| Atheesh.P. Mohan |
| Date: 01/01/2024 |
Work in progress | 65% Completed
Small Regulator|0% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Landscaping|0% Completed
Parking Area|100% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Plumbing|0% Completed
The interlocking completed kerb stone laying completed. landscape is completed. RE prepared and submitted to tourism, they have conducted a meeting on 22/7/2023 and changes were addressed and RE is correcting accordingly and submitted for scrutiny
Attached images
| Stephy Sebastian |
| Date: 01/09/2023 |
Work in progress | 64% Completed
Plumbing|0% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Landscaping|0% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Small Regulator|0% Completed
The interlocking completed kerb stone laying completed. landscape is completed. RE prepared and submitted to tourism, they have conducted a meeting on 22/7/2023 and changes were addressed and RE is correcting accordingly.
Attached images
| Stephy Sebastian |
| Date: 23/08/2023 |
Work in progress | 64% Completed
Plumbing|0% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Landscaping|0% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Small Regulator|0% Completed
The interlocking completed kerb stone laying completed. landscape is completed. RE prepared and submitted to tourism, they have conducted a meeting on 22/7/2023 and changes were addressed and RE is correcting accordingly.
| Stephy Sebastian |
| Date: 14/08/2023 |
Work in progress | 64% Completed
Plumbing|0% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Landscaping|0% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Small Regulator|0% Completed
The interlocking completed kerb stone laying completed. landscape is completed. RE prepared and submitted to tourism, they have conducted a meeting on 22/7/2023 and changes were addressed and RE is correcting accordingly.
Attached images
| Stephy Sebastian |
| Date: 07/08/2023 |
Work in progress | 64% Completed
Small Regulator|0% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Landscaping|0% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Plumbing|0% Completed
The interlocking completed kerb stone laying completed. landscape is completed. RE prepared and submitted to tourism, they have conducted a meeting on 22/7/2023 and changes were addressed and RE is correcting accordingly.
Attached images
| Stephy Sebastian |
| Date: 31/07/2023 |
Work in progress | 61% Completed
Small Regulator|0% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Landscaping|0% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Plumbing|0% Completed
The interlocking completed kerb stone laying completed. landscape is completed. RE prepared and submitted to tourism, they have conducted a meeting on 22/7/2023 and changes were addressed and RE is correcting accordingly.
Attached images
| Stephy Sebastian |
| Date: 24/07/2023 |
Work in progress | 61% Completed
Plumbing|0% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Landscaping|0% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Small Regulator|0% Completed
The interlocking completed kerb stone laying completed. landscape is completed. RE prepared and submitted to tourism, they have conducted a meeting on 22/7/2023 and changes were addressed and RE is correcting accordingly.
Attached images
| Stephy Sebastian |
| Date: 19/07/2023 |
Work in progress | 61% Completed
Plumbing|0% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Landscaping|0% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Small Regulator|0% Completed
The interlocking completed kerb stone laying completed. landscape is completed.
Attached images
| Stephy Sebastian |
| Date: 10/07/2023 |
Work in progress | 61% Completed
Plumbing|0% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Landscaping|0% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Small Regulator|0% Completed
The interlocking completed kerb stone laying completed. landscape is completed.
Attached images
| Stephy Sebastian |
| Date: 27/06/2023 |
Work in progress | 61% Completed
Plumbing|0% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Landscaping|0% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Small Regulator|0% Completed
The interlocking completed kerb stone laying completed. landscape is completed. A meeting is conducted regarding the RE is under preparation.
Attached images
| Stephy Sebastian |
| Date: 19/06/2023 |
Work in progress | 58% Completed
Landscaping|0% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Plumbing|0% Completed
Small Regulator|0% Completed
The interlocking completed kerb stone laying completed. landscape is completed. A meeting is conducted regarding the RE and minutes have been submitted to DD
Attached images
| Stephy Sebastian |
| Date: 05/06/2023 |
Work in progress | 58% Completed
Small Regulator|0% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Landscaping|0% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Plumbing|0% Completed
The interlocking completed kerb stone laying completed. landscape is completed. A meeting is conducted regarding the RE and minutes have been submitted to DD
Attached images
| Stephy Sebastian |
| Date: 22/05/2023 |
Work in progress | 58% Completed
Plumbing|0% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Landscaping|0% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Small Regulator|0% Completed
The interlocking completed kerb stone laying completed. landscape is completed. A meeting is conducted regarding the RE and minutes have been submitted to DD
Attached images
| Stephy Sebastian |
| Date: 15/05/2023 |
Work in progress | 58% Completed
Plumbing|0% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Landscaping|0% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Small Regulator|0% Completed
The interlocking completed kerb stone laying completed. landscape is completed. A meeting is conducted regarding the RE and minutes have been submitted to DD
Attached images
| Stephy Sebastian |
| Date: 08/05/2023 |
Work in progress | 58% Completed
Plumbing|0% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Landscaping|0% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Small Regulator|0% Completed
The interlocking completed kerb stone laying completed. landscape is completed. A meeting is conducted regarding the RE and minutes have been submitted to DD
Attached images
| Stephy Sebastian |
| Date: 24/04/2023 |
Work in progress | 58% Completed
Small Regulator|0% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Landscaping|0% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Plumbing|0% Completed
The interlocking completed kerb stone laying completed. landscape is completed. A meeting is conducted regarding the RE and minutes have been submitted to DD
Attached images
| Stephy Sebastian |
| Date: 17/04/2023 |
Work in progress | 57% Completed
Small Regulator|0% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Landscaping|0% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Plumbing|0% Completed
The interlocking completed kerb stone laying completed. landscape is completed. A meeting is conducted regarding the RE and minutes have been submitted to DD
Attached images
| Stephy Sebastian |
| Date: 10/04/2023 |
Work in progress | 56% Completed
Plumbing|0% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Landscaping|0% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Small Regulator|0% Completed
The interlocking completed kerb stone laying completed. landscape is completed. A meeting is conducted regarding the RE and minutes have been submitted to DD.
