MIDHUN DAS |
Date: 30/09/2024 |
Work in progress | 9% Completed
|0% Completed
plinth work completed
MIDHUN DAS |
Date: 12/09/2024 |
Work in progress | 9% Completed
|0% Completed
plinth belt concrete completed
MIDHUN DAS |
Date: 03/09/2024 |
Work in progress | 7% Completed
|0% Completed
shuttering for plinth belt in progress
MIDHUN DAS |
Date: 22/07/2024 |
Work in progress | 6% Completed
|0% Completed
foundation belt concrete completed
MIDHUN DAS |
Date: 17/07/2024 |
Work in progress | 6% Completed
|0% Completed
no work in progress due to heavy rain
MIDHUN DAS |
Date: 08/07/2024 |
Work in progress | 6% Completed
|0% Completed
BASEMENT BELT WORK AT A PART IS COMPLETED
MIDHUN DAS |
Date: 01/07/2024 |
Work in progress | 6% Completed
|0% Completed
BASEMENT BELT WORK AT A PART IS COMPLETED
MIDHUN DAS |
Date: 24/06/2024 |
Work in progress | 6% Completed
|0% Completed
RR work in progress
MIDHUN DAS |
Date: 18/06/2024 |
Work in progress | 6% Completed
|0% Completed
reinforcement work in progress
MIDHUN DAS |
Date: 11/06/2024 |
Work in progress | 5% Completed
|0% Completed
shuttering work in progress
MIDHUN DAS |
Date: 03/06/2024 |
Work in progress | 5% Completed
|0% Completed
RR work in progress
MIDHUN DAS |
Date: 30/05/2024 |
Work in progress | 5% Completed
|0% Completed
RR WORK IN PROGRESS
MIDHUN DAS |
Date: 20/05/2024 |
Work in progress | 3% Completed
|0% Completed
PCC work completed
MIDHUN DAS |
Date: 12/05/2024 |
Work in progress | 3% Completed
|0% Completed
Excavation work in progress
MIDHUN DAS |
Date: 06/05/2024 |
Work in progress | 3% Completed
|0% Completed
EARTH WORK IN PROGRESS
MIDHUN DAS |
Date: 29/04/2024 |
Work in progress | 3% Completed
|0% Completed
Earth work in progress
MIDHUN DAS |
Date: 22/04/2024 |
Work in progress | 3% Completed
|0% Completed
EARTHWORK EXCAVATION IN PROGRESS
MIDHUN DAS |
Date: 15/04/2024 |
Work in progress | 1% Completed
|0% Completed
no work in progress
MIDHUN DAS |
Date: 08/04/2024 |
Work in progress | 1% Completed
|0% Completed
no work in progress
MIDHUN DAS |
Date: 01/04/2024 |
Work in progress | 1% Completed
|0% Completed
Site clearance in progress
MIDHUN DAS |
Date: 18/03/2024 |
Work in progress | 1% Completed
|0% Completed
NO WORK IN PROGRESS
MIDHUN DAS |
Date: 11/03/2024 |
Work in progress | 1% Completed
|0% Completed
work is not started due to delay by the temple authorities to handerover the site by removing office building demolished waste and cutting of trees in the site.
MIDHUN DAS |
Date: 04/03/2024 |
Work in progress | 1% Completed
|0% Completed
work is not started due to delay by the temple authorities to handerover the site by removing office building demolished waste and cutting of trees in the site.
Abhinandh P T |
Date: 28/02/2024 |
Work in progress | 1% Completed
|0% Completed
SPT conducted