Meenu .E. S
Date: 04/09/2023

Work has been completed | 100% Completed

100.00% CIVIL|100% Completed

100.00% MECHANICAL|100% Completed

100.00% ELECTRICAL|100% Completed

1.all work completed

Meenu .E. S
Date: 10/07/2023

Work has been completed | 100% Completed

100.00% MECHANICAL|100% Completed

100.00% ELECTRICAL|100% Completed

100.00% CIVIL|100% Completed

Site handover to client on 1/06/2023

Meenu .E. S
Date: 12/06/2023

Work has been completed | 100% Completed

100.00% MECHANICAL|100% Completed

100.00% ELECTRICAL|100% Completed

100.00% CIVIL|100% Completed

Site handover to client on 1/06/2023

Meenu .E. S
Date: 05/06/2023

Work in progress | 99% Completed

100.00% MECHANICAL|100% Completed

100.00% ELECTRICAL|100% Completed

100.00% CIVIL|100% Completed

1.site handover to client on 1/06/2023

Meenu .E. S
Date: 29/05/2023

Work in progress | 99% Completed

100.00% ELECTRICAL|100% Completed

100.00% MECHANICAL|100% Completed

100.00% CIVIL|100% Completed

Site clearing work completed for the inauguration program.

Meenu .E. S
Date: 22/05/2023

Work in progress | 99% Completed

100.00% CIVIL|100% Completed

100.00% ELECTRICAL|100% Completed

100.00% MECHANICAL|100% Completed

1.site final clearance work in progress

Attached images

img

Meenu .E. S
Date: 15/05/2023

Work in progress | 99% Completed

100.00% MECHANICAL|100% Completed

100.00% ELECTRICAL|100% Completed

100.00% CIVIL|100% Completed

1.snag list rectification works in progress

Meenu .E. S
Date: 08/05/2023

Work in progress | 99% Completed

100.00% MECHANICAL|100% Completed

100.00% ELECTRICAL|100% Completed

100.00% CIVIL|100% Completed

1.snag list rectification works in progress

Meenu .E. S
Date: 02/05/2023

Work in progress | 99% Completed

100.00% ELECTRICAL|100% Completed

100.00% MECHANICAL|100% Completed

100.00% CIVIL|100% Completed

1.building rectification work in progress

Meenu .E. S
Date: 24/04/2023

Work in progress | 97% Completed

100.00% CIVIL|100% Completed

100.00% ELECTRICAL|100% Completed

100.00% MECHANICAL|100% Completed

1.snag list rectification works in progress

Meenu .E. S
Date: 17/04/2023

Work in progress | 95% Completed

100.00% CIVIL|100% Completed

100.00% ELECTRICAL|100% Completed

100.00% MECHANICAL|100% Completed

1.main building rectification works in progress

Meenu .E. S
Date: 10/04/2023

Work in progress | 95% Completed

100.00% MECHANICAL|100% Completed

100.00% ELECTRICAL|100% Completed

100.00% CIVIL|100% Completed

1.fire fighting works in progress

Attached images

img

Meenu .E. S
Date: 03/04/2023

Work in progress | 95% Completed

100.00% MECHANICAL|100% Completed

100.00% ELECTRICAL|100% Completed

100.00% CIVIL|100% Completed

1.main building fire fighting works in progress

Attached images

img

Meenu .E. S
Date: 27/03/2023

Work in progress | 94% Completed

100.00% MECHANICAL|100% Completed

100.00% ELECTRICAL|100% Completed

100.00% CIVIL|100% Completed

1.main building fire fighting works -overhead tank placing platform pcc works completed

Attached images

img

Meenu .E. S
Date: 20/03/2023

Work in progress | 94% Completed

100.00% CIVIL|100% Completed

100.00% ELECTRICAL|100% Completed

100.00% MECHANICAL|100% Completed

1.main building fire fighting works -fire tank placing platform pcc works in progress

Attached images

img

Meenu .E. S
Date: 13/03/2023

Work in progress | 94% Completed

100.00% CIVIL|100% Completed

100.00% ELECTRICAL|100% Completed

100.00% MECHANICAL|100% Completed

1.main building fire fighting works are pending 2.exterior and interior final finishing works in progress

Meenu .E. S
Date: 06/03/2023

Work in progress | 94% Completed

100.00% MECHANICAL|100% Completed

100.00% ELECTRICAL|100% Completed

100.00% CIVIL|100% Completed

1.exterior and interior final finishing works in progress

Meenu .E. S
Date: 27/02/2023

Work in progress | 94% Completed

100.00% CIVIL|100% Completed

100.00% ELECTRICAL|100% Completed

100.00% MECHANICAL|100% Completed

1.exterior and interior final finishing works in progress

Meenu .E. S
Date: 20/02/2023

Work in progress | 93% Completed

100.00% CIVIL|100% Completed

100.00% ELECTRICAL|100% Completed

100.00% MECHANICAL|100% Completed

Painting works in progress

Meenu .E. S
Date: 13/02/2023

Work in progress | 93% Completed

100.00% MECHANICAL|100% Completed

100.00% ELECTRICAL|100% Completed

100.00% CIVIL|100% Completed

1.painting works exterior and interior final coat in progress

Meenu .E. S
Date: 06/02/2023

Work in progress | 92% Completed

100.00% MECHANICAL|100% Completed

100.00% CIVIL|100% Completed

100.00% ELECTRICAL|100% Completed

1.painting (exterior and interior) final coat in progress

Meenu .E. S
Date: 30/01/2023

Work in progress | 91% Completed

100.00% CIVIL|100% Completed

100.00% ELECTRICAL|100% Completed

100.00% MECHANICAL|100% Completed

1.CCTV Camera fittings completed 2.final coat painting works in progress

Meenu .E. S
Date: 23/01/2023

Work in progress | 90% Completed

100.00% MECHANICAL|100% Completed

100.00% ELECTRICAL|100% Completed

100.00% CIVIL|100% Completed

1.ELV Cable laying excavation work in progress

Meenu .E. S
Date: 16/01/2023

Work in progress | 90% Completed

100.00% MECHANICAL|100% Completed

100.00% ELECTRICAL|100% Completed

100.00% CIVIL|100% Completed

1.CCTV cable laying excavation work in progress

Meenu .E. S
Date: 09/01/2023

Work in progress | 90% Completed

100.00% CIVIL|100% Completed

100.00% ELECTRICAL|100% Completed

100.00% MECHANICAL|100% Completed

1.Water treatment plant pipe connection works in progress 2.ELV CCTV Cable laying in progress 3.fire fighting works extinguishers fixing works completed

Attached images

img

Meenu .E. S
Date: 09/01/2023

Work in progress | 90% Completed

100.00% ELECTRICAL|100% Completed

100.00% MECHANICAL|100% Completed

100.00% CIVIL|100% Completed

1.fire extinguishers fixing completed 2.ELVmain building CCTV cable laying in progress

Meenu .E. S
Date: 02/01/2023

Work in progress | 89% Completed

100.00% CIVIL|100% Completed

100.00% MECHANICAL|100% Completed

100.00% ELECTRICAL|100% Completed

1.Exterior painting in progress 2.electrical final fittings in progress

Attached images

img img

Meenu .E. S
Date: 26/12/2022

Work in progress | 88% Completed

100.00% MECHANICAL|100% Completed

100.00% ELECTRICAL|100% Completed

100.00% CIVIL|100% Completed

1.ELV works in progress 2.electrical fixing works in progress

Attached images

img img

Meenu .E. S
Date: 19/12/2022

Work in progress | 88% Completed

100.00% ELECTRICAL|100% Completed

100.00% CIVIL|100% Completed

100.00% MECHANICAL|100% Completed

1.Front and back entrance door stainless steel grill works in progress 2.electrical final fittings in progress

Attached images

img img img

Meenu .E. S
Date: 12/12/2022

Work in progress | 87% Completed

100.00% ELECTRICAL|100% Completed

100.00% CIVIL|100% Completed

100.00% MECHANICAL|100% Completed

Front entrance door stainless steel grill works in progress

Attached images

img img

Meenu .E. S
Date: 05/12/2022

Work in progress | 86% Completed

100.00% CIVIL|100% Completed

100.00% ELECTRICAL|100% Completed

100.00% MECHANICAL|100% Completed

Smart classes projector and promeathene board fixing completed

Attached images

img img

Meenu .E. S
Date: 28/11/2022

Work in progress | 85% Completed

100.00% CIVIL|100% Completed

100.00% ELECTRICAL|100% Completed

100.00% MECHANICAL|100% Completed

Smart classes projector and promeathene board fixing in progress

Attached images

img

Meenu .E. S
Date: 21/11/2022

Work in progress | 84% Completed

100.00% MECHANICAL|100% Completed

100.00% ELECTRICAL|100% Completed

100.00% CIVIL|100% Completed

DG set and LT panel commissioning in progress.earth pit works in progress.

