Abhinandh P T
Date: 11/07/2025

Work in progress | 27% Completed

% |0% Completed

Ground Floor: Slab work has been completed. Truss work for the bathroom and washroom is currently in progress. Wall plastering work is also underway. PCC work under progress First Floor: Laterite masonry work is in progress. Lintel work has been completed toilet work under progress - solid block work of men's bathrooms completed - plastering work under progress

Abhinandh P T
Date: 23/06/2025

Work in progress | 27% Completed

% |0% Completed

Ground Floor: Slab work has been completed. Truss work for the bathroom and washroom is currently in progress. Wall plastering work is also underway. PCC work under progress First Floor: Laterite masonry work is in progress. Lintel work has been completed toilet work under progress - solid block work of men's bathrooms completed - plastering work under progress

Abhinandh P T
Date: 18/06/2025

Work in progress | 27% Completed

% |0% Completed

Ground Floor: Slab work has been completed. Truss work for the bathroom and washroom is currently in progress. Wall plastering work is also underway. PCC work under progress First Floor: Laterite masonry work is in progress. Lintel work has been completed toilet work under progress - solid block work of men's bathrooms completed - plastering work under progress

Abhinandh P T
Date: 09/06/2025

Work in progress | 27% Completed

% |0% Completed

Ground Floor: Slab work has been completed. Truss work for the bathroom and washroom is currently in progress. Wall plastering work is also underway. PCC work under progress First Floor: Laterite masonry work is in progress. Lintel work has been completed toilet work under progress - solid block work of men's bathrooms completed - plastering work under progress

Abhinandh P T
Date: 02/06/2025

Work in progress | 27% Completed

% |0% Completed

Ground Floor: Slab work has been completed. Truss work for the bathroom and washroom is currently in progress. Wall plastering work is also underway. PCC work under progress First Floor: Laterite masonry work is in progress. Lintel work has been completed toilet work under progress - solid block work of men's bathrooms completed - plastering work under progress

Abhinandh P T
Date: 30/05/2025

Work in progress | 25% Completed

% |0% Completed

Work in progress | 25% Completed | 19/05/2025 Ground Floor:Slab work has been completed. Truss work for the bathroom and washroom is currently in progress. Wall plastering work is also underway.PCC work under progress First Floor: Laterite masonry work is in progress. Lintel work has been completed

Abhinandh P T
Date: 19/05/2025

Work in progress | 25% Completed

% |0% Completed

Ground Floor:Slab work has been completed. Truss work for the bathroom and washroom is currently in progress. Wall plastering work is also underway.PCC work under progress First Floor: Laterite masonry work is in progress. Lintel work has been completed.

Abhinandh P T
Date: 06/05/2025

Work in progress | 24% Completed

% |0% Completed

first floor slab concrete completed second floor laterite work under progress and lintel concrete completed financial progress : 12%

Abhinandh P T
Date: 28/04/2025

Work in progress | 24% Completed

% |0% Completed

first floor slab concrete completed second floor laterite work under progress financial progress : 12%

Abhinandh P T
Date: 28/04/2025

Work in progress | 24% Completed

% |0% Completed

first floor slab concrete completed second floor laterite work under progress financial progress : 12%

Abhinandh P T
Date: 10/04/2025

Work in progress | 23% Completed

% |0% Completed

first floor slab concrete completed second floor laterite work under progress financial progress : 12%

Abhinandh P T
Date: 01/04/2025

Work in progress | 23% Completed

% |0% Completed

first floor slab concrete completed second floor laterite work under progress financial progress : 12%

Abhinandh P T
Date: 17/03/2025

Work in progress | 23% Completed

% |0% Completed

first floor slab concrete completed second floor laterite work under progress financial progress : 12%

