DIDI RAVINDRAN
Date: 06/08/2024

Work in progress | 45% Completed

% |0% Completed

Pier,tunnel and canal raft works are ongoing

Attached images

img

DIDI RAVINDRAN
Date: 27/07/2024

Work in progress | 44% Completed

% |0% Completed

Pier,Raft slab works ongoing

Attached images

img

Nithish C
Date: 18/03/2024

Work in progress | 30% Completed

% |0% Completed

Reinforcement work at pier 72

Attached images

img

Nithish C
Date: 05/03/2024

Work in progress | 27% Completed

% |0% Completed

Pond rennovation work ongoing

Attached images

img

Nithish C
Date: 04/03/2024

Work in progress | 27% Completed

% |0% Completed

Pier 118 1st lift concreting

Attached images

img

Nithish C
Date: 28/02/2024

Work in progress | 27% Completed

% |0% Completed

Raft wall at chainage 4260 to 4290

Attached images

img

Nithish C
Date: 09/01/2024

Work in progress | 21% Completed

% |0% Completed

DR Masonry work at ISD farm pond

Attached images

img

Nithish C
Date: 01/01/2024

Work in progress | 19% Completed

% |0% Completed

Raft concreting at chainage 6+010 to 6040

Attached images

img

Nithish C
Date: 08/11/2023

Work in progress | 19% Completed

% |0% Completed

Slab concreting at chainage 5+950 to 5+5980

Attached images

img

Nithish C
Date: 02/11/2023

Work in progress | 19% Completed

% |0% Completed

Raft concreting at chainage 5+010 to 5+040

Attached images

img

Nithish C
Date: 26/10/2023

Work in progress | 19% Completed

% |0% Completed

Concreting at chainage 6+400

Attached images

img

Nithish C
Date: 16/10/2023

Work in progress | 14% Completed

% |0% Completed

Raft concreting at chainage 5+950 to 5+980

Attached images

img

Nithish C
Date: 10/10/2023

Work in progress | 14% Completed

% |0% Completed

Cover slab concreting at 5+840 to 5+870

Attached images

img

Nithish C
Date: 04/10/2023

Work in progress | 14% Completed

% |0% Completed

PCC at chainage 5+900 to 5+925 m

Attached images

img

Nithish C
Date: 25/09/2023

Work in progress | 14% Completed

% |0% Completed

Raft concreting at chainage 5785 to 5810

Attached images

img

Nithish C
Date: 18/09/2023

Work in progress | 14% Completed

% |0% Completed

PCC work at chainage 4+400 to 4+420

Nithish C
Date: 18/09/2023

Work in progress | 14% Completed

% |0% Completed

PCC at chainage 4+400 to 4+420

Attached images

img

Nithish C
Date: 11/09/2023

Work in progress | 14% Completed

% |0% Completed

Side wall concrete at 4+420 to 4+445

Attached images

img

Nithish C
Date: 05/09/2023

Work in progress | 13% Completed

% |0% Completed

Side wall concrete at 4+475 to 4+505

Attached images

img

Nithish C
Date: 22/08/2023

Work in progress | 13% Completed

% |0% Completed

Wall concreting at chainage 4+535 to 4+565

Attached images

img

Nithish C
Date: 14/08/2023

Work in progress | 13% Completed

% |0% Completed

Wall concreting at chainage 4+625 to 4+655m

Attached images

img

Nithish C
Date: 14/08/2023

Work in progress | 13% Completed

% |0% Completed

Wall concreting at chainage 4+625 to 4+655m

Attached images

img

Nithish C
Date: 08/08/2023

Work in progress | 13% Completed

% |0% Completed

Raft slab concreting at 4+625 to 4+655

Attached images

img

Nithish C
Date: 01/08/2023

Work in progress | 13% Completed

% |0% Completed

Piling work started at aqueduct portion

Attached images