Meenu .E. S
Date: 31/10/2022

Work in progress | 82% Completed

100.00% MECHANICAL|100% Completed

100.00% ELECTRICAL|100% Completed

100.00% CIVIL|100% Completed

Road work completed.front gate fixing and ACP work completed

Attached images

img img img

Meenu .E. S
Date: 31/10/2022

Work in progress | 13% Completed

100.00% MECHANICAL|100% Completed

100.00% ELECTRICAL|100% Completed

100.00% CIVIL|100% Completed

Electrical panel board fixing in progress

Attached images

img

Meenu .E. S
Date: 24/10/2022

Work in progress | 0% Completed

100.00% CIVIL|100% Completed

100.00% ELECTRICAL|100% Completed

100.00% MECHANICAL|100% Completed

1.Electrical panel board fixing in progress.. earth pit work in progress 2.civil work 89%completed

GPS Cordinates

Latitude : 9.8376929

Longitude : 76.4003886

Accuracy : 3.4709999561309814

Meenu .E. S
Date: 17/10/2022

Work in progress | 0% Completed

100.00% CIVIL|100% Completed

100.00% ELECTRICAL|100% Completed

100.00% MECHANICAL|100% Completed

1.civil work -89%completed 2.electrical panel fixing in progress

GPS Cordinates

Latitude : 9.9018162

Longitude : 76.3849103

Accuracy : 12.081999778747559

Meenu .E. S
Date: 10/10/2022

Work in progress | 85% Completed

100.00% MECHANICAL|100% Completed

100.00% ELECTRICAL|100% Completed

100.00% CIVIL|100% Completed

1.carporch tiling work completed.tile pointing work in progress 2.electrical work in progress

Attached images

img

Meenu .E. S
Date: 03/10/2022

Work in progress | 85% Completed

100.00% CIVIL|100% Completed

100.00% ELECTRICAL|100% Completed

100.00% MECHANICAL|100% Completed

1.road tarring completed 2.building carporch tiling work progressing

Attached images

img

Meenu .E. S
Date: 25/09/2022

Work in progress | 84% Completed

100.00% CIVIL|100% Completed

100.00% ELECTRICAL|100% Completed

100.00% MECHANICAL|100% Completed

1.road tarring work completed.

Attached images

img

Meenu .E. S
Date: 18/09/2022

Work in progress | 82% Completed

100.00% MECHANICAL|100% Completed

100.00% ELECTRICAL|100% Completed

100.00% CIVIL|100% Completed

1.road work WMM COMPLETED, SIDE KERB laying completed 2.front gate ACP WORK COMPLETED

GPS Cordinates

Latitude : 8.9311176

Longitude : 76.6437134

Accuracy : 31.045000076293945

Meenu .E. S
Date: 04/09/2023

Work has been completed | 0% Completed

1.all work completed

Meenu .E. S
Date: 04/09/2023

Work has been completed | 0% Completed

1.all work completed

Meenu .E. S
Date: 04/09/2023

Work has been completed | 0% Completed

1.all work completed

Meenu .E. S
Date: 04/09/2023

Work has been completed | 0% Completed

1.all work completed

Meenu .E. S
Date: 04/09/2023

Work has been completed | 0% Completed

1.all work completed

Meenu .E. S
Date: 04/09/2023

Work has been completed | 0% Completed

1.all work completed

Meenu .E. S
Date: 04/09/2023

Work has been completed | 0% Completed

1.all work completed

Meenu .E. S
Date: 04/09/2023

Work has been completed | 0% Completed

1.all work completed

Meenu .E. S
Date: 04/09/2023

Work has been completed | 0% Completed

1.all work completed

Meenu .E. S
Date: 10/07/2023

Work has been completed | 0% Completed

Site handover to client on 1/06/2023

Meenu .E. S
Date: 10/07/2023

Work has been completed | 0% Completed

Site handover to client on 1/06/2023

Meenu .E. S
Date: 10/07/2023

Work has been completed | 0% Completed

Site handover to client on 1/06/2023

Meenu .E. S
Date: 10/07/2023

Work has been completed | 0% Completed

Site handover to client on 1/06/2023

Meenu .E. S
Date: 10/07/2023

Work has been completed | 0% Completed

Site handover to client on 1/06/2023

Meenu .E. S
Date: 10/07/2023

Work has been completed | 0% Completed

Site handover to client on 1/06/2023

Meenu .E. S
Date: 10/07/2023

Work has been completed | 0% Completed

Site handover to client on 1/06/2023

Meenu .E. S
Date: 10/07/2023

Work has been completed | 0% Completed

Site handover to client on 1/06/2023

Meenu .E. S
Date: 10/07/2023

Work has been completed | 0% Completed

Site handover to client on 1/06/2023

Meenu .E. S
Date: 12/06/2023

Work has been completed | 0% Completed

Site handover to client on 1/06/2023

Meenu .E. S
Date: 12/06/2023

Work has been completed | 0% Completed

Site handover to client on 1/06/2023

Meenu .E. S
Date: 12/06/2023

Work has been completed | 0% Completed

Site handover to client on 1/06/2023

Meenu .E. S
Date: 12/06/2023

Work has been completed | 0% Completed

Site handover to client on 1/06/2023

Meenu .E. S
Date: 12/06/2023

Work has been completed | 0% Completed

Site handover to client on 1/06/2023

Meenu .E. S
Date: 12/06/2023

Work has been completed | 0% Completed

Site handover to client on 1/06/2023

Meenu .E. S
Date: 12/06/2023

Work has been completed | 0% Completed

Site handover to client on 1/06/2023

Meenu .E. S
Date: 12/06/2023

Work has been completed | 0% Completed

Site handover to client on 1/06/2023

Meenu .E. S
Date: 12/06/2023

Work has been completed | 0% Completed

Site handover to client on 1/06/2023

Meenu .E. S
Date: 05/06/2023

Work in progress | 0% Completed

1.site handover to client on 1/06/2023

Meenu .E. S
Date: 05/06/2023

Work in progress | 0% Completed

1.site handover to client on 1/06/2023

Meenu .E. S
Date: 05/06/2023

Work in progress | 0% Completed

1.site handover to client on 1/06/2023

Meenu .E. S
Date: 05/06/2023

Work in progress | 0% Completed

1.site handover to client on 1/06/2023

Meenu .E. S
Date: 05/06/2023

Work in progress | 0% Completed

1.site handover to client on 1/06/2023

Meenu .E. S
Date: 05/06/2023

Work in progress | 0% Completed

1.site handover to client on 1/06/2023

Meenu .E. S
Date: 05/06/2023

Work in progress | 0% Completed

1.site handover to client on 1/06/2023

Meenu .E. S
Date: 05/06/2023

Work in progress | 0% Completed

1.site handover to client on 1/06/2023

Meenu .E. S
Date: 05/06/2023

Work in progress | 0% Completed

1.site handover to client on 1/06/2023

Meenu .E. S
Date: 29/05/2023

Work in progress | 0% Completed

Site clearing work completed for the inauguration program.

Meenu .E. S
Date: 29/05/2023

Work in progress | 0% Completed

Site clearing work completed for the inauguration program.

