Abhinandh P T |
Date: 11/07/2025 |
Work in progress | 27% Completed
|0% Completed
Ground Floor: Slab work has been completed. Truss work for the bathroom and washroom is currently in progress. Wall plastering work is also underway. PCC work under progress First Floor: Laterite masonry work is in progress. Lintel work has been completed toilet work under progress - solid block work of men's bathrooms completed - plastering work under progress
Abhinandh P T |
Date: 23/06/2025 |
Work in progress | 27% Completed
|0% Completed
Ground Floor: Slab work has been completed. Truss work for the bathroom and washroom is currently in progress. Wall plastering work is also underway. PCC work under progress First Floor: Laterite masonry work is in progress. Lintel work has been completed toilet work under progress - solid block work of men's bathrooms completed - plastering work under progress
Abhinandh P T |
Date: 18/06/2025 |
Work in progress | 27% Completed
|0% Completed
Ground Floor: Slab work has been completed. Truss work for the bathroom and washroom is currently in progress. Wall plastering work is also underway. PCC work under progress First Floor: Laterite masonry work is in progress. Lintel work has been completed toilet work under progress - solid block work of men's bathrooms completed - plastering work under progress
Abhinandh P T |
Date: 09/06/2025 |
Work in progress | 27% Completed
|0% Completed
Ground Floor: Slab work has been completed. Truss work for the bathroom and washroom is currently in progress. Wall plastering work is also underway. PCC work under progress First Floor: Laterite masonry work is in progress. Lintel work has been completed toilet work under progress - solid block work of men's bathrooms completed - plastering work under progress
Abhinandh P T |
Date: 02/06/2025 |
Work in progress | 27% Completed
|0% Completed
Ground Floor: Slab work has been completed. Truss work for the bathroom and washroom is currently in progress. Wall plastering work is also underway. PCC work under progress First Floor: Laterite masonry work is in progress. Lintel work has been completed toilet work under progress - solid block work of men's bathrooms completed - plastering work under progress
Abhinandh P T |
Date: 30/05/2025 |
Work in progress | 25% Completed
|0% Completed
Work in progress | 25% Completed | 19/05/2025 Ground Floor:Slab work has been completed. Truss work for the bathroom and washroom is currently in progress. Wall plastering work is also underway.PCC work under progress First Floor: Laterite masonry work is in progress. Lintel work has been completed
Abhinandh P T |
Date: 19/05/2025 |
Work in progress | 25% Completed
|0% Completed
Ground Floor:Slab work has been completed. Truss work for the bathroom and washroom is currently in progress. Wall plastering work is also underway.PCC work under progress First Floor: Laterite masonry work is in progress. Lintel work has been completed.
Abhinandh P T |
Date: 06/05/2025 |
Work in progress | 24% Completed
|0% Completed
first floor slab concrete completed second floor laterite work under progress and lintel concrete completed financial progress : 12%
Abhinandh P T |
Date: 28/04/2025 |
Work in progress | 24% Completed
|0% Completed
first floor slab concrete completed second floor laterite work under progress financial progress : 12%
Abhinandh P T |
Date: 28/04/2025 |
Work in progress | 24% Completed
|0% Completed
first floor slab concrete completed second floor laterite work under progress financial progress : 12%
Abhinandh P T |
Date: 10/04/2025 |
Work in progress | 23% Completed
|0% Completed
first floor slab concrete completed second floor laterite work under progress financial progress : 12%
Abhinandh P T |
Date: 01/04/2025 |
Work in progress | 23% Completed
|0% Completed
first floor slab concrete completed second floor laterite work under progress financial progress : 12%
Abhinandh P T |
Date: 17/03/2025 |
Work in progress | 23% Completed
|0% Completed
first floor slab concrete completed second floor laterite work under progress financial progress : 12%
MIDHUN DAS |
Date: 30/09/2024 |
Work in progress | 9% Completed
|0% Completed
plinth work completed
MIDHUN DAS |
Date: 12/09/2024 |
Work in progress | 9% Completed
|0% Completed
plinth belt concrete completed
MIDHUN DAS |
Date: 03/09/2024 |
Work in progress | 7% Completed
|0% Completed
shuttering for plinth belt in progress
MIDHUN DAS |
Date: 22/07/2024 |
Work in progress | 6% Completed
|0% Completed
foundation belt concrete completed
MIDHUN DAS |
Date: 17/07/2024 |
Work in progress | 6% Completed
|0% Completed
no work in progress due to heavy rain
MIDHUN DAS |
Date: 08/07/2024 |
Work in progress | 6% Completed
|0% Completed
BASEMENT BELT WORK AT A PART IS COMPLETED
MIDHUN DAS |
Date: 01/07/2024 |
Work in progress | 6% Completed
|0% Completed
BASEMENT BELT WORK AT A PART IS COMPLETED
MIDHUN DAS |
Date: 24/06/2024 |
Work in progress | 6% Completed
|0% Completed
RR work in progress
MIDHUN DAS |
Date: 18/06/2024 |
Work in progress | 6% Completed
|0% Completed
reinforcement work in progress
MIDHUN DAS |
Date: 11/06/2024 |
Work in progress | 5% Completed
|0% Completed
shuttering work in progress
MIDHUN DAS |
Date: 03/06/2024 |
Work in progress | 5% Completed
|0% Completed
RR work in progress
MIDHUN DAS |
Date: 30/05/2024 |
Work in progress | 5% Completed
|0% Completed
RR WORK IN PROGRESS
MIDHUN DAS |
Date: 20/05/2024 |
Work in progress | 3% Completed
|0% Completed
PCC work completed
MIDHUN DAS |
Date: 12/05/2024 |
Work in progress | 3% Completed
|0% Completed
Excavation work in progress
MIDHUN DAS |
Date: 06/05/2024 |
Work in progress | 3% Completed
|0% Completed
EARTH WORK IN PROGRESS
MIDHUN DAS |
Date: 29/04/2024 |
Work in progress | 3% Completed
|0% Completed
Earth work in progress
MIDHUN DAS |
Date: 22/04/2024 |
Work in progress | 3% Completed
|0% Completed
EARTHWORK EXCAVATION IN PROGRESS
MIDHUN DAS |
Date: 15/04/2024 |
Work in progress | 1% Completed
|0% Completed
no work in progress
MIDHUN DAS |
Date: 08/04/2024 |
Work in progress | 1% Completed
|0% Completed
no work in progress
MIDHUN DAS |
Date: 01/04/2024 |
Work in progress | 1% Completed
|0% Completed
Site clearance in progress
MIDHUN DAS |
Date: 18/03/2024 |
Work in progress | 1% Completed
|0% Completed
NO WORK IN PROGRESS
MIDHUN DAS |
Date: 11/03/2024 |
Work in progress | 1% Completed
|0% Completed
work is not started due to delay by the temple authorities to handerover the site by removing office building demolished waste and cutting of trees in the site.
MIDHUN DAS |
Date: 04/03/2024 |
Work in progress | 1% Completed
|0% Completed
work is not started due to delay by the temple authorities to handerover the site by removing office building demolished waste and cutting of trees in the site.
Abhinandh P T |
Date: 28/02/2024 |
Work in progress | 1% Completed
|0% Completed
SPT conducted