Attached images
| Stephy Sebastian |
| Date: 04/04/2023 |
Work in progress | 56% Completed
Plumbing|0% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Landscaping|0% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Small Regulator|0% Completed
The interlocking completed kerb stone laying completed. landscape is completed. A meeting is conducted regarding the RE and minutes have been submitted to DD.
Attached images
| Stephy Sebastian |
| Date: 27/03/2023 |
Work in progress | 56% Completed
Plumbing|0% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Landscaping|0% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Small Regulator|0% Completed
The interlocking completed kerb stone laying completed. landscape and pluming about to begin. A meeting is conducted regarding the RE and minutes have been submitted to DD.
Attached images
| Stephy Sebastian |
| Date: 18/03/2023 |
Work in progress | 53% Completed
Parking Area|35% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Small Regulator|0% Completed
Landscaping|0% Completed
Plumbing|0% Completed
Plumbing|0% Completed
The interlocking completed kerb stone laying completed. landscape and pluming about to begin. A meeting is conducted regarding the RE and minutes have been submitted to DD.
Attached images
| Stephy Sebastian |
| Date: 06/03/2023 |
Work in progress | 53% Completed
Landscaping|0% Completed
Small Regulator|0% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Plumbing|0% Completed
Providing Landscaping|70% Completed
Building|10% Completed
Parking Area|100% Completed
The interlocking completed kerb stone laying completed. landscape and pluming about to begin. A meeting is conducted regarding the RE and minutes have been submitted to DD.
Attached images
| Stephy Sebastian |
| Date: 27/02/2023 |
Work in progress | 53% Completed
Small Regulator|0% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Landscaping|0% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Plumbing|0% Completed
The interlocking completed kerb stone laying completed. landscape and pluming about to begin. A meeting is conducted regarding the RE and minutes have been submitted to DD.
Attached images
| Stephy Sebastian |
| Date: 20/02/2023 |
Work in progress | 53% Completed
Plumbing|0% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Landscaping|0% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Small Regulator|0% Completed
The interlocking completed kerb stone laying completed. landscape and pluming about to begin. A meeting is conducted regarding the RE and minutes have been submitted to DD.
Attached images
| Stephy Sebastian |
| Date: 13/02/2023 |
Work in progress | 53% Completed
Plumbing|0% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Landscaping|0% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Small Regulator|0% Completed
The interlocking completed kerb stone laying completed. landscape and pluming about to begin. A meeting is conducted regarding the RE and minutes have been submitted to DD.
Attached images
| Stephy Sebastian |
| Date: 06/02/2023 |
Work in progress | 52% Completed
Plumbing|0% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Landscaping|0% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Small Regulator|0% Completed
The interlocking completed kerb stone laying completed. landscape and pluming about to begin. A meeting is conducted regarding the RE and minutes have been submitted to DD.
Attached images
| Stephy Sebastian |
| Date: 30/01/2023 |
Work in progress | 52% Completed
Small Regulator|0% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Landscaping|0% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Plumbing|0% Completed
The interlocking completed kerb stone laying completed. landscape and pluming about to begin.
Attached images
| Stephy Sebastian |
| Date: 23/01/2023 |
Work in progress | 52% Completed
Small Regulator|0% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Landscaping|0% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Plumbing|0% Completed
The interlocking completed kerb stone laying completed. landscape and pluming about to begin.
Attached images
| Stephy Sebastian |
| Date: 16/01/2023 |
Work in progress | 52% Completed
Plumbing|0% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Landscaping|0% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Small Regulator|0% Completed
The interlocking completed kerb stone laying completed. landscape and pluming about to begin.
