Nithish C
Date: 26/07/2024

Work in progress | 34% Completed

% |0% Completed

Total sale quantity- 34.26% Total quantity stacked inside the dam - 29.18%

Attached images

img

Nithish C
Date: 02/04/2024

Work in progress | 22% Completed

% |0% Completed

Sand loading to truck

Attached images

img

Nithish C
Date: 26/03/2024

Work in progress | 22% Completed

% |0% Completed

New seperatuon plant P7 working

Attached images

img

Nithish C
Date: 17/03/2024

Work in progress | 22% Completed

% |0% Completed

Wet excavation at grid number 438 and 439

Attached images

img

Nithish C
Date: 10/03/2024

Work in progress | 21% Completed

% |0% Completed

Sand loading to truck

Attached images

img

Nithish C
Date: 05/03/2024

Work in progress | 21% Completed

% |0% Completed

Total sale quantity- 244965 m3

Attached images

img

Nithish C
Date: 28/02/2024

Work in progress | 21% Completed

% |0% Completed

Total sale quantity- 240049m3

Attached images

img

Nithish C
Date: 01/01/2024

Work in progress | 16% Completed

% |0% Completed

Work on hold

Nithish C
Date: 12/12/2023

Work in progress | 16% Completed

% |0% Completed

Sand separation work progressing

Attached images

img

Nithish C
Date: 08/11/2023

Work in progress | 14% Completed

% |0% Completed

Sand separation plant

Attached images

img

Nithish C
Date: 02/11/2023

Work in progress | 14% Completed

% |0% Completed

Sand production unit

Attached images

img

Nithish C
Date: 25/10/2023

Work in progress | 14% Completed

% |0% Completed

Sand loading to lorry

Attached images

img

Nithish C
Date: 16/10/2023

Work in progress | 14% Completed

% |0% Completed

Sand loading to lorry

Attached images

img

Nithish C
Date: 11/10/2023

Work in progress | 14% Completed

% |0% Completed

Sand loading to tipper

Attached images

img

Nithish C
Date: 04/10/2023

Work in progress | 13% Completed

% |0% Completed

Sand loading to lorry

Attached images

img

Nithish C
Date: 19/09/2023

Work in progress | 13% Completed

% |0% Completed

Sand loading at lorry

Attached images

img

Nithish C
Date: 12/09/2023

Work in progress | 13% Completed

% |0% Completed

Sand loading in tipper

Attached images

img

Nithish C
Date: 05/09/2023

Work in progress | 13% Completed

% |0% Completed

Sand seperation at grid number 440

Attached images

img

Nithish C
Date: 22/08/2023

Work in progress | 13% Completed

% |0% Completed

Silt excavation proceess ongoing

Nithish C
Date: 15/08/2023

Work in progress | 13% Completed

% |0% Completed

Soil excavation at grid number 643

Attached images

img

Nithish C
Date: 08/08/2023

Work in progress | 13% Completed

% |0% Completed

Soil excavation at grid number 438

Attached images

img

Nithish C
Date: 01/08/2023

Work in progress | 13% Completed

% |0% Completed

Silt excavation for sand

Attached images

img

Nithish C
Date: 24/07/2023

Work in progress | 12% Completed

% |0% Completed

Excavation at grid numbers 271 and 272 ongoing

Attached images

img

Nithish C
Date: 02/05/2023

Work in progress | 4% Completed

% |0% Completed

Clay excavation at grid numbers 488 ,492

GPS Cordinates

Latitude : 10.7282432

Longitude : 76.7819776

Accuracy : 5419.080289885569

Attached images

img

Nithish C
Date: 26/04/2023

Work in progress | 4% Completed

% |0% Completed

Excavation of clay at grid numbers 488,492

GPS Cordinates

Latitude : 10.73152

Longitude : 76.7819776

Accuracy : 5476.15860200956

