed

no further work is done at site.water level reduced only 10 cm in river.plastering of guard room will start after the completion of concealed electrical pipe fitting.arranged a meeting of electrical engineers on after 30/9/22.total station carried for the level checking which already established BM at site.(from payyanad stadium to site).

Rahees P
Date: 29/09/2022

Work in progress | 0% Completed

no further work is done at site.water level reduced only 10 cm in river.plastering of guard room will start after the completion of concealed electrical pipe fitting.arranged a meeting of electrical engineers on after 30/9/22.total station carried for the level checking which already established BM at site.(from payyanad stadium to site).

Rahees P
Date: 29/09/2022

Work in progress | 0% Completed

no further work is done at site.water level reduced only 10 cm in river.plastering of guard room will start after the completion of concealed electrical pipe fitting.arranged a meeting of electrical engineers on after 30/9/22.total station carried for the level checking which already established BM at site.(from payyanad stadium to site).

Anu IT Admin
Date: 22/09/2022

Work in progress | 0% Completed

Regulator portion civil work completed. only P1 secondary concrete pending. Right side retaining wall fully completed (160m/160m). Left side retaining wall 20m out of 163m is pending. Regulator portion and retaining wall work paused due to heavy flow of water in river. Guard room construction civil structural work completed. laid roof sheet and plastering work to be started. Electrical drawing finalised, work will start after completion of guardroom plastering. Mechanical shutters are constructed and ready to erect.

Anu IT Admin
Date: 22/09/2022

Work in progress | 0% Completed

Regulator portion civil work completed. only P1 secondary concrete pending. Right side retaining wall fully completed (160m/160m). Left side retaining wall 20m out of 163m is pending. Regulator portion and retaining wall work paused due to heavy flow of water in river. Guard room construction civil structural work completed. laid roof sheet and plastering work to be started. Electrical drawing finalised, work will start after completion of guardroom plastering. Mechanical shutters are constructed and ready to erect.

Anu IT Admin
Date: 22/09/2022

Work in progress | 0% Completed

Regulator portion civil work completed. only P1 secondary concrete pending. Right side retaining wall fully completed (160m/160m). Left side retaining wall 20m out of 163m is pending. Regulator portion and retaining wall work paused due to heavy flow of water in river. Guard room construction civil structural work completed. laid roof sheet and plastering work to be started. Electrical drawing finalised, work will start after completion of guardroom plastering. Mechanical shutters are constructed and ready to erect.

Anu IT Admin
Date: 22/09/2022

Work in progress | 0% Completed

Regulator portion civil work completed. only P1 secondary concrete pending. Right side retaining wall fully completed (160m/160m). Left side retaining wall 20m out of 163m is pending. Regulator portion and retaining wall work paused due to heavy flow of water in river. Guard room construction civil structural work completed. laid roof sheet and plastering work to be started. Electrical drawing finalised, work will start after completion of guardroom plastering. Mechanical shutters are constructed and ready to erect.

Anu IT Admin
Date: 22/09/2022

Work in progress | 0% Completed

Regulator portion civil work completed. only P1 secondary concrete pending. Right side retaining wall fully completed (160m/160m). Left side retaining wall 20m out of 163m is pending. Regulator portion and retaining wall work paused due to heavy flow of water in river. Guard room construction civil structural work completed. laid roof sheet and plastering work to be started. Electrical drawing finalised, work will start after completion of guardroom plastering. Mechanical shutters are constructed and ready to erect.