Meenu .E. S
Date: 29/05/2023

Work in progress | 0% Completed

Site clearing work completed for the inauguration program.

Meenu .E. S
Date: 29/05/2023

Work in progress | 0% Completed

Site clearing work completed for the inauguration program.

Meenu .E. S
Date: 29/05/2023

Work in progress | 0% Completed

Site clearing work completed for the inauguration program.

Meenu .E. S
Date: 29/05/2023

Work in progress | 0% Completed

Site clearing work completed for the inauguration program.

Meenu .E. S
Date: 29/05/2023

Work in progress | 0% Completed

Site clearing work completed for the inauguration program.

Meenu .E. S
Date: 29/05/2023

Work in progress | 0% Completed

Site clearing work completed for the inauguration program.

Meenu .E. S
Date: 29/05/2023

Work in progress | 0% Completed

Site clearing work completed for the inauguration program.

Meenu .E. S
Date: 22/05/2023

Work in progress | 0% Completed

1.site final clearance work in progress

Attached images

img

Meenu .E. S
Date: 22/05/2023

Work in progress | 0% Completed

1.site final clearance work in progress

Attached images

img

Meenu .E. S
Date: 22/05/2023

Work in progress | 0% Completed

1.site final clearance work in progress

Attached images

img

Meenu .E. S
Date: 22/05/2023

Work in progress | 0% Completed

1.site final clearance work in progress

Attached images

img

Meenu .E. S
Date: 22/05/2023

Work in progress | 0% Completed

1.site final clearance work in progress

Attached images

img

Meenu .E. S
Date: 22/05/2023

Work in progress | 0% Completed

1.site final clearance work in progress

Attached images

img

Meenu .E. S
Date: 22/05/2023

Work in progress | 0% Completed

1.site final clearance work in progress

Attached images

img

Meenu .E. S
Date: 22/05/2023

Work in progress | 0% Completed

1.site final clearance work in progress

Attached images

img

Meenu .E. S
Date: 22/05/2023

Work in progress | 0% Completed

1.site final clearance work in progress

Attached images

img

Meenu .E. S
Date: 15/05/2023

Work in progress | 0% Completed

1.snag list rectification works in progress

Meenu .E. S
Date: 15/05/2023

Work in progress | 0% Completed

1.snag list rectification works in progress

Meenu .E. S
Date: 15/05/2023

Work in progress | 0% Completed

1.snag list rectification works in progress

Meenu .E. S
Date: 15/05/2023

Work in progress | 0% Completed

1.snag list rectification works in progress

Meenu .E. S
Date: 15/05/2023

Work in progress | 0% Completed

1.snag list rectification works in progress

Meenu .E. S
Date: 15/05/2023

Work in progress | 0% Completed

1.snag list rectification works in progress

Meenu .E. S
Date: 15/05/2023

Work in progress | 0% Completed

1.snag list rectification works in progress

Meenu .E. S
Date: 15/05/2023

Work in progress | 0% Completed

1.snag list rectification works in progress

Meenu .E. S
Date: 15/05/2023

Work in progress | 0% Completed

1.snag list rectification works in progress

Meenu .E. S
Date: 08/05/2023

Work in progress | 0% Completed

1.snag list rectification works in progress

Meenu .E. S
Date: 08/05/2023

Work in progress | 0% Completed

1.snag list rectification works in progress

Meenu .E. S
Date: 08/05/2023

Work in progress | 0% Completed

1.snag list rectification works in progress

Meenu .E. S
Date: 08/05/2023

Work in progress | 0% Completed

1.snag list rectification works in progress

Meenu .E. S
Date: 08/05/2023

Work in progress | 0% Completed

1.snag list rectification works in progress

Meenu .E. S
Date: 08/05/2023

Work in progress | 0% Completed

1.snag list rectification works in progress

Meenu .E. S
Date: 08/05/2023

Work in progress | 0% Completed

1.snag list rectification works in progress

Meenu .E. S
Date: 08/05/2023

Work in progress | 0% Completed

1.snag list rectification works in progress

Meenu .E. S
Date: 08/05/2023

Work in progress | 0% Completed

1.snag list rectification works in progress

Meenu .E. S
Date: 02/05/2023

Work in progress | 0% Completed

1.building rectification work in progress

Meenu .E. S
Date: 02/05/2023

Work in progress | 0% Completed

1.building rectification work in progress

Meenu .E. S
Date: 02/05/2023

Work in progress | 0% Completed

1.building rectification work in progress

Meenu .E. S
Date: 02/05/2023

Work in progress | 0% Completed

1.building rectification work in progress

Meenu .E. S
Date: 02/05/2023

Work in progress | 0% Completed

1.building rectification work in progress

Meenu .E. S
Date: 02/05/2023

Work in progress | 0% Completed

1.building rectification work in progress

Meenu .E. S
Date: 02/05/2023

Work in progress | 0% Completed

1.building rectification work in progress

Meenu .E. S
Date: 02/05/2023

Work in progress | 0% Completed

1.building rectification work in progress

Meenu .E. S
Date: 02/05/2023

Work in progress | 0% Completed

1.building rectification work in progress

Meenu .E. S
Date: 24/04/2023

Work in progress | 0% Completed

1.snag list rectification works in progress

Meenu .E. S
Date: 24/04/2023

Work in progress | 0% Completed

1.snag list rectification works in progress

Meenu .E. S
Date: 24/04/2023

Work in progress | 0% Completed

1.snag list rectification works in progress

Meenu .E. S
Date: 24/04/2023

Work in progress | 0% Completed

1.snag list rectification works in progress

Meenu .E. S
Date: 24/04/2023

Work in progress | 0% Completed

1.snag list rectification works in progress

Meenu .E. S
Date: 24/04/2023

Work in progress | 0% Completed

1.snag list rectification works in progress

Meenu .E. S
Date: 24/04/2023

Work in progress | 0% Completed

1.snag list rectification works in progress

Meenu .E. S
Date: 24/04/2023

Work in progress | 0% Completed

1.snag list rectification works in progress

Meenu .E. S
Date: 24/04/2023

Work in progress | 0% Completed

1.snag list rectification works in progress

Meenu .E. S
Date: 17/04/2023

Work in progress | 0% Completed

1.main building rectification works in progress

Meenu .E. S
Date: 17/04/2023

Work in progress | 0% Completed

1.main building rectification works in progress

Meenu .E. S
Date: 17/04/2023

Work in progress | 0% Completed

1.main building rectification works in progress

Meenu .E. S
Date: 17/04/2023

Work in progress | 0% Completed

1.main building rectification works in progress

Meenu .E. S
Date: 17/04/2023

Work in progress | 0% Completed

1.main building rectification works in progress

Meenu .E. S
Date: 17/04/2023

Work in progress | 0% Completed

1.main building rectification works in progress

Meenu .E. S
Date: 17/04/2023

Work in progress | 0% Completed

1.main building rectification works in progress

Meenu .E. S
Date: 17/04/2023

Work in progress | 0% Completed

1.main building rectification works in progress

Meenu .E. S
Date: 17/04/2023

Work in progress | 0% Completed

1.main building rectification works in progress

Meenu .E. S
Date: 10/04/2023

