Joel J Varghese
Date: 20/11/2023

Work has been completed | 100% Completed

100.00% valliyoorkavu temple-streetscape|100% Completed

0.00% Stone steps to temple|0% Completed

0.00% electrification|0% Completed

0.00% Lamp post|0% Completed

Final Bill Pending

Joel J Varghese
Date: 18/09/2023

Work has been completed | 100% Completed

100.00% valliyoorkavu temple-streetscape|100% Completed

0.00% Stone steps to temple|0% Completed

0.00% electrification|0% Completed

0.00% Lamp post|0% Completed

Work has been completed Final RE and Final Bill Pending

Date: 24/06/2023

Work has been completed | 100% Completed

100.00% valliyoorkavu temple-streetscape|100% Completed

0.00% Stone steps to temple|0% Completed

0.00% electrification|0% Completed

0.00% Lamp post|0% Completed

COMPLETED

Date: 19/05/2023

Work has been completed | 100% Completed

100.00% valliyoorkavu temple-streetscape|100% Completed

0.00% Stone steps to temple|0% Completed

0.00% electrification|0% Completed

0.00% Lamp post|0% Completed

A2 lifting ongoing

Date: 19/05/2023

Work has been completed | 100% Completed

0.00% Stone steps to temple|0% Completed

0.00% electrification|0% Completed

0.00% Lamp post|0% Completed

100.00% valliyoorkavu temple-streetscape|100% Completed

completed

Date: 13/05/2023

Work has been completed | 100% Completed

100.00% valliyoorkavu temple-streetscape|100% Completed

0.00% Stone steps to temple|0% Completed

0.00% electrification|0% Completed

0.00% Lamp post|0% Completed

completed

Date: 08/05/2023

Work has been completed | 100% Completed

100.00% valliyoorkavu temple-streetscape|100% Completed

0.00% Stone steps to temple|0% Completed

0.00% electrification|0% Completed

0.00% Lamp post|0% Completed

COMPLETED

Date: 24/04/2023

Work has been completed | 100% Completed

100.00% valliyoorkavu temple-streetscape|100% Completed

0.00% Stone steps to temple|0% Completed

0.00% electrification|0% Completed

0.00% Lamp post|0% Completed

Completed 100%

Date: 10/04/2023

Work has been completed | 100% Completed

100.00% valliyoorkavu temple-streetscape|100% Completed

0.00% Stone steps to temple|0% Completed

0.00% electrification|0% Completed

0.00% Lamp post|0% Completed

completed

Date: 03/04/2023

Work has been completed | 100% Completed

100.00% valliyoorkavu temple-streetscape|100% Completed

0.00% Stone steps to temple|0% Completed

0.00% electrification|0% Completed

0.00% Lamp post|0% Completed

Completed

Date: 27/03/2023

Work has been completed | 100% Completed

100.00% valliyoorkavu temple-streetscape|100% Completed

0.00% Stone steps to temple|0% Completed

0.00% electrification|0% Completed

0.00% Lamp post|0% Completed

100% COMPLETED

Date: 20/03/2023

Work has been completed | 100% Completed

100.00% valliyoorkavu temple-streetscape|100% Completed

0.00% Stone steps to temple|0% Completed

0.00% electrification|0% Completed

0.00% Lamp post|0% Completed

completed

Date: 13/03/2023

Work has been completed | 100% Completed

100.00% valliyoorkavu temple-streetscape|100% Completed

0.00% Stone steps to temple|0% Completed

0.00% electrification|0% Completed

0.00% Lamp post|0% Completed

completed

Date: 27/02/2023

Work in progress | 99% Completed

0.00% Lamp post|0% Completed

0.00% Stone steps to temple|0% Completed

0.00% electrification|0% Completed

100.00% valliyoorkavu temple-streetscape|100% Completed

99 % work completed

Date: 20/02/2023

Work in progress | 97% Completed

100.00% valliyoorkavu temple-streetscape|100% Completed

0.00% Stone steps to temple|0% Completed

0.00% electrification|0% Completed

0.00% Lamp post|0% Completed

Ele work completed

Date: 13/02/2023

Work in progress | 97% Completed

100.00% valliyoorkavu temple-streetscape|100% Completed

0.00% Stone steps to temple|0% Completed

0.00% electrification|0% Completed

0.00% Lamp post|0% Completed

ELE WORK COMPLETED

Date: 06/02/2023

Work in progress | 97% Completed

100.00% valliyoorkavu temple-streetscape|100% Completed

0.00% Stone steps to temple|0% Completed

0.00% electrification|0% Completed

0.00% Lamp post|0% Completed

Electrical work completed, Painting work ongoing

Date: 30/01/2023