Attached images
| Stephy Sebastian |
| Date: 09/01/2023 |
Work in progress | 52% Completed
Plumbing|0% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Landscaping|0% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Small Regulator|0% Completed
The interlocking completed kerb stone laying completed
Attached images
| Stephy Sebastian |
| Date: 03/01/2023 |
Work in progress | 52% Completed
Plumbing|0% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Landscaping|0% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Small Regulator|0% Completed
The interlocking completed kerb stone laying completed
Attached images
| Stephy Sebastian |
| Date: 26/12/2022 |
Work in progress | 51% Completed
Plumbing|0% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Landscaping|0% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Small Regulator|0% Completed
The interlock laying is completed. Finishing works are going on Bill under preparation RE is also under preparation
Attached images
| Stephy Sebastian |
| Date: 19/12/2022 |
Work in progress | 50% Completed
Landscaping|0% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Plumbing|0% Completed
Small Regulator|0% Completed
The interlock laying works is on progress and RE should be made after discussion with DD
Attached images
| Stephy Sebastian |
| Date: 12/12/2022 |
Work in progress | 48% Completed
Small Regulator|0% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Landscaping|0% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Plumbing|0% Completed
The interlock work completed Landscaping work is in progress
Attached images
| Stephy Sebastian |
| Date: 04/12/2022 |
Work in progress | 44% Completed
Plumbing|0% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Landscaping|0% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Small Regulator|0% Completed
The interlock work in plot ABCD completed 70% The interlock work of F and G completed up to 90%
Attached images
| Stephy Sebastian |
| Date: 28/11/2022 |
Work in progress | 43% Completed
Plumbing|0% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Landscaping|0% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Small Regulator|0% Completed
The interlock of parking area completed. ABCDE and FG inter lock laying completed kerb stone laying completed
Attached images
| Stephy Sebastian |
| Date: 30/10/2022 |
Not Started
Plumbing|0% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Landscaping|0% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Small Regulator|0% Completed
The GSB laying in parking area ABCDE completed Kerb stone work is in progress The levels has been taken and will be reported soon Lanscaping work is in progress
Attached images
| Stephy Sebastian |
| Date: 25/10/2022 |
Not Started
Small Regulator|0% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Landscaping|0% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Plumbing|0% Completed
.1.The work of parking is in progress the GSB laying is completed 2. The final levels of GSB is taken for plot ABCD and reported 3. GSB laying work is in progress 4. The reporting to CTE for PLOT FG is under progress. 4. GSB laying on ABCD completed. 5. Kerb work is in progress.6. masonry work is in progress.7. final levels of GSB of parking area completely taken
Attached images
| Stephy Sebastian |
| Date: 17/10/2022 |
Not Started
Small Regulator|0% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Landscaping|0% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Plumbing|0% Completed
. The work of parking is in progress the GSB laying is completed 2. The final levels of GSB is taken for plot ABCD and reported 3. GSB laying work is in progress 4. The reporting to CTE for PLOT FG is under progress. 4. GSB laying on ABCD completed. 5. Kerb work is in progress.
Attached images
| Stephy Sebastian |
| Date: 09/10/2022 |
Work in progress | 22% Completed
Plumbing|0% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Landscaping|0% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Small Regulator|0% Completed
1. The work of parking is in progress the GSB laying is completed 2. The final levels of GSB is taken for plot ABCD and reported 3. GSB laying work is in progress 4. The reporting to CTE for PLOT FG is under progress
Attached images
| Stephy Sebastian |
| Date: 03/10/2022 |
Work in progress | 21% Completed
Plumbing|0% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Landscaping|0% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Small Regulator|0% Completed
1. The work of parking is in progress the GSB laying is completed 2. The final levels of GSB is taken for plot ABCD and reported 3. GSB laying work is in progress 4. The reporting to CTE for PLOT FG is under progress
Attached images
| Stephy Sebastian |
| Date: 25/09/2022 |
Work in progress | 20% Completed
Plumbing|0% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Landscaping|0% Completed
Plumbing|0% Completed
Parking Area|35% Completed
Small Regulator|0% Completed
1. The work of parking is in progress the GSB laying is completed 2. The final levels of GSB is taken 3. Calculation work is in progress 4. The reporting to CTE work is under progress
Attached images
| Stephy Sebastian |
| Date: 19/09/2022 |
Work in progress | 17% Completed
Parking Area|35% Completed
Parking Area|100% Completed
Building|10% Completed
Providing Landscaping|70% Completed
Small Regulator|0% Completed
Landscaping|0% Completed
Plumbing|0% Completed
Plumbing|0% Completed
Clearing the site Removing the interlock Initial Level of earth levelling completed Quarry muck filling is completed The bund formation for the regulator is in progress The final levels of GSB is also taken
Attached images