MIDHUN DAS
Date: 30/09/2024

Work in progress | 9% Completed

% |0% Completed

plinth work completed

MIDHUN DAS
Date: 12/09/2024

Work in progress | 9% Completed

% |0% Completed

plinth belt concrete completed

MIDHUN DAS
Date: 03/09/2024

Work in progress | 7% Completed

% |0% Completed

shuttering for plinth belt in progress

MIDHUN DAS
Date: 22/07/2024

Work in progress | 6% Completed

% |0% Completed

foundation belt concrete completed

MIDHUN DAS
Date: 17/07/2024

Work in progress | 6% Completed

% |0% Completed

no work in progress due to heavy rain

MIDHUN DAS
Date: 08/07/2024

Work in progress | 6% Completed

% |0% Completed

BASEMENT BELT WORK AT A PART IS COMPLETED

MIDHUN DAS
Date: 01/07/2024

Work in progress | 6% Completed

% |0% Completed

BASEMENT BELT WORK AT A PART IS COMPLETED

MIDHUN DAS
Date: 24/06/2024

Work in progress | 6% Completed

% |0% Completed

RR work in progress

MIDHUN DAS
Date: 18/06/2024

Work in progress | 6% Completed

% |0% Completed

reinforcement work in progress

MIDHUN DAS
Date: 11/06/2024

Work in progress | 5% Completed

% |0% Completed

shuttering work in progress

MIDHUN DAS
Date: 03/06/2024

Work in progress | 5% Completed

% |0% Completed

RR work in progress

MIDHUN DAS
Date: 30/05/2024

Work in progress | 5% Completed

% |0% Completed

RR WORK IN PROGRESS

MIDHUN DAS
Date: 20/05/2024

Work in progress | 3% Completed

% |0% Completed

PCC work completed

MIDHUN DAS
Date: 12/05/2024

Work in progress | 3% Completed

% |0% Completed

Excavation work in progress

MIDHUN DAS
Date: 06/05/2024

Work in progress | 3% Completed

% |0% Completed

EARTH WORK IN PROGRESS

MIDHUN DAS
Date: 29/04/2024

Work in progress | 3% Completed

% |0% Completed

Earth work in progress

MIDHUN DAS
Date: 22/04/2024

Work in progress | 3% Completed

% |0% Completed

EARTHWORK EXCAVATION IN PROGRESS

MIDHUN DAS
Date: 15/04/2024

Work in progress | 1% Completed

% |0% Completed

no work in progress

MIDHUN DAS
Date: 08/04/2024

Work in progress | 1% Completed

% |0% Completed

no work in progress

MIDHUN DAS
Date: 01/04/2024

Work in progress | 1% Completed

% |0% Completed

Site clearance in progress

MIDHUN DAS
Date: 18/03/2024

Work in progress | 1% Completed

% |0% Completed

NO WORK IN PROGRESS

MIDHUN DAS
Date: 11/03/2024

Work in progress | 1% Completed

% |0% Completed

work is not started due to delay by the temple authorities to handerover the site by removing office building demolished waste and cutting of trees in the site.

MIDHUN DAS
Date: 04/03/2024

Work in progress | 1% Completed

% |0% Completed

work is not started due to delay by the temple authorities to handerover the site by removing office building demolished waste and cutting of trees in the site.

Abhinandh P T
Date: 28/02/2024

Work in progress | 1% Completed

% |0% Completed

SPT conducted

Abhinandh P T
Date: 11/07/2025

Work in progress | 0% Completed

Ground Floor: Slab work has been completed. Truss work for the bathroom and washroom is currently in progress. Wall plastering work is also underway. PCC work under progress First Floor: Laterite masonry work is in progress. Lintel work has been completed toilet work under progress - solid block work of men's bathrooms completed - plastering work under progress

Abhinandh P T
Date: 23/06/2025

Work in progress | 0% Completed

Ground Floor: Slab work has been completed. Truss work for the bathroom and washroom is currently in progress. Wall plastering work is also underway. PCC work under progress First Floor: Laterite masonry work is in progress. Lintel work has been completed toilet work under progress - solid block work of men's bathrooms completed - plastering work under progress

Abhinandh P T
Date: 18/06/2025

Work in progress | 0% Completed

Ground Floor: Slab work has been completed. Truss work for the bathroom and washroom is currently in progress. Wall plastering work is also underway. PCC work under progress First Floor: Laterite masonry work is in progress. Lintel work has been completed toilet work under progress - solid block work of men's bathrooms completed - plastering work under progress

Abhinandh P T
Date: 09/06/2025

Work in progress | 0% Completed

Ground Floor: Slab work has been completed. Truss work for the bathroom and washroom is currently in progress. Wall plastering work is also underway. PCC work under progress First Floor: Laterite masonry work is in progress. Lintel work has been completed toilet work under progress - solid block work of men's bathrooms completed - plastering work under progress

Abhinandh P T
Date: 02/06/2025

Work in progress | 0% Completed

Ground Floor: Slab work has been completed. Truss work for the bathroom and washroom is currently in progress. Wall plastering work is also underway. PCC work under progress First Floor: Laterite masonry work is in progress. Lintel work has been completed toilet work under progress - solid block work of men's bathrooms completed - plastering work under progress

Abhinandh P T
Date: 30/05/2025

Work in progress | 0% Completed

Work in progress | 25% Completed | 19/05/2025 Ground Floor:Slab work has been completed. Truss work for the bathroom and washroom is currently in progress. Wall plastering work is also underway.PCC work under progress First Floor: Laterite masonry work is in progress. Lintel work has been completed

Abhinandh P T
Date: 19/05/2025

Work in progress | 0% Completed

Ground Floor:Slab work has been completed. Truss work for the bathroom and washroom is currently in progress. Wall plastering work is also underway.PCC work under progress First Floor: Laterite masonry work is in progress. Lintel work has been completed.