Work in progress | 97% Completed

100.00% valliyoorkavu temple-streetscape|100% Completed

0.00% Stone steps to temple|0% Completed

0.00% electrification|0% Completed

0.00% Lamp post|0% Completed

Ele work ongoing

Date: 23/01/2023

Work in progress | 97% Completed

100.00% valliyoorkavu temple-streetscape|100% Completed

0.00% Lamp post|0% Completed

0.00% electrification|0% Completed

0.00% Stone steps to temple|0% Completed

Ele work ongoing

Date: 16/01/2023

Work in progress | 97% Completed

100.00% valliyoorkavu temple-streetscape|100% Completed

0.00% Stone steps to temple|0% Completed

0.00% electrification|0% Completed

0.00% Lamp post|0% Completed

Ele work ongoing

Date: 09/01/2023

Work in progress | 97% Completed

100.00% valliyoorkavu temple-streetscape|100% Completed

0.00% Stone steps to temple|0% Completed

0.00% electrification|0% Completed

0.00% Lamp post|0% Completed

Eletrical work ongoing

Attached images

img

Date: 02/01/2023

Work in progress | 97% Completed

100.00% valliyoorkavu temple-streetscape|100% Completed

0.00% Stone steps to temple|0% Completed

0.00% electrification|0% Completed

0.00% Lamp post|0% Completed

Ele work ongoing

Date: 26/12/2022

Work in progress | 96% Completed

100.00% valliyoorkavu temple-streetscape|100% Completed

0.00% Stone steps to temple|0% Completed

0.00% electrification|0% Completed

0.00% Lamp post|0% Completed

ele work ongoing

Date: 20/12/2022

Work in progress | 96% Completed

0.00% Lamp post|0% Completed

0.00% Stone steps to temple|0% Completed

0.00% electrification|0% Completed

100.00% valliyoorkavu temple-streetscape|100% Completed

Stone paving completed

GPS Cordinates

Latitude : 11.8034264

Longitude : 76.0300072

Accuracy : 72.9000015258789

Attached images

img

Date: 12/12/2022

Work in progress | 95% Completed

100.00% valliyoorkavu temple-streetscape|100% Completed

0.00% Stone steps to temple|0% Completed

0.00% electrification|0% Completed

0.00% Lamp post|0% Completed

Paving completed

Attached images

img

Date: 07/12/2022

Work in progress | 95% Completed

100.00% valliyoorkavu temple-streetscape|100% Completed

0.00% Stone steps to temple|0% Completed

0.00% electrification|0% Completed

0.00% Lamp post|0% Completed

Sadhrahalli stone paving completed

Attached images

img

Date: 01/12/2022

Work in progress | 94% Completed

100.00% valliyoorkavu temple-streetscape|100% Completed

0.00% Stone steps to temple|0% Completed

0.00% electrification|0% Completed

0.00% Lamp post|0% Completed

stone paving completed

Attached images

img

Date: 23/11/2022

Work in progress | 91% Completed

100.00% valliyoorkavu temple-streetscape|100% Completed

0.00% Stone steps to temple|0% Completed

0.00% electrification|0% Completed

0.00% Lamp post|0% Completed

stone paving ongoing

Attached images

img

Date: 11/11/2022

Work in progress | 90% Completed

0.00% Lamp post|0% Completed

0.00% Stone steps to temple|0% Completed

0.00% electrification|0% Completed

100.00% valliyoorkavu temple-streetscape|100% Completed

Sadhrahalli paving ongoing

Attached images

img

Date: 03/11/2022

Work in progress | 0% Completed

100.00% valliyoorkavu temple-streetscape|100% Completed

0.00% Stone steps to temple|0% Completed

0.00% electrification|0% Completed

0.00% Lamp post|0% Completed

Plastering work ongoing

GPS Cordinates

Latitude : 11.8074181

Longitude : 76.0386469

Accuracy : 3599.9990234375

Attached images

img

Date: 01/11/2022

Work in progress | 0% Completed

100.00% valliyoorkavu temple-streetscape|100% Completed

0.00% Stone steps to temple|0% Completed

0.00% electrification|0% Completed

0.00% Lamp post|0% Completed

Plastering ongoing

GPS Cordinates

Latitude : 11.803794

Longitude : 76.0301094

Accuracy : 1.9830000400543213

Attached images

img

Date: 25/10/2022

Work in progress | 0% Completed

100.00% valliyoorkavu temple-streetscape|100% Completed

0.00% Stone steps to temple|0% Completed

0.00% electrification|0% Completed

0.00% Lamp post|0% Completed

Electrical work ongoing

GPS Cordinates

Latitude : 11.8033783

Longitude : 76.0300066

Accuracy : 135.60000610351562

Attached images

img

Date: 22/10/2022