Attached images

img

Nithish C
Date: 17/04/2023

Work in progress | 4% Completed

% |0% Completed

Clay excavation at grid numbers 488 and 492

GPS Cordinates

Latitude : 10.7007716

Longitude : 76.750966

Accuracy : 1703.7828267076056

Attached images

img

Nithish C
Date: 10/04/2023

Work in progress | 3% Completed

% |0% Completed

Silt excavation at grid numbers 438,440

GPS Cordinates

Latitude : 10.7007716

Longitude : 76.750966

Accuracy : 1703.7828267076056

Attached images

img

Nithish C
Date: 03/04/2023

Work in progress | 3% Completed

% |0% Completed

Silt excavation at grid number 438,440

GPS Cordinates

Latitude : 9.9312328

Longitude : 76.2673041

Accuracy : 16893.07305711459

Attached images

img

Nithish C
Date: 28/03/2023

Work in progress | 3% Completed

% |0% Completed

Clay excavation at grid numbers 487,491

GPS Cordinates

Latitude : 10.7184128

Longitude : 76.7688704

Accuracy : 4668.414726083723

Attached images

img

Nithish C
Date: 20/03/2023

Work in progress | 3% Completed

% |0% Completed

Excavation of clay at grid numbers 487,491

GPS Cordinates

Latitude : 10.7215141

Longitude : 76.8490328

Accuracy : 4422.080452293195

Attached images

img

Nithish C
Date: 06/03/2023

Work in progress | 3% Completed

% |0% Completed

Excavation at grid numbers 508,538

GPS Cordinates

Latitude : 10.7215141

Longitude : 76.8490328

Accuracy : 4422.080452293195

Attached images

img

Nithish C
Date: 27/02/2023

Work in progress | 2% Completed

% |0% Completed

Excavation at grid numbers 534,538

GPS Cordinates

Latitude : 10.7282432

Longitude : 76.7885312

Accuracy : 5843.19891874529

Attached images

img

Nithish C
Date: 27/02/2023

Work in progress | 2% Completed

% |0% Completed

Excavation at grid number 534,538

GPS Cordinates

Latitude : 10.7282432

Longitude : 76.7885312

Accuracy : 5843.19891874529

Attached images

img

Nithish C
Date: 20/02/2023

Work in progress | 2% Completed

% |0% Completed

Excavation at grid numbers 534 and 538

GPS Cordinates

Latitude : 10.7007716

Longitude : 76.750966

Accuracy : 1703.7828267076056

Attached images

img

Nithish C
Date: 13/02/2023

Work in progress | 2% Completed

% |0% Completed

Exacavation at grid number 512,513

GPS Cordinates

Latitude : 10.7215141

Longitude : 76.8490328

Accuracy : 4422.080452293195

Attached images

img

Nithish C
Date: 06/02/2023

Work in progress | 2% Completed

% |0% Completed

Excavation of clay at grid numbers 614,617 and 620

GPS Cordinates

Latitude : 10.5866868

Longitude : 76.7636187

Accuracy : 106.767

Attached images

img

Nithish C
Date: 31/01/2023

Work in progress | 2% Completed

% |0% Completed

Excavations at grid numbers 614,617,621,530

GPS Cordinates

Latitude : 9.9312328

Longitude : 76.2673041

Accuracy : 16893.07305711459

Attached images

img

Nithish C
Date: 23/01/2023

Work in progress | 2% Completed

% |0% Completed

Excavation at grid 674,675

GPS Cordinates

Latitude : 10.7282432

Longitude : 76.775424

Accuracy : 5226.455840126489

Attached images

img

Nithish C
Date: 16/01/2023

Work in progress | 2% Completed

% |0% Completed

Seperation plant trial running

GPS Cordinates

Latitude : 10.7007716

Longitude : 76.750966

Accuracy : 1703.7828267076056

Attached images

img

Nithish C
Date: 11/01/2023

Work in progress | 1% Completed

% |0% Completed

Dry and wet excavation at grid numbers 637,638,632,633,636,634,620,619,616,617,613,614,680,678,676,642 and 655

