Joel J Varghese
Date: 20/11/2023

Work has been completed | 100% Completed

100.00% ITI KOYILANDY|100% Completed

Works completed.Issue raised by ITI Principal rectification pending. Final RE not approved Final Bill not submitted

Joel J Varghese
Date: 18/09/2023

Work has been completed | 100% Completed

100.00% ITI KOYILANDY|100% Completed

Completed

Joel J Varghese
Date: 09/05/2023

Work has been completed | 100% Completed

100.00% ITI KOYILANDY|100% Completed

Site has been handed over to ITI

Vishnu R
Date: 29/04/2023

Work has been completed | 100% Completed

100.00% ITI KOYILANDY|100% Completed

work completed and site handover to the KASE

Attached images

img

Vishnu R
Date: 11/04/2023

Work in progress | 99% Completed

100.00% ITI KOYILANDY|100% Completed

99 % of work completed and only water proofing work pending

Attached images

img img

Vishnu R
Date: 27/03/2023

Work in progress | 99% Completed

100.00% ITI KOYILANDY|100% Completed

99% of works completed,only water proofing works pending

Vishnu R
Date: 27/02/2023

Work in progress | 99% Completed

100.00% ITI KOYILANDY|100% Completed

civil and fire works completed,Electrical 99% completed,ELV 95 % completed

Attached images

img img

Vishnu R
Date: 20/02/2023

Work in progress | 99% Completed

100.00% ITI KOYILANDY|100% Completed

civil and fire works completed,Electrical 99% completed,ELV 95 % completed

Attached images

img img

Vishnu R
Date: 13/02/2023

Work in progress | 99% Completed

100.00% ITI KOYILANDY|100% Completed

civil and fire works completed,Electrical 99% completed,ELV 95 % completed

Attached images

img img

Vishnu R
Date: 06/02/2023

Work in progress | 99% Completed

100.00% ITI KOYILANDY|100% Completed

civil and fire works completed,Electrical 98% completed,ELV 92 % completed

Attached images

img img img

Vishnu R
Date: 30/01/2023

Work in progress | 99% Completed

100.00% ITI KOYILANDY|100% Completed

civil and fire works completed,Electrical 98% completed,ELV 90 % completed

Attached images

img

Vishnu R
Date: 23/01/2023

Work in progress | 99% Completed

100.00% ITI KOYILANDY|100% Completed

civil and fire works completed,Electrical 98% completed,ELV 90 % completed

Attached images

img

Vishnu R
Date: 16/01/2023

Work in progress | 98% Completed

100.00% ITI KOYILANDY|100% Completed

Door fittings and HVAC and ELV work is in progress

Attached images

img img img

Vishnu R
Date: 09/01/2023

Work in progress | 98% Completed

100.00% ITI KOYILANDY|100% Completed

Door fittings and HVAC and ELV work is in progress

Attached images

img img img img img img

Vishnu R
Date: 03/01/2023

Work in progress | 98% Completed

100.00% ITI KOYILANDY|100% Completed

HVAC ,Electrical and ELV work on progress,sanitary item and door fitting works pending

Attached images

img img img img img img

Vishnu R
Date: 26/12/2022

Work in progress | 97% Completed

100.00% ITI KOYILANDY|100% Completed

Electrical and ELV works ongoing , handrail work for ramp completed , seminar hall HVAC work ongoing sanitary fittings ongoing

Attached images

img img img

Vishnu R
Date: 19/12/2022

Work in progress | 96% Completed

100.00% ITI KOYILANDY|100% Completed

Electrical work ,Handrail work for ramp ,Seminar hall - HVAC work , Name board fixing work, Sanitary works Main Building Civil works – 95% Main Building Electrical works – 95% Main Building ELV Works - 85%

Attached images

img img

Vishnu R
Date: 12/12/2022

Work in progress | 96% Completed

100.00% ITI KOYILANDY|100% Completed

Seminar hall - HVAC work , Name board fixing work, Sanitary works and electrical works are going on the site