Work in progress | 0% Completed

100.00% valliyoorkavu temple-streetscape|100% Completed

0.00% Stone steps to temple|0% Completed

0.00% electrification|0% Completed

0.00% Lamp post|0% Completed

Rcc pier concrete completed

GPS Cordinates

Latitude : 11.8021536

Longitude : 76.0306685

Accuracy : 2200

Attached images

img

Date: 19/10/2022

Work in progress | 75% Completed

0.00% Lamp post|0% Completed

0.00% Stone steps to temple|0% Completed

0.00% electrification|0% Completed

100.00% valliyoorkavu temple-streetscape|100% Completed

Sadrahalli Stone paving ongoing

Attached images

img

Date: 12/10/2022

Work in progress | 66% Completed

100.00% valliyoorkavu temple-streetscape|100% Completed

0.00% Stone steps to temple|0% Completed

0.00% electrification|0% Completed

0.00% Lamp post|0% Completed

Laterite wall

GPS Cordinates

Latitude : 11.8034649

Longitude : 76.0301192

Accuracy : 4.815999984741211

Attached images

img

Date: 04/10/2022

Work in progress | 65% Completed

100.00% valliyoorkavu temple-streetscape|100% Completed

0.00% Stone steps to temple|0% Completed

0.00% electrification|0% Completed

0.00% Lamp post|0% Completed

Laterite wall completed

GPS Cordinates

Latitude : 11.8033845

Longitude : 76.029995

Accuracy : 110

Attached images

img

Date: 26/09/2022

Work in progress | 56% Completed

100.00% valliyoorkavu temple-streetscape|100% Completed

0.00% Stone steps to temple|0% Completed

0.00% electrification|0% Completed

0.00% Lamp post|0% Completed

Laterite wall work ongoing

GPS Cordinates

Latitude : 11.8033828

Longitude : 76.0299808

Accuracy : 116.0999984741211

Attached images

img

Date: 19/09/2022

Work in progress | 56% Completed

0.00% Lamp post|0% Completed

100.00% valliyoorkavu temple-streetscape|100% Completed

0.00% Stone steps to temple|0% Completed

0.00% electrification|0% Completed

Earth work and concrete for steps completed. Latarite work for side wall ongoing

GPS Cordinates

Latitude : 11.8028128

Longitude : 76.0299432

Accuracy : 2000

Attached images

img

Joel J Varghese
Date: 20/11/2023

Work has been completed | 0% Completed

Final Bill Pending

Joel J Varghese
Date: 20/11/2023

Work has been completed | 0% Completed

Final Bill Pending

Joel J Varghese
Date: 20/11/2023

Work has been completed | 0% Completed

Final Bill Pending

Joel J Varghese
Date: 20/11/2023

Work has been completed | 0% Completed

Final Bill Pending

Joel J Varghese
Date: 20/11/2023

Work has been completed | 0% Completed

Final Bill Pending

Joel J Varghese
Date: 20/11/2023

Work has been completed | 0% Completed

Final Bill Pending

Joel J Varghese
Date: 20/11/2023

Work has been completed | 0% Completed

Final Bill Pending

Joel J Varghese
Date: 18/09/2023

Work has been completed | 0% Completed

Work has been completed Final RE and Final Bill Pending

Joel J Varghese
Date: 18/09/2023

Work has been completed | 0% Completed

Work has been completed Final RE and Final Bill Pending

Joel J Varghese
Date: 18/09/2023

Work has been completed | 0% Completed

Work has been completed Final RE and Final Bill Pending

Joel J Varghese
Date: 18/09/2023

Work has been completed | 0% Completed

Work has been completed Final RE and Final Bill Pending

Joel J Varghese
Date: 18/09/2023

Work has been completed | 0% Completed

Work has been completed Final RE and Final Bill Pending

Joel J Varghese
Date: 18/09/2023

Work has been completed | 0% Completed

Work has been completed Final RE and Final Bill Pending

Joel J Varghese
Date: 18/09/2023

Work has been completed | 0% Completed

Work has been completed Final RE and Final Bill Pending

Date: 24/06/2023

Work has been completed | 0% Completed

COMPLETED

Date: 24/06/2023

Work has been completed | 0% Completed

COMPLETED

Date: 24/06/2023

Work has been completed | 0% Completed

COMPLETED

Date: 24/06/2023

Work has been completed | 0% Completed

COMPLETED

Date: 24/06/2023

Work has been completed | 0% Completed

COMPLETED

Date: 24/06/2023

Work has been completed | 0% Completed

COMPLETED

Date: 24/06/2023

Work has been completed | 0% Completed

COMPLETED

Date: 19/05/2023

Work has been completed | 0% Completed

A2 lifting ongoing