img

Nithish C
Date: 24/07/2023

Work in progress | 12% Completed

% |0% Completed

Side wall concrete at chainage 4+445 to 4+475

Attached images

img

Nithish C
Date: 02/05/2023

Work in progress | 10% Completed

% |0% Completed

Reinforcement work for raft at chainage 4+535 to 4+565

GPS Cordinates

Latitude : 10.7282432

Longitude : 76.7819776

Accuracy : 5419.080289885569

Attached images

img

Nithish C
Date: 26/04/2023

Work in progress | 8% Completed

% |0% Completed

PCC of rectangular canal section

GPS Cordinates

Latitude : 10.7282432

Longitude : 76.7819776

Accuracy : 5419.080289885569

Attached images

img

Nithish C
Date: 18/04/2023

Work in progress | 8% Completed

% |0% Completed

Drilling for blasting rock

GPS Cordinates

Latitude : 10.7096143

Longitude : 76.8488525

Accuracy : 2500

Attached images

img

Nithish C
Date: 17/04/2023

Work in progress | 8% Completed

% |0% Completed

Drilling for blasting rock

GPS Cordinates

Latitude : 10.7351671

Longitude : 76.8740778

Accuracy : 2299.9990234375

Attached images

img

Nithish C
Date: 11/04/2023

Work in progress | 6% Completed

% |0% Completed

PCC at chainage 4+640 m

GPS Cordinates

Latitude : 10.7282432

Longitude : 76.7819776

Accuracy : 5419.080289885569

Attached images

img

Nithish C
Date: 03/04/2023

Work in progress | 6% Completed

% |0% Completed

PCC M10 mix concreting at 48 m chainage

GPS Cordinates

Latitude : 9.9312328

Longitude : 76.2673041

Accuracy : 16893.07305711459

Attached images

img

Nithish C
Date: 28/03/2023

Work in progress | 5% Completed

% |0% Completed

Excavation at chainage 4+400m

GPS Cordinates

Latitude : 10.7184128

Longitude : 76.7688704

Accuracy : 4668.414726083723

Attached images

img

Nithish C
Date: 20/03/2023

Work in progress | 5% Completed

% |0% Completed

Excavation at chainage 4+700m

GPS Cordinates

Latitude : 10.7324394

Longitude : 76.8747985

Accuracy : 1799.9990234375

Attached images

img

Nithish C
Date: 13/03/2023

Work in progress | 5% Completed

% |0% Completed

Excavation at chainage 4+600 m

GPS Cordinates

Latitude : 10.7324394

Longitude : 76.8747985

Accuracy : 1799.9990234375

Attached images

img

Nithish C
Date: 13/03/2023

Work in progress | 5% Completed

% |0% Completed

Excavation at grid numbers 487 and 491

GPS Cordinates

Latitude : 10.7867303

Longitude : 76.6547932

Accuracy : 3516.0181859876857

Attached images

img

Nithish C
Date: 06/03/2023

Work in progress | 3% Completed

% |0% Completed

Excavation at chainage 4+420

GPS Cordinates

Latitude : 10.7215141

Longitude : 76.8490328

Accuracy : 4422.080452293195

Attached images

img

Nithish C
Date: 27/02/2023

Work in progress | 3% Completed

% |0% Completed

Excavation at 0 to 370 m

GPS Cordinates

Latitude : 10.7215141

Longitude : 76.8490328

Accuracy : 4422.080452293195

Attached images

img

Nithish C
Date: 20/02/2023

Work in progress | 3% Completed

% |0% Completed

Soil filling at aqueduct portion from chainage 370m to 820m

GPS Cordinates

Latitude : 10.7007716

Longitude : 76.750966

Accuracy : 1703.7828267076056

Attached images

img

Nithish C
Date: 20/02/2023

Work in progress | 3% Completed

% |0% Completed

Soil filling at aqueduct portion at chainage 370m to 820m

GPS Cordinates

Latitude : 10.7007716

Longitude : 76.750966