Attached images

img img img img img

Vishnu R
Date: 06/12/2022

Work in progress | 95% Completed

100.00% ITI KOYILANDY|100% Completed

HVAC work for seminar hall,MEP work ,Sanitary fittings work on progress at site

GPS Cordinates

Latitude : 11.4429567

Longitude : 75.7235584

Accuracy : 64.0999984741211

Attached images

img img img img img img img img img

Vishnu R
Date: 05/12/2022

Work in progress | 95% Completed

100.00% ITI KOYILANDY|100% Completed

Electrical work-95% completed,Mechanical (HVAC and Fire)-80% completed Current status Plumbing sanitary works ongoing HVAC work on going Fire piping work completed

Attached images

img img img img img img img img

Vishnu R
Date: 30/11/2022

Work in progress | 94% Completed

100.00% ITI KOYILANDY|100% Completed

HVAC works, Electrical works ,sanitary items fittings are progress on the site

Attached images

img img img

Vishnu R
Date: 21/11/2022

Work in progress | 93% Completed

100.00% ITI KOYILANDY|100% Completed

Electrical works ,Plumbing works, Bathroom works are in progress, Road works completed

Attached images

img img img

Vishnu R
Date: 31/10/2022

Work in progress | 90% Completed

100.00% ITI KOYILANDY|100% Completed

Belt above retaining wall -concretework Plumbing Trenching for Rain water line Manhole Ele - strip laying for earthing, Leveling works for roads

Attached images

img img img

Vishnu R
Date: 18/10/2022

Work in progress | 0% Completed

100.00% ITI KOYILANDY|100% Completed

RW tank top slab -shuttering Electrical lightning arrester strip laying MEP plumbing line connection

GPS Cordinates

Latitude : 8.4926508

Longitude : 76.9297242

Accuracy : 1026.645752425567

Attached images

img img img img

Vishnu R
Date: 10/10/2022

Work in progress | 85% Completed

100.00% ITI KOYILANDY|100% Completed

PVC septic tank instalation Soakpi- Solid block Soapit slab concrete Rain water tank bottom slab concrete Wall 1st lift concrete Retaing wall using RR masonry,Plumbing external piping work sewage line,Electrical external cable laying works

Attached images

img img img img

Vishnu R
Date: 03/10/2022

Work in progress | 85% Completed

100.00% ITI KOYILANDY|100% Completed

Physical progress - 85% Civil - 80 % Electrical - 65% HVAC- 0% Current sttus: RR masonry for RW wall around main building. Soak pit- earth work and solid block work in progress. UG tank - steel reinforcement work for base slab. Main bulding -electrical work.

Attached images

img img img img img

Date: 24/09/2022

Work in progress | 85% Completed

100.00% ITI KOYILANDY|100% Completed

work resumed. earth work and pcc for septic tank compound wall-earth work and pcc for foundation

Date: 19/09/2022

Work in progress | 85% Completed

100.00% ITI KOYILANDY|100% Completed

work has resumes.electrical work in progress and civil work has arranged to start

Joel J Varghese
Date: 20/11/2023

Work has been completed | 0% Completed

Works completed.Issue raised by ITI Principal rectification pending. Final RE not approved Final Bill not submitted

Joel J Varghese
Date: 20/11/2023

Work has been completed | 0% Completed

Works completed.Issue raised by ITI Principal rectification pending. Final RE not approved Final Bill not submitted

Joel J Varghese
Date: 20/11/2023

Work has been completed | 0% Completed

Works completed.Issue raised by ITI Principal rectification pending. Final RE not approved Final Bill not submitted

Joel J Varghese
Date: 20/11/2023

Work has been completed | 0% Completed

Works completed.Issue raised by ITI Principal rectification pending. Final RE not approved Final Bill not submitted

