Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Swathy.G
Date: 25/07/2025

Work in progress | 15% Completed

% |0% Completed

- Handrail installation is ongoing. - Exhaust fittings in all bathrooms are completed. - Air vent pipes from the duct have been installed; but the top portion of the vent can nit open due to rain. - Roofing for the staff quarters and out side toilet construction are pending due to rainfall. - Roofing materials and handrail supplies have arrived on-site.

Attached images

img

Joel J Varghese
Date: 03/04/2025

Work in progress | 1% Completed

% |0% Completed

Initial works have been started by the contractor

Joel J Varghese
Date: 17/03/2025

Work in progress | 1% Completed

% |0% Completed

Initial works have been started by the contractor

Joel J Varghese
Date: 03/03/2025

Work in progress | 1% Completed

% |0% Completed

SIte handover to Contractor Initial works are in progress and direction from the Tourism Department some changes are made as per site requirement

Attached images

img

Swathy.G
Date: 25/07/2025

Work in progress | 0% Completed

- Handrail installation is ongoing. - Exhaust fittings in all bathrooms are completed. - Air vent pipes from the duct have been installed; but the top portion of the vent can nit open due to rain. - Roofing for the staff quarters and out side toilet construction are pending due to rainfall. - Roofing materials and handrail supplies have arrived on-site.

Attached images

img

Joel J Varghese
Date: 03/04/2025

Work in progress | 0% Completed

Initial works have been started by the contractor

Joel J Varghese
Date: 17/03/2025

Work in progress | 0% Completed

Initial works have been started by the contractor

Joel J Varghese
Date: 03/03/2025

Work in progress | 0% Completed

SIte handover to Contractor Initial works are in progress and direction from the Tourism Department some changes are made as per site requirement

Attached images

img