Accuracy : 1703.7828267076056

Attached images

img

Nithish C
Date: 20/02/2023

Work in progress | 3% Completed

% |0% Completed

Soil filling at aqueduct portion from chainage 370m to 820m

GPS Cordinates

Latitude : 10.7007716

Longitude : 76.750966

Accuracy : 1703.7828267076056

Attached images

img

Nithish C
Date: 13/02/2023

Work in progress | 3% Completed

% |0% Completed

Earthwork excavation at 0 chainage

GPS Cordinates

Latitude : 10.7020097

Longitude : 76.8564207

Accuracy : 2200

Attached images

img

Nithish C
Date: 13/02/2023

Work in progress | 3% Completed

% |0% Completed

Earthwork excavation at 0 chainage

GPS Cordinates

Latitude : 10.7020097

Longitude : 76.8564207

Accuracy : 2200

Attached images

img

Nithish C
Date: 06/02/2023

Work in progress | 3% Completed

% |0% Completed

Excavation started at chainage 40m

GPS Cordinates

Latitude : 10.5866868

Longitude : 76.7636187

Accuracy : 106.767

Attached images

img

Nithish C
Date: 30/01/2023

Work in progress | 3% Completed

% |0% Completed

Earthwork excavation at chainage 6+100

GPS Cordinates

Latitude : 10.7523779

Longitude : 76.8733572

Accuracy : 2799.9990234375

Attached images

img

Nithish C
Date: 30/01/2023

Work in progress | 3% Completed

% |0% Completed

Excavation at chainage 6+000

GPS Cordinates

Latitude : 10.79046

Longitude : 76.8766001

Accuracy : 2400

Attached images

img

Nithish C
Date: 23/01/2023

Work in progress | 2% Completed

% |0% Completed

Excavation at chainage 6+000

GPS Cordinates

Latitude : 10.7282432

Longitude : 76.775424

Accuracy : 5226.455840126489

Attached images

img

Nithish C
Date: 16/01/2023

Work in progress | 2% Completed

% |0% Completed

Excavation about 3m depnth at chainage 6200

GPS Cordinates

Latitude : 10.7007716

Longitude : 76.750966

Accuracy : 1703.7828267076056

Attached images

img

Nithish C
Date: 10/01/2023

Work in progress | 2% Completed

% |0% Completed

checking the levels from moolathara dam to zero point

GPS Cordinates

Latitude : 8.501495057246816

Longitude : 76.96243639888294

Accuracy : 79

Attached images

img

Nithish C
Date: 04/01/2023

Work in progress | 2% Completed

% |0% Completed

Rock drilling at chainage 5+875 to 5+975 and soil excavation after 5+875

GPS Cordinates

Latitude : 10.7867303

Longitude : 76.6547932

Accuracy : 3516.0181859876857

Attached images

img

Nithish C
Date: 26/12/2022

Work in progress | 2% Completed

% |0% Completed

Drilling of rock portion at chainage 5+875 to 5+975 in cut and cover portion

GPS Cordinates

Latitude : 10.7007716

Longitude : 76.750966

Accuracy : 1703.7828267076056

Attached images

img

Nithish C
Date: 26/12/2022

Work in progress | 2% Completed

% |0% Completed

Drilling of rock portion at chainage 5+875 to 5+975 in cut and cover portion

GPS Cordinates

Latitude : 10.7007716

Longitude : 76.750966

Accuracy : 1703.7828267076056

Attached images

img

Nithish C
Date: 26/12/2022

Work in progress | 2% Completed

% |0% Completed

Drilling of rock portion at chainage 5+875 to 5+975 in cut and cover portion

GPS Cordinates

Latitude : 10.7007716

Longitude : 76.750966

Accuracy : 1703.7828267076056

Attached images

img

Nithish C
Date: 26/12/2022

Work in progress | 2% Completed

% |0% Completed

Drilling of rock portion at chainage 5+875 to 5+975 in cut and cover portion