Joel J Varghese
Date: 18/09/2023

Work has been completed | 0% Completed

Completed

Joel J Varghese
Date: 18/09/2023

Work has been completed | 0% Completed

Completed

Joel J Varghese
Date: 18/09/2023

Work has been completed | 0% Completed

Completed

Joel J Varghese
Date: 18/09/2023

Work has been completed | 0% Completed

Completed

Joel J Varghese
Date: 09/05/2023

Work has been completed | 0% Completed

Site has been handed over to ITI

Joel J Varghese
Date: 09/05/2023

Work has been completed | 0% Completed

Site has been handed over to ITI

Joel J Varghese
Date: 09/05/2023

Work has been completed | 0% Completed

Site has been handed over to ITI

Joel J Varghese
Date: 09/05/2023

Work has been completed | 0% Completed

Site has been handed over to ITI

Vishnu R
Date: 29/04/2023

Work has been completed | 0% Completed

work completed and site handover to the KASE

Attached images

img

Vishnu R
Date: 29/04/2023

Work has been completed | 0% Completed

work completed and site handover to the KASE

Attached images

img

Vishnu R
Date: 29/04/2023

Work has been completed | 0% Completed

work completed and site handover to the KASE

Attached images

img

Vishnu R
Date: 29/04/2023

Work has been completed | 0% Completed

work completed and site handover to the KASE

Attached images

img

Vishnu R
Date: 11/04/2023

Work in progress | 0% Completed

99 % of work completed and only water proofing work pending

Attached images

img img

Vishnu R
Date: 11/04/2023

Work in progress | 0% Completed

99 % of work completed and only water proofing work pending

Attached images

img img

Vishnu R
Date: 11/04/2023

Work in progress | 0% Completed

99 % of work completed and only water proofing work pending

Attached images

img img

Vishnu R
Date: 11/04/2023

Work in progress | 0% Completed

99 % of work completed and only water proofing work pending

Attached images

img img

Vishnu R
Date: 27/03/2023

Work in progress | 0% Completed

99% of works completed,only water proofing works pending

Vishnu R
Date: 27/03/2023

Work in progress | 0% Completed

99% of works completed,only water proofing works pending

Vishnu R
Date: 27/03/2023

Work in progress | 0% Completed

99% of works completed,only water proofing works pending

Vishnu R
Date: 27/03/2023

Work in progress | 0% Completed

99% of works completed,only water proofing works pending

Vishnu R
Date: 27/02/2023

Work in progress | 0% Completed

civil and fire works completed,Electrical 99% completed,ELV 95 % completed

Attached images

img img

Vishnu R
Date: 27/02/2023

Work in progress | 0% Completed

civil and fire works completed,Electrical 99% completed,ELV 95 % completed

Attached images

img img

Vishnu R
Date: 27/02/2023

Work in progress | 0% Completed

civil and fire works completed,Electrical 99% completed,ELV 95 % completed

Attached images

img img

Vishnu R
Date: 27/02/2023

Work in progress | 0% Completed

civil and fire works completed,Electrical 99% completed,ELV 95 % completed

Attached images

img img

Vishnu R
Date: 20/02/2023

Work in progress | 0% Completed

civil and fire works completed,Electrical 99% completed,ELV 95 % completed

Attached images

img img

Vishnu R
Date: 20/02/2023

Work in progress | 0% Completed

civil and fire works completed,Electrical 99% completed,ELV 95 % completed

Attached images

img img

Vishnu R
Date: 20/02/2023

Work in progress | 0% Completed

civil and fire works completed,Electrical 99% completed,ELV 95 % completed

Attached images

img img

Vishnu R
Date: 20/02/2023

Work in progress | 0% Completed

civil and fire works completed,Electrical 99% completed,ELV 95 % completed

Attached images

img img

Vishnu R
Date: 13/02/2023

Work in progress | 0% Completed

civil and fire works completed,Electrical 99% completed,ELV 95 % completed

Attached images

img img

Vishnu R
Date: 13/02/2023

Work in progress | 0% Completed

civil and fire works completed,Electrical 99% completed,ELV 95 % completed

Attached images