Work in progress | 0% Completed

1.fire fighting works in progress

Attached images

img

Meenu .E. S
Date: 10/04/2023

Work in progress | 0% Completed

1.fire fighting works in progress

Attached images

img

Meenu .E. S
Date: 10/04/2023

Work in progress | 0% Completed

1.fire fighting works in progress

Attached images

img

Meenu .E. S
Date: 10/04/2023

Work in progress | 0% Completed

1.fire fighting works in progress

Attached images

img

Meenu .E. S
Date: 10/04/2023

Work in progress | 0% Completed

1.fire fighting works in progress

Attached images

img

Meenu .E. S
Date: 10/04/2023

Work in progress | 0% Completed

1.fire fighting works in progress

Attached images

img

Meenu .E. S
Date: 10/04/2023

Work in progress | 0% Completed

1.fire fighting works in progress

Attached images

img

Meenu .E. S
Date: 10/04/2023

Work in progress | 0% Completed

1.fire fighting works in progress

Attached images

img

Meenu .E. S
Date: 10/04/2023

Work in progress | 0% Completed

1.fire fighting works in progress

Attached images

img

Meenu .E. S
Date: 03/04/2023

Work in progress | 0% Completed

1.main building fire fighting works in progress

Attached images

img

Meenu .E. S
Date: 03/04/2023

Work in progress | 0% Completed

1.main building fire fighting works in progress

Attached images

img

Meenu .E. S
Date: 03/04/2023

Work in progress | 0% Completed

1.main building fire fighting works in progress

Attached images

img

Meenu .E. S
Date: 03/04/2023

Work in progress | 0% Completed

1.main building fire fighting works in progress

Attached images

img

Meenu .E. S
Date: 03/04/2023

Work in progress | 0% Completed

1.main building fire fighting works in progress

Attached images

img

Meenu .E. S
Date: 03/04/2023

Work in progress | 0% Completed

1.main building fire fighting works in progress

Attached images

img

Meenu .E. S
Date: 03/04/2023

Work in progress | 0% Completed

1.main building fire fighting works in progress

Attached images

img

Meenu .E. S
Date: 03/04/2023

Work in progress | 0% Completed

1.main building fire fighting works in progress

Attached images

img

Meenu .E. S
Date: 03/04/2023

Work in progress | 0% Completed

1.main building fire fighting works in progress

Attached images

img

Meenu .E. S
Date: 27/03/2023

Work in progress | 0% Completed

1.main building fire fighting works -overhead tank placing platform pcc works completed

Attached images

img

Meenu .E. S
Date: 27/03/2023

Work in progress | 0% Completed

1.main building fire fighting works -overhead tank placing platform pcc works completed

Attached images

img

Meenu .E. S
Date: 27/03/2023

Work in progress | 0% Completed

1.main building fire fighting works -overhead tank placing platform pcc works completed

Attached images

img

Meenu .E. S
Date: 27/03/2023

Work in progress | 0% Completed

1.main building fire fighting works -overhead tank placing platform pcc works completed

Attached images

img

Meenu .E. S
Date: 27/03/2023

Work in progress | 0% Completed

1.main building fire fighting works -overhead tank placing platform pcc works completed

Attached images

img

Meenu .E. S
Date: 27/03/2023

Work in progress | 0% Completed

1.main building fire fighting works -overhead tank placing platform pcc works completed

Attached images

img

Meenu .E. S
Date: 27/03/2023

Work in progress | 0% Completed

1.main building fire fighting works -overhead tank placing platform pcc works completed

Attached images

img

Meenu .E. S
Date: 27/03/2023

Work in progress | 0% Completed

1.main building fire fighting works -overhead tank placing platform pcc works completed

Attached images

img

Meenu .E. S
Date: 27/03/2023

Work in progress | 0% Completed

1.main building fire fighting works -overhead tank placing platform pcc works completed

Attached images

img

Meenu .E. S
Date: 20/03/2023

Work in progress | 0% Completed

1.main building fire fighting works -fire tank placing platform pcc works in progress

Attached images

img

Meenu .E. S
Date: 20/03/2023

Work in progress | 0% Completed

1.main building fire fighting works -fire tank placing platform pcc works in progress

Attached images

img

Meenu .E. S
Date: 20/03/2023

Work in progress | 0% Completed

1.main building fire fighting works -fire tank placing platform pcc works in progress

Attached images

img

Meenu .E. S
Date: 20/03/2023

Work in progress | 0% Completed

1.main building fire fighting works -fire tank placing platform pcc works in progress

Attached images

img

Meenu .E. S
Date: 20/03/2023

Work in progress | 0% Completed

1.main building fire fighting works -fire tank placing platform pcc works in progress

Attached images

img

Meenu .E. S
Date: 20/03/2023

Work in progress | 0% Completed

1.main building fire fighting works -fire tank placing platform pcc works in progress

Attached images

img

Meenu .E. S
Date: 20/03/2023

Work in progress | 0% Completed

1.main building fire fighting works -fire tank placing platform pcc works in progress

Attached images

img

Meenu .E. S
Date: 20/03/2023

Work in progress | 0% Completed

1.main building fire fighting works -fire tank placing platform pcc works in progress

Attached images

img

Meenu .E. S
Date: 20/03/2023

Work in progress | 0% Completed

1.main building fire fighting works -fire tank placing platform pcc works in progress

Attached images

img

Meenu .E. S
Date: 13/03/2023

Work in progress | 0% Completed

1.main building fire fighting works are pending 2.exterior and interior final finishing works in progress

Meenu .E. S
Date: 13/03/2023

Work in progress | 0% Completed

1.main building fire fighting works are pending 2.exterior and interior final finishing works in progress

Meenu .E. S
Date: 13/03/2023

Work in progress | 0% Completed

1.main building fire fighting works are pending 2.exterior and interior final finishing works in progress

Meenu .E. S
Date: 13/03/2023

Work in progress | 0% Completed

1.main building fire fighting works are pending 2.exterior and interior final finishing works in progress

Meenu .E. S
Date: 13/03/2023

Work in progress | 0% Completed

1.main building fire fighting works are pending 2.exterior and interior final finishing works in progress

Meenu .E. S
Date: 13/03/2023

Work in progress | 0% Completed

1.main building fire fighting works are pending 2.exterior and interior final finishing works in progress

Meenu .E. S
Date: 13/03/2023

Work in progress | 0% Completed

1.main building fire fighting works are pending 2.exterior and interior final finishing works in progress

Meenu .E. S
Date: 13/03/2023

Work in progress | 0% Completed

1.main building fire fighting works are pending 2.exterior and interior final finishing works in progress

Meenu .E. S
Date: 13/03/2023

Work in progress | 0% Completed

1.main building fire fighting works are pending 2.exterior and interior final finishing works in progress