GPS Cordinates

Latitude : 10.7007716

Longitude : 76.750966

Accuracy : 1703.7828267076056

Attached images

img

Nithish C
Date: 26/12/2022

Work in progress | 2% Completed

% |0% Completed

Drilling of rock portion at chainage 5+875 to 5+975 in cut and cover portion

GPS Cordinates

Latitude : 10.7007716

Longitude : 76.750966

Accuracy : 1703.7828267076056

Attached images

img

Nithish C
Date: 26/12/2022

Work in progress | 2% Completed

% |0% Completed

Drilling of rock portion at chainage 5+875 to 5+975 in cut and cover portion

GPS Cordinates

Latitude : 10.7007716

Longitude : 76.750966

Accuracy : 1703.7828267076056

Attached images

img

Nithish C
Date: 26/12/2022

Work in progress | 2% Completed

% |0% Completed

Drilling of rock portion at chainage 5+875 to 5+975 in cut and cover portion

GPS Cordinates

Latitude : 10.7007716

Longitude : 76.750966

Accuracy : 1703.7828267076056

Attached images

img

Nithish C
Date: 26/12/2022

Work in progress | 2% Completed

% |0% Completed

Drilling of rock portion at chainage 5+875 to 5+975 in cut and cover portion

GPS Cordinates

Latitude : 10.7007716

Longitude : 76.750966

Accuracy : 1703.7828267076056

Attached images

img

Nithish C
Date: 20/12/2022

Work in progress | 2% Completed

% |0% Completed

Total 50 soil boring test conducted and transferring the benchmark from moolathara regulator to zero point

GPS Cordinates

Latitude : 10.7007716

Longitude : 76.750966

Accuracy : 1703.7828267076056

Attached images

img

Nithish C
Date: 13/12/2022

Work in progress | 2% Completed

% |0% Completed

Total 45 soil boring test completed and earthwork excavation progressing at cut and cover portion

GPS Cordinates

Latitude : 10.7520023

Longitude : 76.8726365

Accuracy : 2700

Attached images

img

Nithish C
Date: 05/12/2022

Work in progress | 2% Completed

% |0% Completed

Earthwork excavation

GPS Cordinates

Latitude : 10.7914487

Longitude : 76.8755191

Accuracy : 2500

Attached images

img

Nithish C
Date: 05/12/2022

Work in progress | 2% Completed

% |0% Completed

Earthwork excavation

GPS Cordinates

Latitude : 10.7914487

Longitude : 76.8755191

Accuracy : 2500

Attached images

img

Nithish C
Date: 31/10/2022

Work in progress | 0% Completed

% |0% Completed

Earthwork excavation

GPS Cordinates

Latitude : 10.7193912

Longitude : 76.8679522

Accuracy : 2599.9990234375

Attached images

img

Nithish C
Date: 17/10/2022

Work in progress | 0% Completed

% |0% Completed

Earthwork excavation

GPS Cordinates

Latitude : 10.7923756

Longitude : 76.8729969

Accuracy : 2200

Attached images

img

Nithish C
Date: 07/10/2022

Work in progress | 2% Completed

% |0% Completed

Earthwork Excavation

GPS Cordinates

Latitude : 10.7678308

Longitude : 76.8798429

Accuracy : 3099.9990234375

Attached images

img

Anu IT Admin
Date: 27/09/2022

Work in progress | 2% Completed

% |0% Completed

Revised Hydraulic particulars submitted by the contractor on 17/08/2022 was approved by the Design Evaluation Committee constituted for MRBC Phase 1, on 06/09/2022. Revised design based on the approved hydraulic particulars on 16-09-2022 is under the scrutiny of Design Evaluation Committee. Initial chainage and set out of 500m has been completed.Remaining setout is in progress. Almost 510 trees has been cut down

