Amal Padmu L P |
Date: 04/09/2023 |
Work in progress | 98% Completed
Water conveyance pipe|0% Completed
Fertigation Room|100% Completed
Sump Tank and Pipe Culvert|0% Completed
Electrification|93% Completed
EB connection Pending
Amal Padmu L P |
Date: 10/07/2023 |
Amal Padmu L P |
Date: 03/07/2023 |
Work in progress | 94% Completed
Electrification|93% Completed
Fertigation Room|100% Completed
Sump Tank and Pipe Culvert|0% Completed
Water conveyance pipe|0% Completed
Installation of pumping unit is pending
Amal Padmu L P |
Date: 26/06/2023 |
Work in progress | 94% Completed
Electrification|93% Completed
Fertigation Room|100% Completed
Sump Tank and Pipe Culvert|0% Completed
Water conveyance pipe|0% Completed
Installation of pumping unit is pending
Amal Padmu L P |
Date: 19/06/2023 |
Work in progress | 92% Completed
Electrification|93% Completed
Fertigation Room|100% Completed
Sump Tank and Pipe Culvert|0% Completed
Water conveyance pipe|0% Completed
Installation of pumping unit is pending
Amal Padmu L P |
Date: 12/06/2023 |
Work in progress | 91% Completed
Electrification|93% Completed
Fertigation Room|100% Completed
Sump Tank and Pipe Culvert|0% Completed
Water conveyance pipe|0% Completed
Installation of pumping unit is pending
Amal Padmu L P |
Date: 05/06/2023 |
Work in progress | 91% Completed
Electrification|93% Completed
Fertigation Room|100% Completed
Sump Tank and Pipe Culvert|0% Completed
Water conveyance pipe|0% Completed
Installation of pumping unit is pending
Amal Padmu L P |
Date: 29/05/2023 |
Work in progress | 90% Completed
Electrification|93% Completed
Fertigation Room|100% Completed
Sump Tank and Pipe Culvert|0% Completed
Water conveyance pipe|0% Completed
Installation of pumping unit is pending
Amal Padmu L P |
Date: 22/05/2023 |
Amal Padmu L P |
Date: 15/05/2023 |
Work in progress | 88% Completed
Water conveyance pipe|0% Completed
Fertigation Room|100% Completed
Sump Tank and Pipe Culvert|0% Completed
Electrification|93% Completed
Installation of pumping unit is pending
Amal Padmu L P |
Date: 07/05/2023 |
Work in progress | 88% Completed
Electrification|93% Completed
Fertigation Room|100% Completed
Sump Tank and Pipe Culvert|0% Completed
Water conveyance pipe|0% Completed
Installation of pumping unit is pending
Amal Padmu L P |
Date: 02/05/2023 |
Work in progress | 88% Completed
Electrification|93% Completed
Fertigation Room|100% Completed
Sump Tank and Pipe Culvert|0% Completed
Water conveyance pipe|0% Completed
Installation of pumping unit is pending
Amal Padmu L P |
Date: 28/04/2023 |
Work in progress | 88% Completed
Electrification|93% Completed
Fertigation Room|100% Completed
Sump Tank and Pipe Culvert|0% Completed
Water conveyance pipe|0% Completed
Installation of pumping unit is pending
Amal Padmu L P |
Date: 17/04/2023 |
Work in progress | 88% Completed
Electrification|93% Completed
Fertigation Room|100% Completed
Sump Tank and Pipe Culvert|0% Completed
Water conveyance pipe|0% Completed
Installation of pumping unit is pending
Amal Padmu L P |
Date: 11/04/2023 |
Work in progress | 88% Completed
Electrification|93% Completed
Fertigation Room|100% Completed
Sump Tank and Pipe Culvert|0% Completed
Water conveyance pipe|0% Completed
Installation of pumping unit is pending
Amal Padmu L P |
Date: 03/04/2023 |
Work in progress | 88% Completed
Electrification|93% Completed
Fertigation Room|100% Completed