Meenu .E. S
Date: 06/03/2023

Work in progress | 0% Completed

1.exterior and interior final finishing works in progress

Meenu .E. S
Date: 06/03/2023

Work in progress | 0% Completed

1.exterior and interior final finishing works in progress

Meenu .E. S
Date: 06/03/2023

Work in progress | 0% Completed

1.exterior and interior final finishing works in progress

Meenu .E. S
Date: 06/03/2023

Work in progress | 0% Completed

1.exterior and interior final finishing works in progress

Meenu .E. S
Date: 06/03/2023

Work in progress | 0% Completed

1.exterior and interior final finishing works in progress

Meenu .E. S
Date: 06/03/2023

Work in progress | 0% Completed

1.exterior and interior final finishing works in progress

Meenu .E. S
Date: 06/03/2023

Work in progress | 0% Completed

1.exterior and interior final finishing works in progress

Meenu .E. S
Date: 06/03/2023

Work in progress | 0% Completed

1.exterior and interior final finishing works in progress

Meenu .E. S
Date: 06/03/2023

Work in progress | 0% Completed

1.exterior and interior final finishing works in progress

Meenu .E. S
Date: 27/02/2023

Work in progress | 0% Completed

1.exterior and interior final finishing works in progress

Meenu .E. S
Date: 27/02/2023

Work in progress | 0% Completed

1.exterior and interior final finishing works in progress

Meenu .E. S
Date: 27/02/2023

Work in progress | 0% Completed

1.exterior and interior final finishing works in progress

Meenu .E. S
Date: 27/02/2023

Work in progress | 0% Completed

1.exterior and interior final finishing works in progress

Meenu .E. S
Date: 27/02/2023

Work in progress | 0% Completed

1.exterior and interior final finishing works in progress

Meenu .E. S
Date: 27/02/2023

Work in progress | 0% Completed

1.exterior and interior final finishing works in progress

Meenu .E. S
Date: 27/02/2023

Work in progress | 0% Completed

1.exterior and interior final finishing works in progress

Meenu .E. S
Date: 27/02/2023

Work in progress | 0% Completed

1.exterior and interior final finishing works in progress

Meenu .E. S
Date: 27/02/2023

Work in progress | 0% Completed

1.exterior and interior final finishing works in progress

Meenu .E. S
Date: 20/02/2023

Work in progress | 0% Completed

Painting works in progress

Meenu .E. S
Date: 20/02/2023

Work in progress | 0% Completed

Painting works in progress

Meenu .E. S
Date: 20/02/2023

Work in progress | 0% Completed

Painting works in progress

Meenu .E. S
Date: 20/02/2023

Work in progress | 0% Completed

Painting works in progress

Meenu .E. S
Date: 20/02/2023

Work in progress | 0% Completed

Painting works in progress

Meenu .E. S
Date: 20/02/2023

Work in progress | 0% Completed

Painting works in progress

Meenu .E. S
Date: 20/02/2023

Work in progress | 0% Completed

Painting works in progress

Meenu .E. S
Date: 20/02/2023

Work in progress | 0% Completed

Painting works in progress

Meenu .E. S
Date: 20/02/2023

Work in progress | 0% Completed

Painting works in progress

Meenu .E. S
Date: 13/02/2023

Work in progress | 0% Completed

1.painting works exterior and interior final coat in progress

Meenu .E. S
Date: 13/02/2023

Work in progress | 0% Completed

1.painting works exterior and interior final coat in progress

Meenu .E. S
Date: 13/02/2023

Work in progress | 0% Completed

1.painting works exterior and interior final coat in progress

Meenu .E. S
Date: 13/02/2023

Work in progress | 0% Completed

1.painting works exterior and interior final coat in progress

Meenu .E. S
Date: 13/02/2023

Work in progress | 0% Completed

1.painting works exterior and interior final coat in progress

Meenu .E. S
Date: 13/02/2023

Work in progress | 0% Completed

1.painting works exterior and interior final coat in progress

Meenu .E. S
Date: 13/02/2023

Work in progress | 0% Completed

1.painting works exterior and interior final coat in progress

Meenu .E. S
Date: 13/02/2023

Work in progress | 0% Completed

1.painting works exterior and interior final coat in progress

Meenu .E. S
Date: 13/02/2023

Work in progress | 0% Completed

1.painting works exterior and interior final coat in progress

Meenu .E. S
Date: 06/02/2023

Work in progress | 0% Completed

1.painting (exterior and interior) final coat in progress

Meenu .E. S
Date: 06/02/2023

Work in progress | 0% Completed

1.painting (exterior and interior) final coat in progress

Meenu .E. S
Date: 06/02/2023

Work in progress | 0% Completed

1.painting (exterior and interior) final coat in progress

Meenu .E. S
Date: 06/02/2023

Work in progress | 0% Completed

1.painting (exterior and interior) final coat in progress

Meenu .E. S
Date: 06/02/2023

Work in progress | 0% Completed

1.painting (exterior and interior) final coat in progress

Meenu .E. S
Date: 06/02/2023

Work in progress | 0% Completed

1.painting (exterior and interior) final coat in progress

Meenu .E. S
Date: 06/02/2023

Work in progress | 0% Completed

1.painting (exterior and interior) final coat in progress

Meenu .E. S
Date: 06/02/2023

Work in progress | 0% Completed

1.painting (exterior and interior) final coat in progress

Meenu .E. S
Date: 06/02/2023

Work in progress | 0% Completed

1.painting (exterior and interior) final coat in progress

Meenu .E. S
Date: 30/01/2023

Work in progress | 0% Completed

1.CCTV Camera fittings completed 2.final coat painting works in progress

Meenu .E. S
Date: 30/01/2023

Work in progress | 0% Completed

1.CCTV Camera fittings completed 2.final coat painting works in progress

Meenu .E. S
Date: 30/01/2023

Work in progress | 0% Completed

1.CCTV Camera fittings completed 2.final coat painting works in progress

Meenu .E. S
Date: 30/01/2023

Work in progress | 0% Completed

1.CCTV Camera fittings completed 2.final coat painting works in progress

Meenu .E. S
Date: 30/01/2023

Work in progress | 0% Completed

1.CCTV Camera fittings completed 2.final coat painting works in progress

Meenu .E. S
Date: 30/01/2023

Work in progress | 0% Completed

1.CCTV Camera fittings completed 2.final coat painting works in progress

Meenu .E. S
Date: 30/01/2023

Work in progress | 0% Completed

1.CCTV Camera fittings completed 2.final coat painting works in progress

Meenu .E. S
Date: 30/01/2023

Work in progress | 0% Completed

1.CCTV Camera fittings completed 2.final coat painting works in progress

Meenu .E. S
Date: 30/01/2023

Work in progress | 0% Completed

1.CCTV Camera fittings completed 2.final coat painting works in progress

Meenu .E. S
Date: 23/01/2023

Work in progress | 0% Completed

1.ELV Cable laying excavation work in progress

Meenu .E. S
Date: 23/01/2023

Work in progress | 0% Completed

1.ELV Cable laying excavation work in progress

Meenu .E. S
Date: 23/01/2023

Work in progress | 0% Completed

1.ELV Cable laying excavation work in progress

Meenu .E. S
Date: 23/01/2023

Work in progress | 0% Completed

1.ELV Cable laying excavation work in progress

Meenu .E. S
Date: 23/01/2023

Work in progress | 0% Completed

1.ELV Cable laying excavation work in progress

Meenu .E. S
Date: 23/01/2023

Work in progress | 0% Completed

1.ELV Cable laying excavation work in progress

Meenu .E. S
Date: 23/01/2023

Work in progress | 0% Completed

1.ELV Cable laying excavation work in progress

Meenu .E. S
Date: 23/01/2023

Work in progress | 0% Completed

1.ELV Cable laying excavation work in progress

Meenu .E. S
Date: 23/01/2023

Work in progress | 0% Completed

1.ELV Cable laying excavation work in progress

Meenu .E. S
Date: 16/01/2023

Work in progress | 0% Completed

1.CCTV cable laying excavation work in progress

Meenu .E. S
Date: 16/01/2023

Work in progress | 0% Completed

1.CCTV cable laying excavation work in progress

Meenu .E. S
Date: 16/01/2023

Work in progress | 0% Completed

1.CCTV cable laying excavation work in progress

Meenu .E. S
Date: 16/01/2023

Work in progress | 0% Completed

1.CCTV cable laying excavation work in progress

Meenu .E. S
Date: 16/01/2023

Work in progress | 0% Completed

1.CCTV cable laying excavation work in progress

Meenu .E. S
Date: 16/01/2023

Work in progress | 0% Completed

1.CCTV cable laying excavation work in progress

Meenu .E. S
Date: 16/01/2023

Work in progress | 0% Completed

1.CCTV cable laying excavation work in progress

Meenu .E. S
Date: 16/01/2023

Work in progress | 0% Completed

1.CCTV cable laying excavation work in progress

Meenu .E. S
Date: 16/01/2023

Work in progress | 0% Completed

1.CCTV cable laying excavation work in progress

Meenu .E. S
Date: 09/01/2023

Work in progress | 0% Completed

1.Water treatment plant pipe connection works in progress 2.ELV CCTV Cable laying in progress 3.fire fighting works extinguishers fixing works completed

Attached images

img

Meenu .E. S
Date: 09/01/2023

Work in progress | 0% Completed

1.Water treatment plant pipe connection works in progress 2.ELV CCTV Cable laying in progress 3.fire fighting works extinguishers fixing works completed

Attached images

img

Meenu .E. S
Date: 09/01/2023

Work in progress | 0% Completed

1.Water treatment plant pipe connection works in progress 2.ELV CCTV Cable laying in progress 3.fire fighting works extinguishers fixing works completed

Attached images

img

Meenu .E. S
Date: 09/01/2023

Work in progress | 0% Completed

1.Water treatment plant pipe connection works in progress 2.ELV CCTV Cable laying in progress 3.fire fighting works extinguishers fixing works completed

