Anu IT Admin |
Date: 22/04/2025 |
Work in progress | 1% Completed
|0% Completed
Rock excavation progressing
Anu IT Admin |
Date: 09/04/2025 |
Not Started
|0% Completed
agreement was executed on 02/04/2025 and the site was handed over on 04/04/2025
Anu IT Admin |
Date: 18/03/2025 |
Not Started
|0% Completed
Selection notice to be issued
Anu IT Admin |
Date: 11/03/2025 |
Not Started
|0% Completed
Selection notice to be issued
Anu IT Admin |
Date: 06/03/2025 |
Not Started
|0% Completed
Selection notice to be issued