img img

Vishnu R
Date: 13/02/2023

Work in progress | 0% Completed

civil and fire works completed,Electrical 99% completed,ELV 95 % completed

Attached images

img img

Vishnu R
Date: 13/02/2023

Work in progress | 0% Completed

civil and fire works completed,Electrical 99% completed,ELV 95 % completed

Attached images

img img

Vishnu R
Date: 06/02/2023

Work in progress | 0% Completed

civil and fire works completed,Electrical 98% completed,ELV 92 % completed

Attached images

img img img

Vishnu R
Date: 06/02/2023

Work in progress | 0% Completed

civil and fire works completed,Electrical 98% completed,ELV 92 % completed

Attached images

img img img

Vishnu R
Date: 06/02/2023

Work in progress | 0% Completed

civil and fire works completed,Electrical 98% completed,ELV 92 % completed

Attached images

img img img

Vishnu R
Date: 06/02/2023

Work in progress | 0% Completed

civil and fire works completed,Electrical 98% completed,ELV 92 % completed

Attached images

img img img

Vishnu R
Date: 30/01/2023

Work in progress | 0% Completed

civil and fire works completed,Electrical 98% completed,ELV 90 % completed

Attached images

img

Vishnu R
Date: 30/01/2023

Work in progress | 0% Completed

civil and fire works completed,Electrical 98% completed,ELV 90 % completed

Attached images

img

Vishnu R
Date: 30/01/2023

Work in progress | 0% Completed

civil and fire works completed,Electrical 98% completed,ELV 90 % completed

Attached images

img

Vishnu R
Date: 30/01/2023

Work in progress | 0% Completed

civil and fire works completed,Electrical 98% completed,ELV 90 % completed

Attached images

img

Vishnu R
Date: 23/01/2023

Work in progress | 0% Completed

civil and fire works completed,Electrical 98% completed,ELV 90 % completed

Attached images

img

Vishnu R
Date: 23/01/2023

Work in progress | 0% Completed

civil and fire works completed,Electrical 98% completed,ELV 90 % completed

Attached images

img

Vishnu R
Date: 23/01/2023

Work in progress | 0% Completed

civil and fire works completed,Electrical 98% completed,ELV 90 % completed

Attached images

img

Vishnu R
Date: 23/01/2023

Work in progress | 0% Completed

civil and fire works completed,Electrical 98% completed,ELV 90 % completed

Attached images

img

Vishnu R
Date: 16/01/2023

Work in progress | 0% Completed

Door fittings and HVAC and ELV work is in progress

Attached images

img img img

Vishnu R
Date: 16/01/2023

Work in progress | 0% Completed

Door fittings and HVAC and ELV work is in progress

Attached images

img img img

Vishnu R
Date: 16/01/2023

Work in progress | 0% Completed

Door fittings and HVAC and ELV work is in progress

Attached images

img img img

Vishnu R
Date: 16/01/2023

Work in progress | 0% Completed

Door fittings and HVAC and ELV work is in progress

Attached images

img img img

Vishnu R
Date: 09/01/2023

Work in progress | 0% Completed

Door fittings and HVAC and ELV work is in progress

Attached images

img img img img img img

Vishnu R
Date: 09/01/2023

Work in progress | 0% Completed

Door fittings and HVAC and ELV work is in progress

Attached images

img img img img img img

Vishnu R
Date: 09/01/2023

Work in progress | 0% Completed

Door fittings and HVAC and ELV work is in progress

Attached images

img img img img img img

Vishnu R
Date: 09/01/2023

Work in progress | 0% Completed

Door fittings and HVAC and ELV work is in progress

Attached images

img img img img img img

Vishnu R
Date: 03/01/2023

Work in progress | 0% Completed

HVAC ,Electrical and ELV work on progress,sanitary item and door fitting works pending

Attached images

img img img img img img

Vishnu R
Date: 03/01/2023

Work in progress | 0% Completed

HVAC ,Electrical and ELV work on progress,sanitary item and door fitting works pending

Attached images

img img img img img img

Vishnu R
Date: 03/01/2023

Work in progress | 0% Completed

HVAC ,Electrical and ELV work on progress,sanitary item and door fitting works pending