Attached images

img

Meenu .E. S
Date: 09/01/2023

Work in progress | 0% Completed

1.Water treatment plant pipe connection works in progress 2.ELV CCTV Cable laying in progress 3.fire fighting works extinguishers fixing works completed

Attached images

img

Meenu .E. S
Date: 09/01/2023

Work in progress | 0% Completed

1.Water treatment plant pipe connection works in progress 2.ELV CCTV Cable laying in progress 3.fire fighting works extinguishers fixing works completed

Attached images

img

Meenu .E. S
Date: 09/01/2023

Work in progress | 0% Completed

1.Water treatment plant pipe connection works in progress 2.ELV CCTV Cable laying in progress 3.fire fighting works extinguishers fixing works completed

Attached images

img

Meenu .E. S
Date: 09/01/2023

Work in progress | 0% Completed

1.Water treatment plant pipe connection works in progress 2.ELV CCTV Cable laying in progress 3.fire fighting works extinguishers fixing works completed

Attached images

img

Meenu .E. S
Date: 09/01/2023

Work in progress | 0% Completed

1.Water treatment plant pipe connection works in progress 2.ELV CCTV Cable laying in progress 3.fire fighting works extinguishers fixing works completed

Attached images

img

Meenu .E. S
Date: 09/01/2023

Work in progress | 0% Completed

1.fire extinguishers fixing completed 2.ELVmain building CCTV cable laying in progress

Meenu .E. S
Date: 09/01/2023

Work in progress | 0% Completed

1.fire extinguishers fixing completed 2.ELVmain building CCTV cable laying in progress

Meenu .E. S
Date: 09/01/2023

Work in progress | 0% Completed

1.fire extinguishers fixing completed 2.ELVmain building CCTV cable laying in progress

Meenu .E. S
Date: 09/01/2023

Work in progress | 0% Completed

1.fire extinguishers fixing completed 2.ELVmain building CCTV cable laying in progress

Meenu .E. S
Date: 09/01/2023

Work in progress | 0% Completed

1.fire extinguishers fixing completed 2.ELVmain building CCTV cable laying in progress

Meenu .E. S
Date: 09/01/2023

Work in progress | 0% Completed

1.fire extinguishers fixing completed 2.ELVmain building CCTV cable laying in progress

Meenu .E. S
Date: 09/01/2023

Work in progress | 0% Completed

1.fire extinguishers fixing completed 2.ELVmain building CCTV cable laying in progress

Meenu .E. S
Date: 09/01/2023

Work in progress | 0% Completed

1.fire extinguishers fixing completed 2.ELVmain building CCTV cable laying in progress

Meenu .E. S
Date: 09/01/2023

Work in progress | 0% Completed

1.fire extinguishers fixing completed 2.ELVmain building CCTV cable laying in progress

Meenu .E. S
Date: 02/01/2023

Work in progress | 0% Completed

1.Exterior painting in progress 2.electrical final fittings in progress

Attached images

img img

Meenu .E. S
Date: 02/01/2023

Work in progress | 0% Completed

1.Exterior painting in progress 2.electrical final fittings in progress

Attached images

img img

Meenu .E. S
Date: 02/01/2023

Work in progress | 0% Completed

1.Exterior painting in progress 2.electrical final fittings in progress

Attached images

img img

Meenu .E. S
Date: 02/01/2023

Work in progress | 0% Completed

1.Exterior painting in progress 2.electrical final fittings in progress

Attached images

img img

Meenu .E. S
Date: 02/01/2023

Work in progress | 0% Completed

1.Exterior painting in progress 2.electrical final fittings in progress

Attached images

img img

Meenu .E. S
Date: 02/01/2023

Work in progress | 0% Completed

1.Exterior painting in progress 2.electrical final fittings in progress

Attached images

img img

Meenu .E. S
Date: 02/01/2023

Work in progress | 0% Completed

1.Exterior painting in progress 2.electrical final fittings in progress

Attached images

img img

Meenu .E. S
Date: 02/01/2023

Work in progress | 0% Completed

1.Exterior painting in progress 2.electrical final fittings in progress

Attached images

img img

Meenu .E. S
Date: 02/01/2023

Work in progress | 0% Completed

1.Exterior painting in progress 2.electrical final fittings in progress

Attached images

img img

Meenu .E. S
Date: 26/12/2022

Work in progress | 0% Completed

1.ELV works in progress 2.electrical fixing works in progress

Attached images

img img

Meenu .E. S
Date: 26/12/2022

Work in progress | 0% Completed

1.ELV works in progress 2.electrical fixing works in progress

Attached images

img img

Meenu .E. S
Date: 26/12/2022

Work in progress | 0% Completed

1.ELV works in progress 2.electrical fixing works in progress

Attached images

img img

Meenu .E. S
Date: 26/12/2022

Work in progress | 0% Completed

1.ELV works in progress 2.electrical fixing works in progress

Attached images

img img

Meenu .E. S
Date: 26/12/2022

Work in progress | 0% Completed

1.ELV works in progress 2.electrical fixing works in progress

Attached images

img img

Meenu .E. S
Date: 26/12/2022

Work in progress | 0% Completed

1.ELV works in progress 2.electrical fixing works in progress

Attached images

img img

Meenu .E. S
Date: 26/12/2022

Work in progress | 0% Completed

1.ELV works in progress 2.electrical fixing works in progress

Attached images

img img

Meenu .E. S
Date: 26/12/2022

Work in progress | 0% Completed

1.ELV works in progress 2.electrical fixing works in progress

Attached images

img img

Meenu .E. S
Date: 26/12/2022

Work in progress | 0% Completed

1.ELV works in progress 2.electrical fixing works in progress

Attached images

img img

Meenu .E. S
Date: 19/12/2022

Work in progress | 0% Completed

1.Front and back entrance door stainless steel grill works in progress 2.electrical final fittings in progress

Attached images

img img img

Meenu .E. S
Date: 19/12/2022

Work in progress | 0% Completed

1.Front and back entrance door stainless steel grill works in progress 2.electrical final fittings in progress

Attached images

img img img

Meenu .E. S
Date: 19/12/2022

Work in progress | 0% Completed

1.Front and back entrance door stainless steel grill works in progress 2.electrical final fittings in progress

Attached images

img img img

Meenu .E. S
Date: 19/12/2022

Work in progress | 0% Completed

1.Front and back entrance door stainless steel grill works in progress 2.electrical final fittings in progress

Attached images

img img img

Meenu .E. S
Date: 19/12/2022

Work in progress | 0% Completed

1.Front and back entrance door stainless steel grill works in progress 2.electrical final fittings in progress

Attached images

img img img

Meenu .E. S
Date: 19/12/2022

Work in progress | 0% Completed

1.Front and back entrance door stainless steel grill works in progress 2.electrical final fittings in progress

Attached images

img img img

Meenu .E. S
Date: 19/12/2022

Work in progress | 0% Completed

1.Front and back entrance door stainless steel grill works in progress 2.electrical final fittings in progress

Attached images

img img img

Meenu .E. S
Date: 19/12/2022

Work in progress | 0% Completed

1.Front and back entrance door stainless steel grill works in progress 2.electrical final fittings in progress

Attached images

img img img

Meenu .E. S
Date: 19/12/2022

Work in progress | 0% Completed

1.Front and back entrance door stainless steel grill works in progress 2.electrical final fittings in progress

