Amal Padmu L P |
Date: 18/03/2024 |
Work has been completed | 100% Completed
Submain|100% Completed
Automation|100% Completed
Mainline|100% Completed
Completed
Amal Padmu L P |
Date: 18/03/2024 |
Amal Padmu L P |
Date: 01/01/2024 |
Work has been completed | 100% Completed
Mainline|100% Completed
Automation|100% Completed
Submain|100% Completed
Testing on going
Amal Padmu L P |
Date: 11/09/2023 |
Work in progress | 98% Completed
Mainline|100% Completed
Automation|100% Completed
Submain|100% Completed
Sub main and mainline works are completed. testing and commissioning are pending due to the delay in obtaining EB connection
Amal Padmu L P |
Date: 04/09/2023 |
Work in progress | 98% Completed
Mainline|100% Completed
Automation|100% Completed
Submain|100% Completed
Sub main and mainline works are completed. testing and commissioning are pending due to the delay in obtaining EB connection
Amal Padmu L P |
Date: 10/07/2023 |
Amal Padmu L P |
Date: 03/07/2023 |
Amal Padmu L P |
Date: 26/06/2023 |
Amal Padmu L P |
Date: 19/06/2023 |
Amal Padmu L P |
Date: 12/06/2023 |
Work in progress | 95% Completed
Mainline|100% Completed
Automation|100% Completed
Submain|100% Completed
Sub main and mainline works are completed. Head Unit works are pending due to the delay in civil works
Amal Padmu L P |
Date: 05/06/2023 |
Amal Padmu L P |
Date: 29/05/2023 |
Work in progress | 95% Completed
Automation|100% Completed
Mainline|100% Completed
Submain|100% Completed
Sub main and mainline works are completed. Head Unit works are pending due to the delay in civil works
Amal Padmu L P |
Date: 22/05/2023 |
Amal Padmu L P |
Date: 07/05/2023 |
Work in progress | 94% Completed
Mainline|100% Completed
Automation|100% Completed
Submain|100% Completed
Sub main and mainline works are completed. Head Unit works are pending due to the delay in civil works
Amal Padmu L P |
Date: 02/05/2023 |
Work in progress | 94% Completed
Mainline|100% Completed
Automation|100% Completed
Submain|100% Completed
Sub main and mainline works are completed. Head Unit works are pending due to the delay in civil works
Amal Padmu L P |
Date: 24/04/2023 |
Work in progress | 94% Completed
Mainline|100% Completed
Automation|100% Completed
Submain|100% Completed
Sub main and mainline works are completed. Head Unit works are pending due to the delay in civil works
Amal Padmu L P |
Date: 17/04/2023 |
Work in progress | 94% Completed
Mainline|100% Completed
Automation|100% Completed
Submain|100% Completed
Sub main and mainline works are completed. Head Unit works are pending due to the delay in civil works
Amal Padmu L P |
Date: 11/04/2023 |
Work in progress | 94% Completed
Mainline|100% Completed
Automation|100% Completed
Submain|100% Completed
Sub main and mainline works are completed. Head Unit works are pending due to the delay in civil works
Amal Padmu L P |
Date: 03/04/2023 |
Work in progress | 94% Completed
Mainline|100% Completed
Automation|100% Completed
Submain|100% Completed
Sub main and mainline works are completed. Head Unit works are pending due to the delay in civil works
Amal Padmu L P |
Date: 27/03/2023 |
Work in progress | 94% Completed
Mainline|100% Completed
Automation|100% Completed
Submain|100% Completed
Sub main and mainline works are completed. Head Unit works are pending due to the delay in civil works
Amal Padmu L P |
Date: 21/03/2023 |
Work in progress | 94% Completed
Automation|100% Completed
Submain|100% Completed
Mainline|100% Completed
Sub main and main line works are completed. Head Unit works are pending due to the delay in civil works
Amal Padmu L P |
Date: 13/03/2023 |
Work in progress | 94% Completed
Submain|100% Completed
Mainline|100% Completed
Automation|100% Completed
Sub main and main line works are completed. Head Unit works are pending due to the delay in civil works
Amal Padmu L P |
Date: 06/03/2023 |
Work in progress | 94% Completed
Automation|100% Completed
Mainline|100% Completed
Submain|100% Completed
Sub main and main line works are completed. Head Unit works are pending due to the delay in civil works
Amal Padmu L P |
Date: 27/02/2023 |
Amal Padmu L P |
Date: 20/02/2023 |
Work in progress | 94% Completed
Mainline|100% Completed
Automation|100% Completed
Submain|100% Completed
Sub main and main line works are completed. Head Unit works are pending due to the delay in civil works
Amal Padmu L P |
Date: 13/02/2023 |
Work in progress | 94% Completed
Mainline|100% Completed
Automation|100% Completed
Submain|100% Completed
Sub main and main line works are completed. Head Unit works are pending due to the delay in civil works
Amal Padmu L P |
Date: 06/02/2023 |
Work in progress | 94% Completed
Mainline|100% Completed
Automation|100% Completed
Submain|100% Completed
Sub main and main line works are completed. Head Unit works are pending due to the delay in civil works
Amal Padmu L P |
Date: 30/01/2023 |
Amal Padmu L P |
Date: 23/01/2023 |
Amal Padmu L P |
Date: 16/01/2023 |
Amal Padmu L P |
Date: 09/01/2023 |
Amal Padmu L P |
Date: 03/01/2023 |
Amal Padmu L P |
Date: 26/12/2022 |
Amal Padmu L P |
Date: 19/12/2022 |
Amal Padmu L P |
Date: 12/12/2022 |
Amal Padmu L P |
Date: 03/12/2022 |
Amal Padmu L P |
Date: 03/12/2022 |
Amal Padmu L P |
Date: 29/10/2022 |
Work in progress | 0% Completed
Mainline|100% Completed
Automation|100% Completed
Submain|100% Completed
Submain works -100% Main line works- 100% Automation works - ongoing, it can be completed only after the installation of pumping unit
GPS Cordinates
Latitude : 10.7135463
Longitude : 76.8683125
Accuracy : 2900
Attached images
Amal Padmu L P |
Date: 25/10/2022 |
Amal Padmu L P |
Date: 17/10/2022 |
Amal Padmu L P |
Date: 10/10/2022 |
Amal Padmu L P |
Date: 01/10/2022 |
Amal Padmu L P |
Date: 26/09/2022 |