Date: 19/05/2023

Work has been completed | 0% Completed

completed

Date: 19/05/2023

Work has been completed | 0% Completed

completed

Date: 19/05/2023

Work has been completed | 0% Completed

completed

Date: 19/05/2023

Work has been completed | 0% Completed

completed

Date: 19/05/2023

Work has been completed | 0% Completed

completed

Date: 19/05/2023

Work has been completed | 0% Completed

completed

Date: 19/05/2023

Work has been completed | 0% Completed

completed

Date: 19/05/2023

Work has been completed | 0% Completed

A2 lifting ongoing

Date: 19/05/2023

Work has been completed | 0% Completed

A2 lifting ongoing

Date: 19/05/2023

Work has been completed | 0% Completed

A2 lifting ongoing

Date: 19/05/2023

Work has been completed | 0% Completed

A2 lifting ongoing

Date: 19/05/2023

Work has been completed | 0% Completed

A2 lifting ongoing

Date: 19/05/2023

Work has been completed | 0% Completed

A2 lifting ongoing

Date: 13/05/2023

Work has been completed | 0% Completed

completed

Date: 13/05/2023

Work has been completed | 0% Completed

completed

Date: 13/05/2023

Work has been completed | 0% Completed

completed

Date: 13/05/2023

Work has been completed | 0% Completed

completed

Date: 13/05/2023

Work has been completed | 0% Completed

completed

Date: 13/05/2023

Work has been completed | 0% Completed

completed

Date: 13/05/2023

Work has been completed | 0% Completed

completed

Date: 08/05/2023

Work has been completed | 0% Completed

COMPLETED

Date: 08/05/2023

Work has been completed | 0% Completed

COMPLETED

Date: 08/05/2023

Work has been completed | 0% Completed

COMPLETED

Date: 08/05/2023

Work has been completed | 0% Completed

COMPLETED

Date: 08/05/2023

Work has been completed | 0% Completed

COMPLETED

Date: 08/05/2023

Work has been completed | 0% Completed

COMPLETED

Date: 08/05/2023

Work has been completed | 0% Completed

COMPLETED

Date: 24/04/2023

Work has been completed | 0% Completed

Completed 100%

Date: 24/04/2023

Work has been completed | 0% Completed

Completed 100%

Date: 24/04/2023

Work has been completed | 0% Completed

Completed 100%

Date: 24/04/2023

Work has been completed | 0% Completed

Completed 100%

Date: 24/04/2023

Work has been completed | 0% Completed

Completed 100%

Date: 24/04/2023

Work has been completed | 0% Completed

Completed 100%

Date: 24/04/2023

Work has been completed | 0% Completed

Completed 100%

Date: 10/04/2023

Work has been completed | 0% Completed

completed

Date: 10/04/2023

Work has been completed | 0% Completed

completed

Date: 10/04/2023

Work has been completed | 0% Completed

completed

Date: 10/04/2023

Work has been completed | 0% Completed

completed

Date: 10/04/2023

Work has been completed | 0% Completed

completed

Date: 10/04/2023

Work has been completed | 0% Completed

completed

Date: 10/04/2023

Work has been completed | 0% Completed

completed

Date: 03/04/2023

Work has been completed | 0% Completed

Completed

Date: 03/04/2023

Work has been completed | 0% Completed

Completed

Date: 03/04/2023

Work has been completed | 0% Completed

Completed

Date: 03/04/2023

Work has been completed | 0% Completed

Completed

Date: 03/04/2023

Work has been completed | 0% Completed

Completed

Date: 03/04/2023

Work has been completed | 0% Completed

Completed

Date: 03/04/2023

Work has been completed | 0% Completed

Completed

Date: 27/03/2023

Work has been completed | 0% Completed

100% COMPLETED

Date: 27/03/2023

Work has been completed | 0% Completed

100% COMPLETED

Date: 27/03/2023

Work has been completed | 0% Completed

100% COMPLETED

Date: 27/03/2023

Work has been completed | 0% Completed

100% COMPLETED

Date: 27/03/2023

Work has been completed | 0% Completed

100% COMPLETED

Date: 27/03/2023

Work has been completed | 0% Completed

100% COMPLETED

Date: 27/03/2023

Work has been completed | 0% Completed

100% COMPLETED

Date: 20/03/2023

Work has been completed | 0% Completed

completed

Date: 20/03/2023

Work has been completed | 0% Completed

completed

Date: 20/03/2023

Work has been completed | 0% Completed

completed

Date: 20/03/2023

Work has been completed | 0% Completed