Attached images

img img img

Meenu .E. S
Date: 12/12/2022

Work in progress | 0% Completed

Front entrance door stainless steel grill works in progress

Attached images

img img

Meenu .E. S
Date: 12/12/2022

Work in progress | 0% Completed

Front entrance door stainless steel grill works in progress

Attached images

img img

Meenu .E. S
Date: 12/12/2022

Work in progress | 0% Completed

Front entrance door stainless steel grill works in progress

Attached images

img img

Meenu .E. S
Date: 12/12/2022

Work in progress | 0% Completed

Front entrance door stainless steel grill works in progress

Attached images

img img

Meenu .E. S
Date: 12/12/2022

Work in progress | 0% Completed

Front entrance door stainless steel grill works in progress

Attached images

img img

Meenu .E. S
Date: 12/12/2022

Work in progress | 0% Completed

Front entrance door stainless steel grill works in progress

Attached images

img img

Meenu .E. S
Date: 12/12/2022

Work in progress | 0% Completed

Front entrance door stainless steel grill works in progress

Attached images

img img

Meenu .E. S
Date: 12/12/2022

Work in progress | 0% Completed

Front entrance door stainless steel grill works in progress

Attached images

img img

Meenu .E. S
Date: 12/12/2022

Work in progress | 0% Completed

Front entrance door stainless steel grill works in progress

Attached images

img img

Meenu .E. S
Date: 05/12/2022

Work in progress | 0% Completed

Smart classes projector and promeathene board fixing completed

Attached images

img img

Meenu .E. S
Date: 05/12/2022

Work in progress | 0% Completed

Smart classes projector and promeathene board fixing completed

Attached images

img img

Meenu .E. S
Date: 05/12/2022

Work in progress | 0% Completed

Smart classes projector and promeathene board fixing completed

Attached images

img img

Meenu .E. S
Date: 05/12/2022

Work in progress | 0% Completed

Smart classes projector and promeathene board fixing completed

Attached images

img img

Meenu .E. S
Date: 05/12/2022

Work in progress | 0% Completed

Smart classes projector and promeathene board fixing completed

Attached images

img img

Meenu .E. S
Date: 05/12/2022

Work in progress | 0% Completed

Smart classes projector and promeathene board fixing completed

Attached images

img img

Meenu .E. S
Date: 05/12/2022

Work in progress | 0% Completed

Smart classes projector and promeathene board fixing completed

Attached images

img img

Meenu .E. S
Date: 05/12/2022

Work in progress | 0% Completed

Smart classes projector and promeathene board fixing completed

Attached images

img img

Meenu .E. S
Date: 05/12/2022

Work in progress | 0% Completed

Smart classes projector and promeathene board fixing completed

Attached images

img img

Meenu .E. S
Date: 28/11/2022

Work in progress | 0% Completed

Smart classes projector and promeathene board fixing in progress

Attached images

img

Meenu .E. S
Date: 28/11/2022

Work in progress | 0% Completed

Smart classes projector and promeathene board fixing in progress

Attached images

img

Meenu .E. S
Date: 28/11/2022

Work in progress | 0% Completed

Smart classes projector and promeathene board fixing in progress

Attached images

img

Meenu .E. S
Date: 28/11/2022

Work in progress | 0% Completed

Smart classes projector and promeathene board fixing in progress

Attached images

img

Meenu .E. S
Date: 28/11/2022

Work in progress | 0% Completed

Smart classes projector and promeathene board fixing in progress

Attached images

img

Meenu .E. S
Date: 28/11/2022

Work in progress | 0% Completed

Smart classes projector and promeathene board fixing in progress

Attached images

img

Meenu .E. S
Date: 28/11/2022

Work in progress | 0% Completed

Smart classes projector and promeathene board fixing in progress

Attached images

img

Meenu .E. S
Date: 28/11/2022

Work in progress | 0% Completed

Smart classes projector and promeathene board fixing in progress

Attached images

img

Meenu .E. S
Date: 28/11/2022

Work in progress | 0% Completed

Smart classes projector and promeathene board fixing in progress

Attached images

img

Meenu .E. S
Date: 21/11/2022

Work in progress | 75% Completed

DG set and LT panel commissioning in progress.earth pit works in progress.

Meenu .E. S
Date: 21/11/2022

Work in progress | 75% Completed

DG set and LT panel commissioning in progress.earth pit works in progress.

Meenu .E. S
Date: 21/11/2022

Work in progress | 75% Completed

DG set and LT panel commissioning in progress.earth pit works in progress.

Meenu .E. S
Date: 21/11/2022

Work in progress | 75% Completed

DG set and LT panel commissioning in progress.earth pit works in progress.

Meenu .E. S
Date: 21/11/2022

Work in progress | 75% Completed

DG set and LT panel commissioning in progress.earth pit works in progress.

Meenu .E. S
Date: 21/11/2022

Work in progress | 75% Completed

DG set and LT panel commissioning in progress.earth pit works in progress.

Meenu .E. S
Date: 21/11/2022

Work in progress | 75% Completed

DG set and LT panel commissioning in progress.earth pit works in progress.

Meenu .E. S
Date: 21/11/2022

Work in progress | 75% Completed

DG set and LT panel commissioning in progress.earth pit works in progress.

Meenu .E. S
Date: 21/11/2022

Work in progress | 75% Completed

DG set and LT panel commissioning in progress.earth pit works in progress.

Meenu .E. S
Date: 31/10/2022

Work in progress | 89% Completed

Road work completed.front gate fixing and ACP work completed

Attached images

img img img

Meenu .E. S
Date: 31/10/2022

Work in progress | 89% Completed

Road work completed.front gate fixing and ACP work completed

Attached images

img img img

Meenu .E. S
Date: 31/10/2022

Work in progress | 89% Completed

Road work completed.front gate fixing and ACP work completed

Attached images

img img img

Meenu .E. S
Date: 31/10/2022

Work in progress | 89% Completed

Road work completed.front gate fixing and ACP work completed

Attached images

img img img

Meenu .E. S
Date: 31/10/2022

Work in progress | 89% Completed

Road work completed.front gate fixing and ACP work completed

Attached images

img img img

Meenu .E. S
Date: 31/10/2022

Work in progress | 89% Completed

Road work completed.front gate fixing and ACP work completed

Attached images

img img img

Meenu .E. S
Date: 31/10/2022

Work in progress | 89% Completed

Road work completed.front gate fixing and ACP work completed

Attached images

img img img

Meenu .E. S
Date: 31/10/2022

Work in progress | 89% Completed

Road work completed.front gate fixing and ACP work completed

Attached images

img img img

Meenu .E. S
Date: 31/10/2022

Work in progress | 89% Completed

Road work completed.front gate fixing and ACP work completed

Attached images

img img img

Meenu .E. S
Date: 31/10/2022

Work in progress | 65% Completed

Electrical panel board fixing in progress

Attached images

img

Meenu .E. S
Date: 31/10/2022

Work in progress | 65% Completed

Electrical panel board fixing in progress

Attached images

img

Meenu .E. S
Date: 31/10/2022

Work in progress | 65% Completed

Electrical panel board fixing in progress

Attached images

img

Meenu .E. S
Date: 31/10/2022

Work in progress | 65% Completed

Electrical panel board fixing in progress

Attached images

img

Meenu .E. S
Date: 31/10/2022

Work in progress | 65% Completed

Electrical panel board fixing in progress

Attached images

img

Meenu .E. S
Date: 31/10/2022

Work in progress | 65% Completed

Electrical panel board fixing in progress

Attached images

img

Meenu .E. S
Date: 31/10/2022

Work in progress | 65% Completed

Electrical panel board fixing in progress

Attached images

img

Meenu .E. S
Date: 31/10/2022

Work in progress | 65% Completed

Electrical panel board fixing in progress

Attached images

img

Meenu .E. S
Date: 31/10/2022

Work in progress | 65% Completed

Electrical panel board fixing in progress

Attached images

img

Meenu .E. S
Date: 24/10/2022

Work in progress | 0% Completed

1.Electrical panel board fixing in progress.. earth pit work in progress 2.civil work 89%completed

Meenu .E. S
Date: 24/10/2022

Work in progress | 0% Completed

1.Electrical panel board fixing in progress.. earth pit work in progress 2.civil work 89%completed

Meenu .E. S
Date: 24/10/2022

Work in progress | 0% Completed

1.Electrical panel board fixing in progress.. earth pit work in progress 2.civil work 89%completed

Meenu .E. S
Date: 24/10/2022

Work in progress | 0% Completed

1.Electrical panel board fixing in progress.. earth pit work in progress 2.civil work 89%completed

