Joel J Varghese |
Date: 20/11/2023 |
Work has been completed | 100% Completed
ITI KOYILANDY|100% Completed
Works completed.Issue raised by ITI Principal rectification pending. Final RE not approved Final Bill not submitted
Joel J Varghese |
Date: 18/09/2023 |
Work has been completed | 100% Completed
ITI KOYILANDY|100% Completed
Completed
Joel J Varghese |
Date: 09/05/2023 |
Work has been completed | 100% Completed
ITI KOYILANDY|100% Completed
Site has been handed over to ITI
Vishnu R |
Date: 29/04/2023 |
Vishnu R |
Date: 11/04/2023 |
Vishnu R |
Date: 27/03/2023 |
Work in progress | 99% Completed
ITI KOYILANDY|100% Completed
99% of works completed,only water proofing works pending
Vishnu R |
Date: 27/02/2023 |
Vishnu R |
Date: 20/02/2023 |
Vishnu R |
Date: 13/02/2023 |
Vishnu R |
Date: 06/02/2023 |
Vishnu R |
Date: 30/01/2023 |
Vishnu R |
Date: 23/01/2023 |
Vishnu R |
Date: 16/01/2023 |
Vishnu R |
Date: 09/01/2023 |
Vishnu R |
Date: 03/01/2023 |
Vishnu R |
Date: 26/12/2022 |
Vishnu R |
Date: 19/12/2022 |
Vishnu R |
Date: 12/12/2022 |
Vishnu R |
Date: 06/12/2022 |
Vishnu R |
Date: 05/12/2022 |
Vishnu R |
Date: 30/11/2022 |
Vishnu R |
Date: 21/11/2022 |
Vishnu R |
Date: 31/10/2022 |
Vishnu R |
Date: 18/10/2022 |
Vishnu R |
Date: 10/10/2022 |
Work in progress | 85% Completed
ITI KOYILANDY|100% Completed
PVC septic tank instalation Soakpi- Solid block Soapit slab concrete Rain water tank bottom slab concrete Wall 1st lift concrete Retaing wall using RR masonry,Plumbing external piping work sewage line,Electrical external cable laying works
Attached images
Vishnu R |
Date: 03/10/2022 |
Work in progress | 85% Completed
ITI KOYILANDY|100% Completed
Physical progress - 85% Civil - 80 % Electrical - 65% HVAC- 0% Current sttus: RR masonry for RW wall around main building. Soak pit- earth work and solid block work in progress. UG tank - steel reinforcement work for base slab. Main bulding -electrical work.
Attached images
Date: 24/09/2022 |
Work in progress | 85% Completed
ITI KOYILANDY|100% Completed
work resumed. earth work and pcc for septic tank compound wall-earth work and pcc for foundation
Date: 19/09/2022 |
Work in progress | 85% Completed
ITI KOYILANDY|100% Completed
work has resumes.electrical work in progress and civil work has arranged to start