GPS Cordinates

Latitude : 8.485648343989816

Longitude : 76.92838095152611

Accuracy : 67

DIDI RAVINDRAN
Date: 06/08/2024

Work in progress | 0% Completed

Pier,tunnel and canal raft works are ongoing

Attached images

img

DIDI RAVINDRAN
Date: 27/07/2024

Work in progress | 0% Completed

Pier,Raft slab works ongoing

Attached images

img

Nithish C
Date: 18/03/2024

Work in progress | 0% Completed

Reinforcement work at pier 72

Attached images

img

Nithish C
Date: 05/03/2024

Work in progress | 0% Completed

Pond rennovation work ongoing

Attached images

img

Nithish C
Date: 04/03/2024

Work in progress | 0% Completed

Pier 118 1st lift concreting

Attached images

img

Nithish C
Date: 28/02/2024

Work in progress | 0% Completed

Raft wall at chainage 4260 to 4290

Attached images

img

Nithish C
Date: 09/01/2024

Work in progress | 0% Completed

DR Masonry work at ISD farm pond

Attached images

img

Nithish C
Date: 01/01/2024

Work in progress | 0% Completed

Raft concreting at chainage 6+010 to 6040

Attached images

img

Nithish C
Date: 08/11/2023

Work in progress | 0% Completed

Slab concreting at chainage 5+950 to 5+5980

Attached images

img

Nithish C
Date: 02/11/2023

Work in progress | 0% Completed

Raft concreting at chainage 5+010 to 5+040

Attached images

img

Nithish C
Date: 26/10/2023

Work in progress | 0% Completed

Concreting at chainage 6+400

Attached images

img

Nithish C
Date: 16/10/2023

Work in progress | 0% Completed

Raft concreting at chainage 5+950 to 5+980

Attached images

img

Nithish C
Date: 10/10/2023

Work in progress | 0% Completed

Cover slab concreting at 5+840 to 5+870

Attached images

img

Nithish C
Date: 04/10/2023

Work in progress | 0% Completed

PCC at chainage 5+900 to 5+925 m

Attached images

img

Nithish C
Date: 25/09/2023

Work in progress | 0% Completed

Raft concreting at chainage 5785 to 5810

Attached images

img

Nithish C
Date: 18/09/2023

Work in progress | 0% Completed

PCC work at chainage 4+400 to 4+420

Nithish C
Date: 18/09/2023

Work in progress | 0% Completed

PCC at chainage 4+400 to 4+420

Attached images

img

Nithish C
Date: 11/09/2023

Work in progress | 0% Completed

Side wall concrete at 4+420 to 4+445

Attached images

img

Nithish C
Date: 05/09/2023

Work in progress | 0% Completed

Side wall concrete at 4+475 to 4+505

Attached images

img

Nithish C
Date: 22/08/2023

Work in progress | 0% Completed

Wall concreting at chainage 4+535 to 4+565

Attached images

img

Nithish C
Date: 14/08/2023

Work in progress | 0% Completed

Wall concreting at chainage 4+625 to 4+655m

Attached images

img

Nithish C
Date: 14/08/2023

Work in progress | 0% Completed

Wall concreting at chainage 4+625 to 4+655m

Attached images

img

Nithish C
Date: 08/08/2023

Work in progress | 0% Completed

Raft slab concreting at 4+625 to 4+655

Attached images

img

Nithish C
Date: 01/08/2023

Work in progress | 0% Completed

Piling work started at aqueduct portion

Attached images

img

Nithish C
Date: 24/07/2023

Work in progress | 0% Completed

Side wall concrete at chainage 4+445 to 4+475

Attached images

img

Nithish C
Date: 02/05/2023

Work in progress | 0% Completed

Reinforcement work for raft at chainage 4+535 to 4+565

Attached images

img

Nithish C
Date: 26/04/2023

Work in progress | 0% Completed

PCC of rectangular canal section

Attached images

img

Nithish C
Date: 18/04/2023

Work in progress | 0% Completed

Drilling for blasting rock

Attached images

img

Nithish C
Date: 17/04/2023

Work in progress | 0% Completed

Drilling for blasting rock

Attached images

img

Nithish C
Date: 11/04/2023

Work in progress | 0% Completed

PCC at chainage 4+640 m

Attached images

img

Nithish C
Date: 03/04/2023

Work in progress | 0% Completed

PCC M10 mix concreting at 48 m chainage

Attached images

img

Nithish C
Date: 28/03/2023

Work in progress | 0% Completed

Excavation at chainage 4+400m

Attached images

img

Nithish C
Date: 20/03/2023

Work in progress | 0% Completed

Excavation at chainage 4+700m

Attached images

img

Nithish C
Date: 13/03/2023

Work in progress | 0% Completed

Excavation at chainage 4+600 m

Attached images

img

Nithish C
Date: 13/03/2023

Work in progress | 0% Completed

Excavation at grid numbers 487 and 491

Attached images

img

Nithish C
Date: 06/03/2023

Work in progress | 0% Completed