completed

Date: 20/03/2023

Work has been completed | 0% Completed

completed

Date: 20/03/2023

Work has been completed | 0% Completed

completed

Date: 20/03/2023

Work has been completed | 0% Completed

completed

Date: 13/03/2023

Work has been completed | 0% Completed

completed

Date: 13/03/2023

Work has been completed | 0% Completed

completed

Date: 13/03/2023

Work has been completed | 0% Completed

completed

Date: 13/03/2023

Work has been completed | 0% Completed

completed

Date: 13/03/2023

Work has been completed | 0% Completed

completed

Date: 13/03/2023

Work has been completed | 0% Completed

completed

Date: 13/03/2023

Work has been completed | 0% Completed

completed

Date: 27/02/2023

Work in progress | 0% Completed

99 % work completed

Date: 27/02/2023

Work in progress | 0% Completed

99 % work completed

Date: 27/02/2023

Work in progress | 0% Completed

99 % work completed

Date: 27/02/2023

Work in progress | 0% Completed

99 % work completed

Date: 27/02/2023

Work in progress | 0% Completed

99 % work completed

Date: 27/02/2023

Work in progress | 0% Completed

99 % work completed

Date: 27/02/2023

Work in progress | 0% Completed

99 % work completed

Date: 20/02/2023

Work in progress | 0% Completed

Ele work completed

Date: 20/02/2023

Work in progress | 0% Completed

Ele work completed

Date: 20/02/2023

Work in progress | 0% Completed

Ele work completed

Date: 20/02/2023

Work in progress | 0% Completed

Ele work completed

Date: 20/02/2023

Work in progress | 0% Completed

Ele work completed

Date: 20/02/2023

Work in progress | 0% Completed

Ele work completed

Date: 20/02/2023

Work in progress | 0% Completed

Ele work completed

Date: 13/02/2023

Work in progress | 0% Completed

ELE WORK COMPLETED

Date: 13/02/2023

Work in progress | 0% Completed

ELE WORK COMPLETED

Date: 13/02/2023

Work in progress | 0% Completed

ELE WORK COMPLETED

Date: 13/02/2023

Work in progress | 0% Completed

ELE WORK COMPLETED

Date: 13/02/2023

Work in progress | 0% Completed

ELE WORK COMPLETED

Date: 13/02/2023

Work in progress | 0% Completed

ELE WORK COMPLETED

Date: 13/02/2023

Work in progress | 0% Completed

ELE WORK COMPLETED

Date: 06/02/2023

Work in progress | 0% Completed

Electrical work completed, Painting work ongoing

Date: 06/02/2023

Work in progress | 0% Completed

Electrical work completed, Painting work ongoing

Date: 06/02/2023

Work in progress | 0% Completed

Electrical work completed, Painting work ongoing

Date: 06/02/2023

Work in progress | 0% Completed

Electrical work completed, Painting work ongoing

Date: 06/02/2023

Work in progress | 0% Completed

Electrical work completed, Painting work ongoing

Date: 06/02/2023

Work in progress | 0% Completed

Electrical work completed, Painting work ongoing

Date: 06/02/2023

Work in progress | 0% Completed

Electrical work completed, Painting work ongoing

Date: 30/01/2023

Work in progress | 0% Completed

Ele work ongoing

Date: 30/01/2023

Work in progress | 0% Completed

Ele work ongoing

Date: 30/01/2023

Work in progress | 0% Completed

Ele work ongoing

Date: 30/01/2023

Work in progress | 0% Completed

Ele work ongoing

Date: 30/01/2023

Work in progress | 0% Completed

Ele work ongoing

Date: 30/01/2023

Work in progress | 0% Completed

Ele work ongoing

Date: 30/01/2023

Work in progress | 0% Completed

Ele work ongoing

Date: 23/01/2023

Work in progress | 0% Completed

Ele work ongoing

Date: 23/01/2023

Work in progress | 0% Completed

Ele work ongoing

Date: 23/01/2023

Work in progress | 0% Completed

Ele work ongoing

Date: 23/01/2023

Work in progress | 0% Completed

Ele work ongoing

Date: 23/01/2023

Work in progress | 0% Completed

Ele work ongoing

Date: 23/01/2023

Work in progress | 0% Completed

Ele work ongoing

Date: 23/01/2023

Work in progress | 0% Completed

Ele work ongoing

Date: 16/01/2023

Work in progress | 0% Completed

Ele work ongoing

Date: 16/01/2023

Work in progress | 0% Completed

Ele work ongoing

Date: 16/01/2023

Work in progress | 0% Completed

Ele work ongoing

Date: 16/01/2023

Work in progress | 0% Completed

Ele work ongoing

Date: 16/01/2023