Attached images

img img img img img img

Vishnu R
Date: 03/01/2023

Work in progress | 0% Completed

HVAC ,Electrical and ELV work on progress,sanitary item and door fitting works pending

Attached images

img img img img img img

Vishnu R
Date: 26/12/2022

Work in progress | 0% Completed

Electrical and ELV works ongoing , handrail work for ramp completed , seminar hall HVAC work ongoing sanitary fittings ongoing

Attached images

img img img

Vishnu R
Date: 26/12/2022

Work in progress | 0% Completed

Electrical and ELV works ongoing , handrail work for ramp completed , seminar hall HVAC work ongoing sanitary fittings ongoing

Attached images

img img img

Vishnu R
Date: 26/12/2022

Work in progress | 0% Completed

Electrical and ELV works ongoing , handrail work for ramp completed , seminar hall HVAC work ongoing sanitary fittings ongoing

Attached images

img img img

Vishnu R
Date: 26/12/2022

Work in progress | 0% Completed

Electrical and ELV works ongoing , handrail work for ramp completed , seminar hall HVAC work ongoing sanitary fittings ongoing

Attached images

img img img

Vishnu R
Date: 19/12/2022

Work in progress | 0% Completed

Electrical work ,Handrail work for ramp ,Seminar hall - HVAC work , Name board fixing work, Sanitary works Main Building Civil works – 95% Main Building Electrical works – 95% Main Building ELV Works - 85%

Attached images

img img

Vishnu R
Date: 19/12/2022

Work in progress | 0% Completed

Electrical work ,Handrail work for ramp ,Seminar hall - HVAC work , Name board fixing work, Sanitary works Main Building Civil works – 95% Main Building Electrical works – 95% Main Building ELV Works - 85%

Attached images

img img

Vishnu R
Date: 19/12/2022

Work in progress | 0% Completed

Electrical work ,Handrail work for ramp ,Seminar hall - HVAC work , Name board fixing work, Sanitary works Main Building Civil works – 95% Main Building Electrical works – 95% Main Building ELV Works - 85%

Attached images

img img

Vishnu R
Date: 19/12/2022

Work in progress | 0% Completed

Electrical work ,Handrail work for ramp ,Seminar hall - HVAC work , Name board fixing work, Sanitary works Main Building Civil works – 95% Main Building Electrical works – 95% Main Building ELV Works - 85%

Attached images

img img

Vishnu R
Date: 12/12/2022

Work in progress | 0% Completed

Seminar hall - HVAC work , Name board fixing work, Sanitary works and electrical works are going on the site

Attached images

img img img img img

Vishnu R
Date: 12/12/2022

Work in progress | 0% Completed

Seminar hall - HVAC work , Name board fixing work, Sanitary works and electrical works are going on the site

Attached images

img img img img img

Vishnu R
Date: 12/12/2022

Work in progress | 0% Completed

Seminar hall - HVAC work , Name board fixing work, Sanitary works and electrical works are going on the site

Attached images

img img img img img

Vishnu R
Date: 12/12/2022

Work in progress | 0% Completed

Seminar hall - HVAC work , Name board fixing work, Sanitary works and electrical works are going on the site

Attached images

img img img img img

Vishnu R
Date: 06/12/2022

Work in progress | 0% Completed

HVAC work for seminar hall,MEP work ,Sanitary fittings work on progress at site

Attached images

img img img img img img img img img

Vishnu R
Date: 06/12/2022

Work in progress | 0% Completed

HVAC work for seminar hall,MEP work ,Sanitary fittings work on progress at site

Attached images

img img img img img img img img img

Vishnu R
Date: 06/12/2022

Work in progress | 0% Completed

HVAC work for seminar hall,MEP work ,Sanitary fittings work on progress at site

Attached images

img img img img img img img img img

Vishnu R
Date: 06/12/2022

Work in progress | 0% Completed

HVAC work for seminar hall,MEP work ,Sanitary fittings work on progress at site

Attached images

img img img img img img img img img

Vishnu R
Date: 05/12/2022

Work in progress | 0% Completed

Electrical work-95% completed,Mechanical (HVAC and Fire)-80% completed Current status Plumbing sanitary works ongoing HVAC work on going Fire piping work completed

