| MIDHUN DAS |
| Date: 30/08/2025 |
Work in progress | 75% Completed
submain works|65% Completed
Electrification|0% Completed
Mainline Works|75% Completed
pump room|0% Completed
Pond|0% Completed
Automation & Head unit|0% Completed
due to heavy rain no work in progress
| MIDHUN DAS |
| Date: 11/08/2025 |
Work in progress | 75% Completed
Automation & Head unit|0% Completed
Electrification|0% Completed
Mainline Works|75% Completed
pump room|0% Completed
Pond|0% Completed
submain works|65% Completed
No work in progress
| MIDHUN DAS |
| Date: 01/08/2025 |
Work in progress | 75% Completed
Automation & Head unit|0% Completed
Electrification|0% Completed
Mainline Works|75% Completed
pump room|0% Completed
Pond|0% Completed
submain works|65% Completed
NO WORK IN PROGRESS DUE TO HEAVY RAIN
| MIDHUN DAS |
| Date: 21/07/2025 |
Work in progress | 75% Completed
Automation & Head unit|0% Completed
Electrification|0% Completed
Mainline Works|75% Completed
pump room|0% Completed
Pond|0% Completed
submain works|65% Completed
no work in progress due to heavy rain .[
| MIDHUN DAS |
| Date: 16/07/2025 |
Work in progress | 75% Completed
Automation & Head unit|0% Completed
Electrification|0% Completed
Mainline Works|75% Completed
pump room|0% Completed
Pond|0% Completed
submain works|65% Completed
no work in progress due heavy rain
| MIDHUN DAS |
| Date: 07/07/2025 |
Work in progress | 75% Completed
Automation & Head unit|0% Completed
Electrification|0% Completed
Mainline Works|75% Completed
pump room|0% Completed
Pond|0% Completed
submain works|65% Completed
No work in progress due to rain
| MIDHUN DAS |
| Date: 07/04/2025 |
Work in progress | 60% Completed
submain works|65% Completed
Automation & Head unit|0% Completed
Pond|0% Completed
pump room|0% Completed
Mainline Works|75% Completed
Electrification|0% Completed
micro irrigation part in progress
| MIDHUN DAS |
| Date: 01/04/2025 |
Work in progress | 60% Completed
submain works|65% Completed
Electrification|0% Completed
Mainline Works|75% Completed
pump room|0% Completed
Pond|0% Completed
Automation & Head unit|0% Completed
main line work in progress
| MIDHUN DAS |
| Date: 24/03/2025 |
Work in progress | 60% Completed
Automation & Head unit|0% Completed
Electrification|0% Completed
Mainline Works|75% Completed
pump room|0% Completed
Pond|0% Completed
submain works|65% Completed
micro irrigation part work in progress.
| MIDHUN DAS |
| Date: 17/03/2025 |
Work in progress | 50% Completed
Automation & Head unit|0% Completed
Electrification|0% Completed
Mainline Works|75% Completed
pump room|0% Completed
Pond|0% Completed
submain works|65% Completed
MICRO IRRIGATION PIPELINE WORKS IN PROGRESS
| MIDHUN DAS |
| Date: 10/03/2025 |
Work in progress | 50% Completed
Automation & Head unit|0% Completed
Electrification|0% Completed
Mainline Works|75% Completed
pump room|0% Completed
Pond|0% Completed
submain works|65% Completed
main line and sublone trenching and laying in progress
| MIDHUN DAS |
| Date: 10/03/2025 |
Work in progress | 50% Completed
Electrification|0% Completed
Mainline Works|75% Completed
pump room|0% Completed
Pond|0% Completed
Automation & Head unit|0% Completed
submain works|65% Completed
main line and sublone trenching and laying in progress
| MIDHUN DAS |
| Date: 24/02/2025 |
Work in progress | 50% Completed
submain works|65% Completed
Electrification|0% Completed
Mainline Works|75% Completed
pump room|0% Completed
Pond|0% Completed
Automation & Head unit|0% Completed
Main line and subline trenching and laying upto 35 acres completed.
| MIDHUN DAS |
| Date: 17/02/2025 |
Work in progress | 10% Completed
submain works|65% Completed
Automation & Head unit|0% Completed
Pond|0% Completed
pump room|0% Completed
Mainline Works|75% Completed
Electrification|0% Completed
pump room civil work completed upto plastering, mainline trenching and pipe laying work are progressing.