Work in progress | 0% Completed

Ele work ongoing

Date: 16/01/2023

Work in progress | 0% Completed

Ele work ongoing

Date: 16/01/2023

Work in progress | 0% Completed

Ele work ongoing

Date: 09/01/2023

Work in progress | 0% Completed

Eletrical work ongoing

Attached images

img

Date: 09/01/2023

Work in progress | 0% Completed

Eletrical work ongoing

Attached images

img

Date: 09/01/2023

Work in progress | 0% Completed

Eletrical work ongoing

Attached images

img

Date: 09/01/2023

Work in progress | 0% Completed

Eletrical work ongoing

Attached images

img

Date: 09/01/2023

Work in progress | 0% Completed

Eletrical work ongoing

Attached images

img

Date: 09/01/2023

Work in progress | 0% Completed

Eletrical work ongoing

Attached images

img

Date: 09/01/2023

Work in progress | 0% Completed

Eletrical work ongoing

Attached images

img

Date: 02/01/2023

Work in progress | 0% Completed

Ele work ongoing

Date: 02/01/2023

Work in progress | 0% Completed

Ele work ongoing

Date: 02/01/2023

Work in progress | 0% Completed

Ele work ongoing

Date: 02/01/2023

Work in progress | 0% Completed

Ele work ongoing

Date: 02/01/2023

Work in progress | 0% Completed

Ele work ongoing

Date: 02/01/2023

Work in progress | 0% Completed

Ele work ongoing

Date: 02/01/2023

Work in progress | 0% Completed

Ele work ongoing

Date: 26/12/2022

Work in progress | 0% Completed

ele work ongoing

Date: 26/12/2022

Work in progress | 0% Completed

ele work ongoing

Date: 26/12/2022

Work in progress | 0% Completed

ele work ongoing

Date: 26/12/2022

Work in progress | 0% Completed

ele work ongoing

Date: 26/12/2022

Work in progress | 0% Completed

ele work ongoing

Date: 26/12/2022

Work in progress | 0% Completed

ele work ongoing

Date: 26/12/2022

Work in progress | 0% Completed

ele work ongoing

Date: 20/12/2022

Work in progress | 0% Completed

Stone paving completed

Attached images

img

Date: 20/12/2022

Work in progress | 0% Completed

Stone paving completed

Attached images

img

Date: 20/12/2022

Work in progress | 0% Completed

Stone paving completed

Attached images

img

Date: 20/12/2022

Work in progress | 0% Completed

Stone paving completed

Attached images

img

Date: 20/12/2022

Work in progress | 0% Completed

Stone paving completed

Attached images

img

Date: 20/12/2022

Work in progress | 0% Completed

Stone paving completed

Attached images

img

Date: 20/12/2022

Work in progress | 0% Completed

Stone paving completed

Attached images

img

Date: 12/12/2022

Work in progress | 0% Completed

Paving completed

Attached images

img

Date: 12/12/2022

Work in progress | 0% Completed

Paving completed

Attached images

img

Date: 12/12/2022

Work in progress | 0% Completed

Paving completed

Attached images

img

Date: 12/12/2022

Work in progress | 0% Completed

Paving completed

Attached images

img

Date: 12/12/2022

Work in progress | 0% Completed

Paving completed

Attached images

img

Date: 12/12/2022

Work in progress | 0% Completed

Paving completed

Attached images

img

Date: 12/12/2022

Work in progress | 0% Completed

Paving completed

Attached images

img

Date: 07/12/2022

Work in progress | 0% Completed

Sadhrahalli stone paving completed

Attached images

img

Date: 07/12/2022

Work in progress | 0% Completed

Sadhrahalli stone paving completed

Attached images

img

Date: 07/12/2022

Work in progress | 0% Completed

Sadhrahalli stone paving completed

Attached images

img

Date: 07/12/2022

Work in progress | 0% Completed

Sadhrahalli stone paving completed

Attached images

img

Date: 07/12/2022

Work in progress | 0% Completed

Sadhrahalli stone paving completed

Attached images

img

Date: 07/12/2022

Work in progress | 0% Completed

Sadhrahalli stone paving completed

Attached images

img

Date: 07/12/2022

Work in progress | 0% Completed

Sadhrahalli stone paving completed

Attached images

img

Date: 01/12/2022

Work in progress | 0% Completed

stone paving completed

Attached images

img

Date: 01/12/2022

Work in progress | 0% Completed

stone paving completed

Attached images

img

Date: 01/12/2022

Work in progress | 0% Completed

stone paving completed

Attached images