Attached images

img img img img img img img img

Vishnu R
Date: 05/12/2022

Work in progress | 0% Completed

Electrical work-95% completed,Mechanical (HVAC and Fire)-80% completed Current status Plumbing sanitary works ongoing HVAC work on going Fire piping work completed

Attached images

img img img img img img img img

Vishnu R
Date: 05/12/2022

Work in progress | 0% Completed

Electrical work-95% completed,Mechanical (HVAC and Fire)-80% completed Current status Plumbing sanitary works ongoing HVAC work on going Fire piping work completed

Attached images

img img img img img img img img

Vishnu R
Date: 05/12/2022

Work in progress | 0% Completed

Electrical work-95% completed,Mechanical (HVAC and Fire)-80% completed Current status Plumbing sanitary works ongoing HVAC work on going Fire piping work completed

Attached images

img img img img img img img img

Vishnu R
Date: 30/11/2022

Work in progress | 0% Completed

HVAC works, Electrical works ,sanitary items fittings are progress on the site

Attached images

img img img

Vishnu R
Date: 30/11/2022

Work in progress | 0% Completed

HVAC works, Electrical works ,sanitary items fittings are progress on the site

Attached images

img img img

Vishnu R
Date: 30/11/2022

Work in progress | 0% Completed

HVAC works, Electrical works ,sanitary items fittings are progress on the site

Attached images

img img img

Vishnu R
Date: 30/11/2022

Work in progress | 0% Completed

HVAC works, Electrical works ,sanitary items fittings are progress on the site

Attached images

img img img

Vishnu R
Date: 21/11/2022

Work in progress | 93% Completed

Electrical works ,Plumbing works, Bathroom works are in progress, Road works completed

Attached images

img img img

Vishnu R
Date: 21/11/2022

Work in progress | 93% Completed

Electrical works ,Plumbing works, Bathroom works are in progress, Road works completed

Attached images

img img img

Vishnu R
Date: 21/11/2022

Work in progress | 93% Completed

Electrical works ,Plumbing works, Bathroom works are in progress, Road works completed

Attached images

img img img

Vishnu R
Date: 21/11/2022

Work in progress | 93% Completed

Electrical works ,Plumbing works, Bathroom works are in progress, Road works completed

Attached images

img img img

Vishnu R
Date: 31/10/2022

Work in progress | 90% Completed

Belt above retaining wall -concretework Plumbing Trenching for Rain water line Manhole Ele - strip laying for earthing, Leveling works for roads

Attached images

img img img

Vishnu R
Date: 31/10/2022

Work in progress | 90% Completed

Belt above retaining wall -concretework Plumbing Trenching for Rain water line Manhole Ele - strip laying for earthing, Leveling works for roads

Attached images

img img img

Vishnu R
Date: 31/10/2022

Work in progress | 90% Completed

Belt above retaining wall -concretework Plumbing Trenching for Rain water line Manhole Ele - strip laying for earthing, Leveling works for roads

Attached images

img img img

Vishnu R
Date: 31/10/2022

Work in progress | 90% Completed

Belt above retaining wall -concretework Plumbing Trenching for Rain water line Manhole Ele - strip laying for earthing, Leveling works for roads

Attached images

img img img

Vishnu R
Date: 18/10/2022

Work in progress | 0% Completed

RW tank top slab -shuttering Electrical lightning arrester strip laying MEP plumbing line connection

Attached images

img img img img

Vishnu R
Date: 18/10/2022

Work in progress | 0% Completed

RW tank top slab -shuttering Electrical lightning arrester strip laying MEP plumbing line connection

Attached images

img img img img

Vishnu R
Date: 18/10/2022

Work in progress | 0% Completed

RW tank top slab -shuttering Electrical lightning arrester strip laying MEP plumbing line connection

