Ebin Solomon |
Date: 26/05/2024 |
Work in progress | 70% Completed
Road work|80% Completed
Restaurants, Toilets, Entrance Gate|65% Completed
Landscaping|0% Completed
Electrical and plumbing|25% Completed
Work in progress -70% Completed .Road work - 80% Completed. Restaurant-70%, Toilet block-75, Entrance Gate -60% Completed .Landscaping | 0% Completed Electrical and plumbing -25%
Ebin Solomon |
Date: 22/04/2024 |
Work in progress | 65% Completed
Electrical and plumbing|25% Completed
Landscaping|0% Completed
Restaurants, Toilets, Entrance Gate|65% Completed
Road work|80% Completed
Work in progress -65% Completed .Road work - 79% Completed. Restaurants, Toilets, Entrance Gate -50% Completed .Landscaping | 0% Completed Electrical and plumbing -20%
Ebin Solomon |
Date: 28/02/2024 |
Work in progress | 55% Completed
Electrical and plumbing|25% Completed
Landscaping|0% Completed
Restaurants, Toilets, Entrance Gate|65% Completed
Road work|80% Completed
Work in progress | 50% Completed | 03/01/2024 Road work | 75% Completed Restaurants, Toilets, Entrance Gate | 25% Completed Landscaping | 0% Completed Electrical and plumbing | 0% Completed Road work | 78% Completed Restaurants, Toilets, Entrance Gate | 45% Completed Landscaping | 0% Completed Electrical and plumbing | 0% Completed
Ebin Solomon |
Date: 03/01/2024 |
Work in progress | 50% Completed
Electrical and plumbing|25% Completed
Landscaping|0% Completed
Restaurants, Toilets, Entrance Gate|65% Completed
Road work|80% Completed
Road work | 75% Completed Restaurants, Toilets, Entrance Gate | 25% Completed Landscaping | 0% Completed Electrical and plumbing | 0% Completed
Ebin Solomon |
Date: 03/01/2024 |
Work in progress | 50% Completed
Landscaping|0% Completed
Restaurants, Toilets, Entrance Gate|65% Completed
Electrical and plumbing|25% Completed
Road work|80% Completed
Road work | 75% Completed Restaurants, Toilets, Entrance Gate | 25% Completed Landscaping | 0% Completed Electrical and plumbing | 0% Completed
Vishnu R |
Date: 07/08/2023 |
Work in progress | 48% Completed
Electrical and plumbing|25% Completed
Landscaping|0% Completed
Restaurants, Toilets, Entrance Gate|65% Completed
Road work|80% Completed
oad work | 75% Completed Restaurants, Toilets, Entrance Gate | 20% Completed Landscaping | 0% Completed Electrical and plumbing | 0% Completed
Attached images
Vishnu R |
Date: 31/07/2023 |
Work in progress | 47% Completed
Electrical and plumbing|25% Completed
Landscaping|0% Completed
Restaurants, Toilets, Entrance Gate|65% Completed
Road work|80% Completed
Road work | 75% Completed Restaurants, Toilets, Entrance Gate | 20% Completed Landscaping | 0% Completed Electrical and plumbing | 0% Completed oad work | 75% Completed Restaurants, Toilets, Entrance Gate | 20% Completed Landscaping | 0% Completed Electrical and plumbing | 0% Completed RESTUARTANT BLOCK AND TOILET BLOCK UPTO PLINTH ALL CONCRETE WORK COMPLETED
Attached images
Vishnu R |
Date: 19/07/2023 |
Work in progress | 46% Completed
Road work|80% Completed
Landscaping|0% Completed
Restaurants, Toilets, Entrance Gate|65% Completed
Electrical and plumbing|25% Completed
oad work | 75% Completed Restaurants, Toilets, Entrance Gate | 20% Completed Landscaping | 0% Completed Electrical and plumbing | 0% Completed RESTUARTANT BLOCK AND TOILET BLOCK UPTO PLINTH ALL CONCRETE WORK COMPLETED
Attached images
Vishnu R |
Date: 11/07/2023 |
Vishnu R |
Date: 27/06/2023 |
Vishnu R |
Date: 15/06/2023 |
Vishnu R |
Date: 08/06/2023 |
Vishnu R |
Date: 29/05/2023 |
Vishnu R |
Date: 23/05/2023 |
Vishnu R |
Date: 15/05/2023 |
Vishnu R |
Date: 09/05/2023 |
Vishnu R |
Date: 29/04/2023 |
Date: 20/02/2023 |
Date: 13/02/2023 |
Date: 06/02/2023 |
Date: 30/01/2023 |
Date: 23/01/2023 |
Work in progress | 12% Completed
Electrical and plumbing|25% Completed
Landscaping|0% Completed
Restaurants, Toilets, Entrance Gate|65% Completed
Road work|80% Completed
Retaining wall works in progress, Road earthwork in progress, cutting of trees in progress, Culvert works inr progress, Restaurant building setout done.
Attached images
Date: 16/01/2023 |
Work in progress | 11% Completed
Electrical and plumbing|25% Completed
Landscaping|0% Completed
Restaurants, Toilets, Entrance Gate|65% Completed
Road work|80% Completed
Retaining wall works in progress, Road earthwork in progress, cutting of trees in progress, Culvert wotks in progress.
Attached images
Date: 09/01/2023 |
Work in progress | 8% Completed
Electrical and plumbing|25% Completed
Landscaping|0% Completed
Restaurants, Toilets, Entrance Gate|65% Completed
Road work|80% Completed
Retaining wall works in progress, Road earthwork in progress, Trees were cut and send to irrigation dept., Culvert wotks in progress
Attached images
Date: 02/01/2023 |
Date: 26/12/2022 |
Work in progress | 6% Completed
Road work|80% Completed
Landscaping|0% Completed
Restaurants, Toilets, Entrance Gate|65% Completed
Electrical and plumbing|25% Completed
Retaining wall concrete works, Earthwork for road, Felling of trees in progress, Area for restaurant was marked in presence of Architect
Attached images
Date: 19/12/2022 |
Date: 12/12/2022 |
Date: 12/12/2022 |
Date: 12/12/2022 |
Date: 05/12/2022 |
Work in progress | 5% Completed
Electrical and plumbing|25% Completed
Landscaping|0% Completed
Restaurants, Toilets, Entrance Gate|65% Completed
Road work|80% Completed
Road work-retaining wall works in progress Earthwork for roadwork in progress Felling of trees for road work in presence of Forest dpt. officials is in progress
Attached images
Date: 30/11/2022 |