Meenu .E. S
Date: 24/10/2022

Work in progress | 0% Completed

1.Electrical panel board fixing in progress.. earth pit work in progress 2.civil work 89%completed

Meenu .E. S
Date: 24/10/2022

Work in progress | 0% Completed

1.Electrical panel board fixing in progress.. earth pit work in progress 2.civil work 89%completed

Meenu .E. S
Date: 24/10/2022

Work in progress | 0% Completed

1.Electrical panel board fixing in progress.. earth pit work in progress 2.civil work 89%completed

Meenu .E. S
Date: 24/10/2022

Work in progress | 0% Completed

1.Electrical panel board fixing in progress.. earth pit work in progress 2.civil work 89%completed

Meenu .E. S
Date: 24/10/2022

Work in progress | 0% Completed

1.Electrical panel board fixing in progress.. earth pit work in progress 2.civil work 89%completed

Meenu .E. S
Date: 17/10/2022

Work in progress | 0% Completed

1.civil work -89%completed 2.electrical panel fixing in progress

Meenu .E. S
Date: 17/10/2022

Work in progress | 0% Completed

1.civil work -89%completed 2.electrical panel fixing in progress

Meenu .E. S
Date: 17/10/2022

Work in progress | 0% Completed

1.civil work -89%completed 2.electrical panel fixing in progress

Meenu .E. S
Date: 17/10/2022

Work in progress | 0% Completed

1.civil work -89%completed 2.electrical panel fixing in progress

Meenu .E. S
Date: 17/10/2022

Work in progress | 0% Completed

1.civil work -89%completed 2.electrical panel fixing in progress

Meenu .E. S
Date: 17/10/2022

Work in progress | 0% Completed

1.civil work -89%completed 2.electrical panel fixing in progress

Meenu .E. S
Date: 17/10/2022

Work in progress | 0% Completed

1.civil work -89%completed 2.electrical panel fixing in progress

Meenu .E. S
Date: 17/10/2022

Work in progress | 0% Completed

1.civil work -89%completed 2.electrical panel fixing in progress

Meenu .E. S
Date: 17/10/2022

Work in progress | 0% Completed

1.civil work -89%completed 2.electrical panel fixing in progress

Meenu .E. S
Date: 10/10/2022

Work in progress | 0% Completed

1.carporch tiling work completed.tile pointing work in progress 2.electrical work in progress

Attached images

img

Meenu .E. S
Date: 10/10/2022

Work in progress | 0% Completed

1.carporch tiling work completed.tile pointing work in progress 2.electrical work in progress

Attached images

img

Meenu .E. S
Date: 10/10/2022

Work in progress | 0% Completed

1.carporch tiling work completed.tile pointing work in progress 2.electrical work in progress

Attached images

img

Meenu .E. S
Date: 10/10/2022

Work in progress | 0% Completed

1.carporch tiling work completed.tile pointing work in progress 2.electrical work in progress

Attached images

img

Meenu .E. S
Date: 10/10/2022

Work in progress | 0% Completed

1.carporch tiling work completed.tile pointing work in progress 2.electrical work in progress

Attached images

img

Meenu .E. S
Date: 10/10/2022

Work in progress | 0% Completed

1.carporch tiling work completed.tile pointing work in progress 2.electrical work in progress

Attached images

img

Meenu .E. S
Date: 10/10/2022

Work in progress | 0% Completed

1.carporch tiling work completed.tile pointing work in progress 2.electrical work in progress

Attached images

img

Meenu .E. S
Date: 10/10/2022

Work in progress | 0% Completed

1.carporch tiling work completed.tile pointing work in progress 2.electrical work in progress

Attached images

img

Meenu .E. S
Date: 10/10/2022

Work in progress | 0% Completed

1.carporch tiling work completed.tile pointing work in progress 2.electrical work in progress

Attached images

img

Meenu .E. S
Date: 03/10/2022

Work in progress | 0% Completed

1.road tarring completed 2.building carporch tiling work progressing

Attached images

img

Meenu .E. S
Date: 03/10/2022

Work in progress | 0% Completed

1.road tarring completed 2.building carporch tiling work progressing

Attached images

img

Meenu .E. S
Date: 03/10/2022

Work in progress | 0% Completed

1.road tarring completed 2.building carporch tiling work progressing

Attached images

img

Meenu .E. S
Date: 03/10/2022

Work in progress | 0% Completed

1.road tarring completed 2.building carporch tiling work progressing

Attached images

img

Meenu .E. S
Date: 03/10/2022

Work in progress | 0% Completed

1.road tarring completed 2.building carporch tiling work progressing

Attached images

img

Meenu .E. S
Date: 03/10/2022

Work in progress | 0% Completed

1.road tarring completed 2.building carporch tiling work progressing

Attached images

img

Meenu .E. S
Date: 03/10/2022

Work in progress | 0% Completed

1.road tarring completed 2.building carporch tiling work progressing

Attached images

img

Meenu .E. S
Date: 03/10/2022

Work in progress | 0% Completed

1.road tarring completed 2.building carporch tiling work progressing

Attached images

img

Meenu .E. S
Date: 03/10/2022

Work in progress | 0% Completed

1.road tarring completed 2.building carporch tiling work progressing

Attached images

img

Meenu .E. S
Date: 25/09/2022

Work in progress | 0% Completed

1.road tarring work completed.

Attached images

img

Meenu .E. S
Date: 25/09/2022

Work in progress | 0% Completed

1.road tarring work completed.

Attached images

img

Meenu .E. S
Date: 25/09/2022

Work in progress | 0% Completed

1.road tarring work completed.

Attached images

img

Meenu .E. S
Date: 25/09/2022

Work in progress | 0% Completed

1.road tarring work completed.

Attached images

img

Meenu .E. S
Date: 25/09/2022

Work in progress | 0% Completed

1.road tarring work completed.

Attached images

img

Meenu .E. S
Date: 25/09/2022

Work in progress | 0% Completed

1.road tarring work completed.

Attached images

img

Meenu .E. S
Date: 25/09/2022

Work in progress | 0% Completed

1.road tarring work completed.

Attached images

img

Meenu .E. S
Date: 25/09/2022

Work in progress | 0% Completed

1.road tarring work completed.

Attached images

img

Meenu .E. S
Date: 25/09/2022

Work in progress | 0% Completed

1.road tarring work completed.

Attached images

img

Meenu .E. S
Date: 18/09/2022

Work in progress | 0% Completed

1.road work WMM COMPLETED, SIDE KERB laying completed 2.front gate ACP WORK COMPLETED

Meenu .E. S
Date: 18/09/2022

Work in progress | 0% Completed

1.road work WMM COMPLETED, SIDE KERB laying completed 2.front gate ACP WORK COMPLETED

Meenu .E. S
Date: 18/09/2022

Work in progress | 0% Completed

1.road work WMM COMPLETED, SIDE KERB laying completed 2.front gate ACP WORK COMPLETED

Meenu .E. S
Date: 18/09/2022

Work in progress | 0% Completed

1.road work WMM COMPLETED, SIDE KERB laying completed 2.front gate ACP WORK COMPLETED

Meenu .E. S
Date: 18/09/2022

Work in progress | 0% Completed

1.road work WMM COMPLETED, SIDE KERB laying completed 2.front gate ACP WORK COMPLETED

Meenu .E. S
Date: 18/09/2022

Work in progress | 0% Completed

1.road work WMM COMPLETED, SIDE KERB laying completed 2.front gate ACP WORK COMPLETED

Meenu .E. S
Date: 18/09/2022

Work in progress | 0% Completed

1.road work WMM COMPLETED, SIDE KERB laying completed 2.front gate ACP WORK COMPLETED

Meenu .E. S
Date: 18/09/2022

Work in progress | 0% Completed

1.road work WMM COMPLETED, SIDE KERB laying completed 2.front gate ACP WORK COMPLETED

Meenu .E. S
Date: 18/09/2022

Work in progress | 0% Completed

1.road work WMM COMPLETED, SIDE KERB laying completed 2.front gate ACP WORK COMPLETED