Praveen Jose
Date: 18/07/2025

Work in progress | 65% Completed

% |0% Completed

Excavation activities are currently on hold due to elevated water levels in the dam, which has made further operations temporarily unfeasible. However, outward passes are being issued from the yard

Attached images

img

Nithish C
Date: 26/07/2024

Work in progress | 34% Completed

% |0% Completed

Total sale quantity- 34.26% Total quantity stacked inside the dam - 29.18%

Attached images

img

Nithish C
Date: 02/04/2024

Work in progress | 22% Completed

% |0% Completed

Sand loading to truck

Attached images

img

Nithish C
Date: 26/03/2024

Work in progress | 22% Completed

% |0% Completed

New seperatuon plant P7 working

Attached images

img

Nithish C
Date: 17/03/2024

Work in progress | 22% Completed

% |0% Completed

Wet excavation at grid number 438 and 439

Attached images

img

Nithish C
Date: 10/03/2024

Work in progress | 21% Completed

% |0% Completed

Sand loading to truck

Attached images

img

Nithish C
Date: 05/03/2024

Work in progress | 21% Completed

% |0% Completed

Total sale quantity- 244965 m3

Attached images

img

Nithish C
Date: 28/02/2024

Work in progress | 21% Completed

% |0% Completed

Total sale quantity- 240049m3

Attached images

img

Nithish C
Date: 01/01/2024

Work in progress | 16% Completed

% |0% Completed

Work on hold

Nithish C
Date: 12/12/2023

Work in progress | 16% Completed

% |0% Completed

Sand separation work progressing

Attached images

img

Nithish C
Date: 08/11/2023

Work in progress | 14% Completed

% |0% Completed

Sand separation plant

Attached images

img

Nithish C
Date: 02/11/2023

Work in progress | 14% Completed

% |0% Completed

Sand production unit

Attached images

img

Nithish C
Date: 25/10/2023

Work in progress | 14% Completed

% |0% Completed

Sand loading to lorry

Attached images

img

Nithish C
Date: 16/10/2023

Work in progress | 14% Completed

% |0% Completed

Sand loading to lorry

Attached images

img

Nithish C
Date: 11/10/2023

Work in progress | 14% Completed

% |0% Completed

Sand loading to tipper

Attached images

img

Nithish C
Date: 04/10/2023

Work in progress | 13% Completed

% |0% Completed

Sand loading to lorry

Attached images

img

Nithish C
Date: 19/09/2023

Work in progress | 13% Completed

% |0% Completed

Sand loading at lorry

Attached images

img

Nithish C
Date: 12/09/2023

Work in progress | 13% Completed

% |0% Completed

Sand loading in tipper

Attached images

img

Nithish C
Date: 05/09/2023

Work in progress | 13% Completed

% |0% Completed

Sand seperation at grid number 440

Attached images

img

Nithish C
Date: 22/08/2023

Work in progress | 13% Completed

% |0% Completed

Silt excavation proceess ongoing

Nithish C
Date: 15/08/2023

Work in progress | 13% Completed

% |0% Completed

Soil excavation at grid number 643

Attached images

img

Nithish C
Date: 08/08/2023

Work in progress | 13% Completed

% |0% Completed

Soil excavation at grid number 438

Attached images

img

Nithish C
Date: 01/08/2023

Work in progress | 13% Completed

% |0% Completed

Silt excavation for sand

Attached images

img

Nithish C
Date: 24/07/2023

Work in progress | 12% Completed

% |0% Completed

Excavation at grid numbers 271 and 272 ongoing

Attached images

img

Nithish C
Date: 02/05/2023

Work in progress | 4% Completed

% |0% Completed

Clay excavation at grid numbers 488 ,492

GPS Cordinates

Latitude : 10.7282432

Longitude : 76.7819776

Accuracy : 5419.080289885569

Attached images

img

Nithish C
Date: 26/04/2023

Work in progress | 4% Completed

% |0% Completed

Excavation of clay at grid numbers 488,492

GPS Cordinates

Latitude : 10.73152

Longitude : 76.7819776

Accuracy : 5476.15860200956

Attached images

img

Nithish C
Date: 17/04/2023

Work in progress | 4% Completed

% |0% Completed

Clay excavation at grid numbers 488 and 492

GPS Cordinates

Latitude : 10.7007716

Longitude : 76.750966

Accuracy : 1703.7828267076056

Attached images

img

Nithish C
Date: 10/04/2023

Work in progress | 3% Completed

% |0% Completed

Silt excavation at grid numbers 438,440

GPS Cordinates

Latitude : 10.7007716

Longitude : 76.750966

Accuracy : 1703.7828267076056

Attached images

img

Nithish C
Date: 03/04/2023

Work in progress | 3% Completed

% |0% Completed

Silt excavation at grid number 438,440

GPS Cordinates

Latitude : 9.9312328

Longitude : 76.2673041

Accuracy : 16893.07305711459

Attached images