img

Date: 01/12/2022

Work in progress | 0% Completed

stone paving completed

Attached images

img

Date: 01/12/2022

Work in progress | 0% Completed

stone paving completed

Attached images

img

Date: 01/12/2022

Work in progress | 0% Completed

stone paving completed

Attached images

img

Date: 01/12/2022

Work in progress | 0% Completed

stone paving completed

Attached images

img

Date: 23/11/2022

Work in progress | 91% Completed

stone paving ongoing

Attached images

img

Date: 23/11/2022

Work in progress | 91% Completed

stone paving ongoing

Attached images

img

Date: 23/11/2022

Work in progress | 91% Completed

stone paving ongoing

Attached images

img

Date: 23/11/2022

Work in progress | 91% Completed

stone paving ongoing

Attached images

img

Date: 23/11/2022

Work in progress | 91% Completed

stone paving ongoing

Attached images

img

Date: 23/11/2022

Work in progress | 91% Completed

stone paving ongoing

Attached images

img

Date: 23/11/2022

Work in progress | 91% Completed

stone paving ongoing

Attached images

img

Date: 11/11/2022

Work in progress | 90% Completed

Sadhrahalli paving ongoing

Attached images

img

Date: 11/11/2022

Work in progress | 90% Completed

Sadhrahalli paving ongoing

Attached images

img

Date: 11/11/2022

Work in progress | 90% Completed

Sadhrahalli paving ongoing

Attached images

img

Date: 11/11/2022

Work in progress | 90% Completed

Sadhrahalli paving ongoing

Attached images

img

Date: 11/11/2022

Work in progress | 90% Completed

Sadhrahalli paving ongoing

Attached images

img

Date: 11/11/2022

Work in progress | 90% Completed

Sadhrahalli paving ongoing

Attached images

img

Date: 11/11/2022

Work in progress | 90% Completed

Sadhrahalli paving ongoing

Attached images

img

Date: 03/11/2022

Work in progress | 0% Completed

Plastering work ongoing

Attached images

img

Date: 03/11/2022

Work in progress | 0% Completed

Plastering work ongoing

Attached images

img

Date: 03/11/2022

Work in progress | 0% Completed

Plastering work ongoing

Attached images

img

Date: 03/11/2022

Work in progress | 0% Completed

Plastering work ongoing

Attached images

img

Date: 03/11/2022

Work in progress | 0% Completed

Plastering work ongoing

Attached images

img

Date: 03/11/2022

Work in progress | 0% Completed

Plastering work ongoing

Attached images

img

Date: 03/11/2022

Work in progress | 0% Completed

Plastering work ongoing

Attached images

img

Date: 01/11/2022

Work in progress | 0% Completed

Plastering ongoing

Attached images

img

Date: 01/11/2022

Work in progress | 0% Completed

Plastering ongoing

Attached images

img

Date: 01/11/2022

Work in progress | 0% Completed

Plastering ongoing

Attached images

img

Date: 01/11/2022

Work in progress | 0% Completed

Plastering ongoing

Attached images

img

Date: 01/11/2022

Work in progress | 0% Completed

Plastering ongoing

Attached images

img

Date: 01/11/2022

Work in progress | 0% Completed

Plastering ongoing

Attached images

img

Date: 01/11/2022

Work in progress | 0% Completed

Plastering ongoing

Attached images

img

Date: 25/10/2022

Work in progress | 0% Completed

Electrical work ongoing

Attached images

img

Date: 25/10/2022

Work in progress | 0% Completed

Electrical work ongoing

Attached images

img

Date: 25/10/2022

Work in progress | 0% Completed

Electrical work ongoing

Attached images

img

Date: 25/10/2022

Work in progress | 0% Completed

Electrical work ongoing

Attached images

img

Date: 25/10/2022

Work in progress | 0% Completed

Electrical work ongoing

Attached images

img

Date: 25/10/2022

Work in progress | 0% Completed

Electrical work ongoing

Attached images

img

Date: 25/10/2022

Work in progress | 0% Completed

Electrical work ongoing

Attached images

img

Date: 22/10/2022

Work in progress | 0% Completed

Rcc pier concrete completed

Attached images

img

Date: 22/10/2022

Work in progress | 0% Completed

Rcc pier concrete completed

Attached images

img

Date: 22/10/2022

Work in progress | 0% Completed

Rcc pier concrete completed

Attached images

img

Date: 22/10/2022

Work in progress | 0% Completed

Rcc pier concrete completed