Attached images

img img img img

Vishnu R
Date: 18/10/2022

Work in progress | 0% Completed

RW tank top slab -shuttering Electrical lightning arrester strip laying MEP plumbing line connection

Attached images

img img img img

Vishnu R
Date: 10/10/2022

Work in progress | 0% Completed

PVC septic tank instalation Soakpi- Solid block Soapit slab concrete Rain water tank bottom slab concrete Wall 1st lift concrete Retaing wall using RR masonry,Plumbing external piping work sewage line,Electrical external cable laying works

Attached images

img img img img

Vishnu R
Date: 10/10/2022

Work in progress | 0% Completed

PVC septic tank instalation Soakpi- Solid block Soapit slab concrete Rain water tank bottom slab concrete Wall 1st lift concrete Retaing wall using RR masonry,Plumbing external piping work sewage line,Electrical external cable laying works

Attached images

img img img img

Vishnu R
Date: 10/10/2022

Work in progress | 0% Completed

PVC septic tank instalation Soakpi- Solid block Soapit slab concrete Rain water tank bottom slab concrete Wall 1st lift concrete Retaing wall using RR masonry,Plumbing external piping work sewage line,Electrical external cable laying works

Attached images

img img img img

Vishnu R
Date: 10/10/2022

Work in progress | 0% Completed

PVC septic tank instalation Soakpi- Solid block Soapit slab concrete Rain water tank bottom slab concrete Wall 1st lift concrete Retaing wall using RR masonry,Plumbing external piping work sewage line,Electrical external cable laying works

Attached images

img img img img

Vishnu R
Date: 03/10/2022

Work in progress | 0% Completed

Physical progress - 85% Civil - 80 % Electrical - 65% HVAC- 0% Current sttus: RR masonry for RW wall around main building. Soak pit- earth work and solid block work in progress. UG tank - steel reinforcement work for base slab. Main bulding -electrical work.

Attached images

img img img img img

Vishnu R
Date: 03/10/2022

Work in progress | 0% Completed

Physical progress - 85% Civil - 80 % Electrical - 65% HVAC- 0% Current sttus: RR masonry for RW wall around main building. Soak pit- earth work and solid block work in progress. UG tank - steel reinforcement work for base slab. Main bulding -electrical work.

Attached images

img img img img img

Vishnu R
Date: 03/10/2022

Work in progress | 0% Completed

Physical progress - 85% Civil - 80 % Electrical - 65% HVAC- 0% Current sttus: RR masonry for RW wall around main building. Soak pit- earth work and solid block work in progress. UG tank - steel reinforcement work for base slab. Main bulding -electrical work.

Attached images

img img img img img

Vishnu R
Date: 03/10/2022

Work in progress | 0% Completed

Physical progress - 85% Civil - 80 % Electrical - 65% HVAC- 0% Current sttus: RR masonry for RW wall around main building. Soak pit- earth work and solid block work in progress. UG tank - steel reinforcement work for base slab. Main bulding -electrical work.

Attached images

img img img img img

Date: 24/09/2022

Work in progress | 0% Completed

work resumed. earth work and pcc for septic tank compound wall-earth work and pcc for foundation

Date: 24/09/2022

Work in progress | 0% Completed

work resumed. earth work and pcc for septic tank compound wall-earth work and pcc for foundation

Date: 24/09/2022

Work in progress | 0% Completed

work resumed. earth work and pcc for septic tank compound wall-earth work and pcc for foundation

Date: 24/09/2022

Work in progress | 0% Completed

work resumed. earth work and pcc for septic tank compound wall-earth work and pcc for foundation

Date: 19/09/2022

Work in progress | 0% Completed

work has resumes.electrical work in progress and civil work has arranged to start

Date: 19/09/2022

Work in progress | 0% Completed

work has resumes.electrical work in progress and civil work has arranged to start

Date: 19/09/2022

Work in progress | 0% Completed

work has resumes.electrical work in progress and civil work has arranged to start

Date: 19/09/2022

Work in progress | 0% Completed

work has resumes.electrical work in progress and civil work has arranged to start