Sump Tank and Pipe Culvert|0% Completed
Water conveyance pipe|0% Completed
Installation of pumping unit is pending
Amal Padmu L P |
Date: 27/03/2023 |
Work in progress | 88% Completed
Sump Tank and Pipe Culvert|0% Completed
Fertigation Room|100% Completed
Water conveyance pipe|0% Completed
Electrification|93% Completed
Installation of pumping unit is pending
Amal Padmu L P |
Date: 21/03/2023 |
Work in progress | 88% Completed
Water conveyance pipe|0% Completed
Electrification|93% Completed
Sump Tank and Pipe Culvert|0% Completed
Fertigation Room|100% Completed
Installation of the Pumping unit is pending
Amal Padmu L P |
Date: 13/03/2023 |
Amal Padmu L P |
Date: 06/03/2023 |
Amal Padmu L P |
Date: 27/02/2023 |
Amal Padmu L P |
Date: 20/02/2023 |
Work in progress | 87% Completed
Electrification|93% Completed
Fertigation Room|100% Completed
Sump Tank and Pipe Culvert|0% Completed
Water conveyance pipe|0% Completed
Installation of Pumping unit is pending
Amal Padmu L P |
Date: 13/02/2023 |
Work in progress | 87% Completed
Electrification|93% Completed
Fertigation Room|100% Completed
Sump Tank and Pipe Culvert|0% Completed
Water conveyance pipe|0% Completed
Installation of Pumping unit is pending
Amal Padmu L P |
Date: 06/02/2023 |
Amal Padmu L P |
Date: 31/01/2023 |
Amal Padmu L P |
Date: 23/01/2023 |
Work in progress | 85% Completed
Electrification|93% Completed
Fertigation Room|100% Completed
Sump Tank and Pipe Culvert|0% Completed
Water conveyance pipe|0% Completed
Informed contractor to complete the remaining works
Amal Padmu L P |
Date: 19/01/2023 |
Work in progress | 85% Completed
Water conveyance pipe|0% Completed
Fertigation Room|100% Completed
Sump Tank and Pipe Culvert|0% Completed
Electrification|93% Completed
Informed contractor to complete the remaining works
Amal Padmu L P |
Date: 27/12/2022 |
Work in progress | 85% Completed
Water conveyance pipe|0% Completed
Fertigation Room|100% Completed
Sump Tank and Pipe Culvert|0% Completed
Electrification|93% Completed
Informed contractor to complete the remaining works
GPS Cordinates
Latitude : 10.7359472
Longitude : 76.8445671
Accuracy : 20
Anu IT Admin |
Date: 29/11/2022 |
Amal Padmu L P |
Date: 29/10/2022 |
Work in progress | 0% Completed
Electrification|93% Completed
Fertigation Room|100% Completed
Sump Tank and Pipe Culvert|0% Completed
Water conveyance pipe|0% Completed
Construction of Irrigation Room -100% Electrical work -90% Pathway to Irrigation room -to be started
GPS Cordinates
Latitude : 10.7135463
Longitude : 76.8683125
Accuracy : 2900
Attached images
Amal Padmu L P |
Date: 25/10/2022 |
Amal Padmu L P |
Date: 17/10/2022 |
Amal Padmu L P |
Date: 10/10/2022 |
Work in progress | 72% Completed
Electrification|93% Completed
Fertigation Room|100% Completed
Sump Tank and Pipe Culvert|0% Completed
Water conveyance pipe|0% Completed
pending works- installation of the pumping unit - construction of the pathway to the pumphouse instructed the contractor to restart the work.
Attached images
Amal Padmu L P |
Date: 01/10/2022 |
Work in progress | 72% Completed
Electrification|93% Completed
Fertigation Room|100% Completed
Sump Tank and Pipe Culvert|0% Completed
Water conveyance pipe|0% Completed
Installation of electrical panel is completed
GPS Cordinates
Latitude : 10.7138296
Longitude : 76.8668711
Accuracy : 2700
Attached images
Amal Padmu L P |
Date: 26/09/2022 |
Amal Padmu L P |
Date: 17/09/2022 |