Swathy.G |
Date: 25/07/2025 |
Work in progress | 15% Completed
|0% Completed
- Handrail installation is ongoing. - Exhaust fittings in all bathrooms are completed. - Air vent pipes from the duct have been installed; but the top portion of the vent can nit open due to rain. - Roofing for the staff quarters and out side toilet construction are pending due to rainfall. - Roofing materials and handrail supplies have arrived on-site.
Attached images
Joel J Varghese |
Date: 03/04/2025 |
Work in progress | 1% Completed
|0% Completed
Initial works have been started by the contractor
Joel J Varghese |
Date: 17/03/2025 |
Work in progress | 1% Completed
|0% Completed
Initial works have been started by the contractor