Attached images

img

Date: 22/10/2022

Work in progress | 0% Completed

Rcc pier concrete completed

Attached images

img

Date: 22/10/2022

Work in progress | 0% Completed

Rcc pier concrete completed

Attached images

img

Date: 22/10/2022

Work in progress | 0% Completed

Rcc pier concrete completed

Attached images

img

Date: 19/10/2022

Work in progress | 75% Completed

Sadrahalli Stone paving ongoing

Attached images

img

Date: 19/10/2022

Work in progress | 75% Completed

Sadrahalli Stone paving ongoing

Attached images

img

Date: 19/10/2022

Work in progress | 75% Completed

Sadrahalli Stone paving ongoing

Attached images

img

Date: 19/10/2022

Work in progress | 75% Completed

Sadrahalli Stone paving ongoing

Attached images

img

Date: 19/10/2022

Work in progress | 75% Completed

Sadrahalli Stone paving ongoing

Attached images

img

Date: 19/10/2022

Work in progress | 75% Completed

Sadrahalli Stone paving ongoing

Attached images

img

Date: 19/10/2022

Work in progress | 75% Completed

Sadrahalli Stone paving ongoing

Attached images

img

Date: 12/10/2022

Work in progress | 0% Completed

Laterite wall

Attached images

img

Date: 12/10/2022

Work in progress | 0% Completed

Laterite wall

Attached images

img

Date: 12/10/2022

Work in progress | 0% Completed

Laterite wall

Attached images

img

Date: 12/10/2022

Work in progress | 0% Completed

Laterite wall

Attached images

img

Date: 12/10/2022

Work in progress | 0% Completed

Laterite wall

Attached images

img

Date: 12/10/2022

Work in progress | 0% Completed

Laterite wall

Attached images

img

Date: 12/10/2022

Work in progress | 0% Completed

Laterite wall

Attached images

img

Date: 04/10/2022

Work in progress | 0% Completed

Laterite wall completed

Attached images

img

Date: 04/10/2022

Work in progress | 0% Completed

Laterite wall completed

Attached images

img

Date: 04/10/2022

Work in progress | 0% Completed

Laterite wall completed

Attached images

img

Date: 04/10/2022

Work in progress | 0% Completed

Laterite wall completed

Attached images

img

Date: 04/10/2022

Work in progress | 0% Completed

Laterite wall completed

Attached images

img

Date: 04/10/2022

Work in progress | 0% Completed

Laterite wall completed

Attached images

img

Date: 04/10/2022

Work in progress | 0% Completed

Laterite wall completed

Attached images

img

Date: 26/09/2022

Work in progress | 0% Completed

Laterite wall work ongoing

Attached images

img

Date: 26/09/2022

Work in progress | 0% Completed

Laterite wall work ongoing

Attached images

img

Date: 26/09/2022

Work in progress | 0% Completed

Laterite wall work ongoing

Attached images

img

Date: 26/09/2022

Work in progress | 0% Completed

Laterite wall work ongoing

Attached images

img

Date: 26/09/2022

Work in progress | 0% Completed

Laterite wall work ongoing

Attached images

img

Date: 26/09/2022

Work in progress | 0% Completed

Laterite wall work ongoing

Attached images

img

Date: 26/09/2022

Work in progress | 0% Completed

Laterite wall work ongoing

Attached images

img

Date: 19/09/2022

Work in progress | 0% Completed

Earth work and concrete for steps completed. Latarite work for side wall ongoing

Attached images

img

Date: 19/09/2022

Work in progress | 0% Completed

Earth work and concrete for steps completed. Latarite work for side wall ongoing

Attached images

img

Date: 19/09/2022

Work in progress | 0% Completed

Earth work and concrete for steps completed. Latarite work for side wall ongoing

Attached images

img

Date: 19/09/2022

Work in progress | 0% Completed

Earth work and concrete for steps completed. Latarite work for side wall ongoing

Attached images

img

Date: 19/09/2022

Work in progress | 0% Completed

Earth work and concrete for steps completed. Latarite work for side wall ongoing

Attached images

img

Date: 19/09/2022

Work in progress | 0% Completed

Earth work and concrete for steps completed. Latarite work for side wall ongoing

Attached images

img

Date: 19/09/2022

Work in progress | 0% Completed

Earth work and concrete for steps completed. Latarite work for side wall ongoing

Attached images

img