Abhinandh P T
Date: 06/05/2025

Work in progress | 0% Completed

first floor slab concrete completed second floor laterite work under progress and lintel concrete completed financial progress : 12%

Abhinandh P T
Date: 28/04/2025

Work in progress | 0% Completed

first floor slab concrete completed second floor laterite work under progress financial progress : 12%

Abhinandh P T
Date: 28/04/2025

Work in progress | 0% Completed

first floor slab concrete completed second floor laterite work under progress financial progress : 12%

Abhinandh P T
Date: 10/04/2025

Work in progress | 0% Completed

first floor slab concrete completed second floor laterite work under progress financial progress : 12%

Abhinandh P T
Date: 01/04/2025

Work in progress | 0% Completed

first floor slab concrete completed second floor laterite work under progress financial progress : 12%

Abhinandh P T
Date: 17/03/2025

Work in progress | 0% Completed

first floor slab concrete completed second floor laterite work under progress financial progress : 12%

MIDHUN DAS
Date: 30/09/2024

Work in progress | 0% Completed

plinth work completed

MIDHUN DAS
Date: 12/09/2024

Work in progress | 0% Completed

plinth belt concrete completed

MIDHUN DAS
Date: 03/09/2024

Work in progress | 0% Completed

shuttering for plinth belt in progress

MIDHUN DAS
Date: 22/07/2024

Work in progress | 0% Completed

foundation belt concrete completed

MIDHUN DAS
Date: 17/07/2024

Work in progress | 0% Completed

no work in progress due to heavy rain

MIDHUN DAS
Date: 08/07/2024

Work in progress | 0% Completed

BASEMENT BELT WORK AT A PART IS COMPLETED

MIDHUN DAS
Date: 01/07/2024

Work in progress | 0% Completed

BASEMENT BELT WORK AT A PART IS COMPLETED

MIDHUN DAS
Date: 24/06/2024

Work in progress | 0% Completed

RR work in progress

MIDHUN DAS
Date: 18/06/2024

Work in progress | 0% Completed

reinforcement work in progress

MIDHUN DAS
Date: 11/06/2024

Work in progress | 0% Completed

shuttering work in progress

MIDHUN DAS
Date: 03/06/2024

Work in progress | 0% Completed

RR work in progress

MIDHUN DAS
Date: 30/05/2024

Work in progress | 0% Completed

RR WORK IN PROGRESS

MIDHUN DAS
Date: 20/05/2024

Work in progress | 0% Completed

PCC work completed

MIDHUN DAS
Date: 12/05/2024

Work in progress | 0% Completed

Excavation work in progress

MIDHUN DAS
Date: 06/05/2024

Work in progress | 0% Completed

EARTH WORK IN PROGRESS

MIDHUN DAS
Date: 29/04/2024

Work in progress | 0% Completed

Earth work in progress

MIDHUN DAS
Date: 22/04/2024

Work in progress | 0% Completed

EARTHWORK EXCAVATION IN PROGRESS

MIDHUN DAS
Date: 15/04/2024

Work in progress | 0% Completed

no work in progress

MIDHUN DAS
Date: 08/04/2024

Work in progress | 0% Completed

no work in progress

MIDHUN DAS
Date: 01/04/2024

Work in progress | 0% Completed

Site clearance in progress

MIDHUN DAS
Date: 18/03/2024

Work in progress | 0% Completed

NO WORK IN PROGRESS

MIDHUN DAS
Date: 11/03/2024

Work in progress | 0% Completed

work is not started due to delay by the temple authorities to handerover the site by removing office building demolished waste and cutting of trees in the site.

MIDHUN DAS
Date: 04/03/2024

Work in progress | 0% Completed

work is not started due to delay by the temple authorities to handerover the site by removing office building demolished waste and cutting of trees in the site.

Abhinandh P T
Date: 28/02/2024

Work in progress | 0% Completed

SPT conducted