| Ebin Solomon |
| Date: 18/07/2025 |
Work in progress | 25% Completed
|0% Completed
Due to heavy rain the roofing work can't exicute at site. Will continue after the climate condition is changed.
| Ebin Solomon |
| Date: 01/04/2025 |
Work in progress | 21% Completed
|0% Completed
Work in progress
| Ebin Solomon |
| Date: 22/03/2025 |
Work in progress | 20% Completed
|0% Completed
Work in progress
| Ebin Solomon |
| Date: 03/03/2025 |
Work in progress | 18% Completed
|0% Completed
Ootupura and multi purpose hall laterite work in progress
| Ebin Solomon |
| Date: 17/02/2025 |
Work in progress | 12% Completed
|0% Completed
Ootupura and multi purpose hall plinth level completed.
| Praveen Jose |
| Date: 28/12/2024 |
| Praveen Jose |
| Date: 26/07/2024 |
Work in progress | 1% Completed
|0% Completed
SPT for soil investigation finished