GPS Cordinates

Latitude : 10.7007716

Longitude : 76.750966

Accuracy : 1703.7828267076056

Attached images

img

Nithish C
Date: 26/07/2024

Work in progress | 0% Completed

Total sale quantity- 34.26% Total quantity stacked inside the dam - 29.18%

Attached images

img

Nithish C
Date: 02/04/2024

Work in progress | 0% Completed

Sand loading to truck

Attached images

img

Nithish C
Date: 26/03/2024

Work in progress | 0% Completed

New seperatuon plant P7 working

Attached images

img

Nithish C
Date: 17/03/2024

Work in progress | 0% Completed

Wet excavation at grid number 438 and 439

Attached images

img

Nithish C
Date: 10/03/2024

Work in progress | 0% Completed

Sand loading to truck

Attached images

img

Nithish C
Date: 05/03/2024

Work in progress | 0% Completed

Total sale quantity- 244965 m3

Attached images

img

Nithish C
Date: 28/02/2024

Work in progress | 0% Completed

Total sale quantity- 240049m3

Attached images

img

Nithish C
Date: 01/01/2024

Work in progress | 0% Completed

Work on hold

Nithish C
Date: 12/12/2023

Work in progress | 0% Completed

Sand separation work progressing

Attached images

img

Nithish C
Date: 08/11/2023

Work in progress | 0% Completed

Sand separation plant

Attached images

img

Nithish C
Date: 02/11/2023

Work in progress | 0% Completed

Sand production unit

Attached images

img

Nithish C
Date: 25/10/2023

Work in progress | 0% Completed

Sand loading to lorry

Attached images

img

Nithish C
Date: 16/10/2023

Work in progress | 0% Completed

Sand loading to lorry

Attached images

img

Nithish C
Date: 11/10/2023

Work in progress | 0% Completed

Sand loading to tipper

Attached images

img

Nithish C
Date: 04/10/2023

Work in progress | 0% Completed

Sand loading to lorry

Attached images

img

Nithish C
Date: 19/09/2023

Work in progress | 0% Completed

Sand loading at lorry

Attached images

img

Nithish C
Date: 12/09/2023

Work in progress | 0% Completed

Sand loading in tipper

Attached images

img

Nithish C
Date: 05/09/2023

Work in progress | 0% Completed

Sand seperation at grid number 440

Attached images

img

Nithish C
Date: 22/08/2023

Work in progress | 0% Completed

Silt excavation proceess ongoing

Nithish C
Date: 15/08/2023

Work in progress | 0% Completed

Soil excavation at grid number 643

Attached images

img

Nithish C
Date: 08/08/2023

Work in progress | 0% Completed

Soil excavation at grid number 438

Attached images

img

Nithish C
Date: 01/08/2023

Work in progress | 0% Completed

Silt excavation for sand

Attached images

img

Nithish C
Date: 24/07/2023

Work in progress | 0% Completed

Excavation at grid numbers 271 and 272 ongoing

Attached images

img

Nithish C
Date: 02/05/2023

Work in progress | 0% Completed

Clay excavation at grid numbers 488 ,492

Attached images

img

Nithish C
Date: 26/04/2023

Work in progress | 0% Completed

Excavation of clay at grid numbers 488,492

Attached images

img

Nithish C
Date: 17/04/2023

Work in progress | 0% Completed

Clay excavation at grid numbers 488 and 492

Attached images

img

Nithish C
Date: 10/04/2023

Work in progress | 0% Completed

Silt excavation at grid numbers 438,440

Attached images

img

Nithish C
Date: 03/04/2023

Work in progress | 0% Completed

Silt excavation at grid number 438,440

Attached images

img

Nithish C
Date: 28/03/2023

Work in progress | 0% Completed

Clay excavation at grid numbers 487,491

Attached images

img

Nithish C
Date: 20/03/2023

Work in progress | 0% Completed

Excavation of clay at grid numbers 487,491

Attached images

img

Nithish C
Date: 06/03/2023

Work in progress | 0% Completed

Excavation at grid numbers 508,538

Attached images

img

Nithish C
Date: 27/02/2023

Work in progress | 0% Completed

Excavation at grid numbers 534,538

Attached images

img

Nithish C
Date: 27/02/2023

Work in progress | 0% Completed

Excavation at grid number 534,538

Attached images

img

Nithish C
Date: 20/02/2023

Work in progress | 0% Completed

Excavation at grid numbers 534 and 538

Attached images

img

Nithish C
Date: 13/02/2023

Work in progress | 0% Completed

Exacavation at grid number 512,513

Attached images

img

Nithish C
Date: 06/02/2023

Work in progress | 0% Completed

Excavation of clay at grid numbers 614,617 and 620

Attached images

img

Nithish C
Date: 31/01/2023

Work in progress | 0% Completed

Excavations at grid numbers 614,617,621,530

Attached images

img

Nithish C
Date: 23/01/2023

Work in progress | 0% Completed

Excavation at grid 674,675

Attached images

img

Nithish C
Date: 16/01/2023

Work in progress | 0% Completed

Seperation plant trial running

Attached images

img

Nithish C
Date: 11/01/2023

Work in progress | 0% Completed

Dry and wet excavation at grid numbers 637,638,632,633,636,634,620,619,616,617,613,614,680,678,676,642 and 655

Attached images

img