Excavation at chainage 4+420

Attached images

img

Nithish C
Date: 27/02/2023

Work in progress | 0% Completed

Excavation at 0 to 370 m

Attached images

img

Nithish C
Date: 20/02/2023

Work in progress | 0% Completed

Soil filling at aqueduct portion from chainage 370m to 820m

Attached images

img

Nithish C
Date: 20/02/2023

Work in progress | 0% Completed

Soil filling at aqueduct portion at chainage 370m to 820m

Attached images

img

Nithish C
Date: 20/02/2023

Work in progress | 0% Completed

Soil filling at aqueduct portion from chainage 370m to 820m

Attached images

img

Nithish C
Date: 13/02/2023

Work in progress | 0% Completed

Earthwork excavation at 0 chainage

Attached images

img

Nithish C
Date: 13/02/2023

Work in progress | 0% Completed

Earthwork excavation at 0 chainage

Attached images

img

Nithish C
Date: 06/02/2023

Work in progress | 0% Completed

Excavation started at chainage 40m

Attached images

img

Nithish C
Date: 30/01/2023

Work in progress | 0% Completed

Earthwork excavation at chainage 6+100

Attached images

img

Nithish C
Date: 30/01/2023

Work in progress | 0% Completed

Excavation at chainage 6+000

Attached images

img

Nithish C
Date: 23/01/2023

Work in progress | 0% Completed

Excavation at chainage 6+000

Attached images

img

Nithish C
Date: 16/01/2023

Work in progress | 0% Completed

Excavation about 3m depnth at chainage 6200

Attached images

img

Nithish C
Date: 10/01/2023

Work in progress | 0% Completed

checking the levels from moolathara dam to zero point

Attached images

img

Nithish C
Date: 04/01/2023

Work in progress | 0% Completed

Rock drilling at chainage 5+875 to 5+975 and soil excavation after 5+875

Attached images

img

Nithish C
Date: 26/12/2022

Work in progress | 0% Completed

Drilling of rock portion at chainage 5+875 to 5+975 in cut and cover portion

Attached images

img

Nithish C
Date: 26/12/2022

Work in progress | 0% Completed

Drilling of rock portion at chainage 5+875 to 5+975 in cut and cover portion

Attached images

img

Nithish C
Date: 26/12/2022

Work in progress | 0% Completed

Drilling of rock portion at chainage 5+875 to 5+975 in cut and cover portion

Attached images

img

Nithish C
Date: 26/12/2022

Work in progress | 0% Completed

Drilling of rock portion at chainage 5+875 to 5+975 in cut and cover portion

Attached images

img

Nithish C
Date: 26/12/2022

Work in progress | 0% Completed

Drilling of rock portion at chainage 5+875 to 5+975 in cut and cover portion

Attached images

img

Nithish C
Date: 26/12/2022

Work in progress | 0% Completed

Drilling of rock portion at chainage 5+875 to 5+975 in cut and cover portion

Attached images

img

Nithish C
Date: 26/12/2022

Work in progress | 0% Completed

Drilling of rock portion at chainage 5+875 to 5+975 in cut and cover portion

Attached images

img

Nithish C
Date: 26/12/2022

Work in progress | 0% Completed

Drilling of rock portion at chainage 5+875 to 5+975 in cut and cover portion

Attached images

img

Nithish C
Date: 20/12/2022

Work in progress | 0% Completed

Total 50 soil boring test conducted and transferring the benchmark from moolathara regulator to zero point

Attached images

img

Nithish C
Date: 13/12/2022

Work in progress | 0% Completed

Total 45 soil boring test completed and earthwork excavation progressing at cut and cover portion

Attached images

img

Nithish C
Date: 05/12/2022

Work in progress | 0% Completed

Earthwork excavation

Attached images

img

Nithish C
Date: 05/12/2022

Work in progress | 0% Completed

Earthwork excavation

Attached images

img

Nithish C
Date: 31/10/2022

Work in progress | 0% Completed

Earthwork excavation

Attached images

img

Nithish C
Date: 17/10/2022

Work in progress | 0% Completed

Earthwork excavation

Attached images

img

Nithish C
Date: 07/10/2022

Work in progress | 0% Completed

Earthwork Excavation

Attached images

img

Anu IT Admin
Date: 27/09/2022

Work in progress | 0% Completed

Revised Hydraulic particulars submitted by the contractor on 17/08/2022 was approved by the Design Evaluation Committee constituted for MRBC Phase 1, on 06/09/2022. Revised design based on the approved hydraulic particulars on 16-09-2022 is under the scrutiny of Design Evaluation Committee. Initial chainage and set out of 500m has been completed.Remaining setout is in progress. Almost 510 trees has been cut down