Amal Padmu L P |
Date: 04/09/2023 |
Work in progress | 99% Completed
Fertigation Room|95% Completed
Electrification|99% Completed
Civil work for lamp post|0% Completed
Sump Tank|100% Completed
EB connection Pending
Amal Padmu L P |
Date: 10/07/2023 |
Amal Padmu L P |
Date: 03/07/2023 |
Work in progress | 99% Completed
Sump Tank|100% Completed
Electrification|99% Completed
Civil work for lamp post|0% Completed
Fertigation Room|95% Completed
final Finishing works are ongoing
Amal Padmu L P |
Date: 26/06/2023 |
Work in progress | 99% Completed
Sump Tank|100% Completed
Electrification|99% Completed
Civil work for lamp post|0% Completed
Fertigation Room|95% Completed
Finishing works are ongoing
Amal Padmu L P |
Date: 19/06/2023 |
Work in progress | 99% Completed
Sump Tank|100% Completed
Electrification|99% Completed
Civil work for lamp post|0% Completed
Fertigation Room|95% Completed
Finishing works are ongoing
Amal Padmu L P |
Date: 12/06/2023 |
Work in progress | 99% Completed
Fertigation Room|95% Completed
Electrification|99% Completed
Civil work for lamp post|0% Completed
Sump Tank|100% Completed
Finishing works are ongoing
Amal Padmu L P |
Date: 05/06/2023 |
Work in progress | 99% Completed
Sump Tank|100% Completed
Electrification|99% Completed
Civil work for lamp post|0% Completed
Fertigation Room|95% Completed
Finishing works are ongoing
Amal Padmu L P |
Date: 29/05/2023 |
Work in progress | 99% Completed
Sump Tank|100% Completed
Electrification|99% Completed
Civil work for lamp post|0% Completed
Fertigation Room|95% Completed
Electrical work ongoing
Amal Padmu L P |
Date: 21/05/2023 |
Amal Padmu L P |
Date: 15/05/2023 |
Work in progress | 93% Completed
Fertigation Room|95% Completed
Electrification|99% Completed
Civil work for lamp post|0% Completed
Sump Tank|100% Completed
Electrical works are pending
Amal Padmu L P |
Date: 07/05/2023 |
Work in progress | 93% Completed
Sump Tank|100% Completed
Electrification|99% Completed
Civil work for lamp post|0% Completed
Fertigation Room|95% Completed
Electrical works are pending
Amal Padmu L P |
Date: 02/05/2023 |
Work in progress | 88% Completed
Sump Tank|100% Completed
Electrification|99% Completed
Civil work for lamp post|0% Completed
Fertigation Room|95% Completed
Electrical works are pending
Amal Padmu L P |
Date: 24/04/2023 |
Work in progress | 88% Completed
Sump Tank|100% Completed
Electrification|99% Completed
Civil work for lamp post|0% Completed
Fertigation Room|95% Completed
Electrical works are pending
Amal Padmu L P |
Date: 17/04/2023 |
Work in progress | 87% Completed
Sump Tank|100% Completed
Electrification|99% Completed
Civil work for lamp post|0% Completed
Fertigation Room|95% Completed
Electrical works are pending
Amal Padmu L P |
Date: 11/04/2023 |
Amal Padmu L P |
Date: 03/04/2023 |
Work in progress | 85% Completed
Sump Tank|100% Completed
Electrification|99% Completed
Civil work for lamp post|0% Completed
Fertigation Room|95% Completed
Electrical works to be start
Amal Padmu L P |
Date: 27/03/2023 |
Amal Padmu L P |
Date: 21/03/2023 |
Amal Padmu L P |
Date: 13/03/2023 |
Amal Padmu L P |
Date: 06/03/2023 |
Amal Padmu L P |
Date: 27/02/2023 |
Amal Padmu L P |
Date: 20/02/2023 |
Amal Padmu L P |
Date: 13/02/2023 |
Amal Padmu L P |
Date: 07/02/2023 |
Amal Padmu L P |
Date: 31/01/2023 |
Work in progress | 41% Completed
Sump Tank|100% Completed
Electrification|99% Completed
Civil work for lamp post|0% Completed
Fertigation Room|95% Completed
Informed the contractor to complete the remaining works
Amal Padmu L P |
Date: 24/01/2023 |
Work in progress | 41% Completed
Sump Tank|100% Completed
Electrification|99% Completed
Civil work for lamp post|0% Completed
Fertigation Room|95% Completed
Informed the contractor to complete the remaining works
Amal Padmu L P |
Date: 19/01/2023 |
Work in progress | 41% Completed
Fertigation Room|95% Completed
Electrification|99% Completed
Civil work for lamp post|0% Completed
Sump Tank|100% Completed
Informed contractor to complete the remaining works
Amal Padmu L P |
Date: 27/12/2022 |
Work in progress | 41% Completed
Fertigation Room|95% Completed
Electrification|99% Completed
Civil work for lamp post|0% Completed
Sump Tank|100% Completed
Instruction given to the contractor to complete the remaining works
GPS Cordinates
Latitude : 10.7359472
Longitude : 76.8445672
Accuracy : 20
Anu IT Admin |
Date: 29/11/2022 |
Amal Padmu L P |
Date: 29/10/2022 |
Work in progress | 0% Completed
Sump Tank|100% Completed
Electrification|99% Completed
Civil work for lamp post|0% Completed
Fertigation Room|95% Completed
Foundation works-100% Column casting -100% Roofslab casting -100% Brick work for wall -to be started
GPS Cordinates
Latitude : 10.6848827
Longitude : 76.8265059
Accuracy : 1100
Attached images
Amal Padmu L P |
Date: 25/10/2022 |
Amal Padmu L P |
Date: 19/10/2022 |
Amal Padmu L P |
Date: 10/10/2022 |
Amal Padmu L P |
Date: 01/10/2022 |
Amal Padmu L P |
Date: 26/09/2022 |