img

Nithish C
Date: 28/03/2023

Work in progress | 3% Completed

% |0% Completed

Clay excavation at grid numbers 487,491

GPS Cordinates

Latitude : 10.7184128

Longitude : 76.7688704

Accuracy : 4668.414726083723

Attached images

img

Nithish C
Date: 20/03/2023

Work in progress | 3% Completed

% |0% Completed

Excavation of clay at grid numbers 487,491

GPS Cordinates

Latitude : 10.7215141

Longitude : 76.8490328

Accuracy : 4422.080452293195

Attached images

img

Nithish C
Date: 06/03/2023

Work in progress | 3% Completed

% |0% Completed

Excavation at grid numbers 508,538

GPS Cordinates

Latitude : 10.7215141

Longitude : 76.8490328

Accuracy : 4422.080452293195

Attached images

img

Nithish C
Date: 27/02/2023

Work in progress | 2% Completed

% |0% Completed

Excavation at grid numbers 534,538

GPS Cordinates

Latitude : 10.7282432

Longitude : 76.7885312

Accuracy : 5843.19891874529

Attached images

img

Nithish C
Date: 27/02/2023

Work in progress | 2% Completed

% |0% Completed

Excavation at grid number 534,538

GPS Cordinates

Latitude : 10.7282432

Longitude : 76.7885312

Accuracy : 5843.19891874529

Attached images

img

Nithish C
Date: 20/02/2023

Work in progress | 2% Completed

% |0% Completed

Excavation at grid numbers 534 and 538

GPS Cordinates

Latitude : 10.7007716

Longitude : 76.750966

Accuracy : 1703.7828267076056

Attached images

img

Nithish C
Date: 13/02/2023

Work in progress | 2% Completed

% |0% Completed

Exacavation at grid number 512,513

GPS Cordinates

Latitude : 10.7215141

Longitude : 76.8490328

Accuracy : 4422.080452293195

Attached images

img

Nithish C
Date: 06/02/2023

Work in progress | 2% Completed

% |0% Completed

Excavation of clay at grid numbers 614,617 and 620

GPS Cordinates

Latitude : 10.5866868

Longitude : 76.7636187

Accuracy : 106.767

Attached images

img

Nithish C
Date: 31/01/2023

Work in progress | 2% Completed

% |0% Completed

Excavations at grid numbers 614,617,621,530

GPS Cordinates

Latitude : 9.9312328

Longitude : 76.2673041

Accuracy : 16893.07305711459

Attached images

img

Nithish C
Date: 23/01/2023

Work in progress | 2% Completed

% |0% Completed

Excavation at grid 674,675

GPS Cordinates

Latitude : 10.7282432

Longitude : 76.775424

Accuracy : 5226.455840126489

Attached images

img

Nithish C
Date: 16/01/2023

Work in progress | 2% Completed

% |0% Completed

Seperation plant trial running

GPS Cordinates

Latitude : 10.7007716

Longitude : 76.750966

Accuracy : 1703.7828267076056

Attached images

img

Nithish C
Date: 11/01/2023

Work in progress | 1% Completed

% |0% Completed

Dry and wet excavation at grid numbers 637,638,632,633,636,634,620,619,616,617,613,614,680,678,676,642 and 655

GPS Cordinates

Latitude : 10.7007716

Longitude : 76.750966

Accuracy : 1703.7828267076056

Attached images

img

Praveen Jose
Date: 18/07/2025

Work in progress | 0% Completed

Excavation activities are currently on hold due to elevated water levels in the dam, which has made further operations temporarily unfeasible. However, outward passes are being issued from the yard

Attached images

img

Nithish C
Date: 26/07/2024

Work in progress | 0% Completed

Total sale quantity- 34.26% Total quantity stacked inside the dam - 29.18%

Attached images

img

Nithish C
Date: 02/04/2024

Work in progress | 0% Completed

Sand loading to truck

Attached images

img

Nithish C
Date: 26/03/2024

Work in progress | 0% Completed

New seperatuon plant P7 working

Attached images

img

Nithish C
Date: 17/03/2024

Work in progress | 0% Completed

Wet excavation at grid number 438 and 439

Attached images

img

Nithish C
Date: 10/03/2024

Work in progress | 0% Completed

Sand loading to truck

Attached images

img

Nithish C
Date: 05/03/2024

Work in progress | 0% Completed

Total sale quantity- 244965 m3

Attached images

img

Nithish C
Date: 28/02/2024

Work in progress | 0% Completed

Total sale quantity- 240049m3

Attached images

img

Nithish C
Date: 01/01/2024

Work in progress | 0% Completed

Work on hold

Nithish C
Date: 12/12/2023

Work in progress | 0% Completed

Sand separation work progressing

Attached images

img

Nithish C
Date: 08/11/2023

Work in progress | 0% Completed

Sand separation plant

Attached images

img

Nithish C
Date: 02/11/2023

Work in progress | 0% Completed

Sand production unit

Attached images

img

Nithish C
Date: 25/10/2023

Work in progress | 0% Completed

Sand loading to lorry

Attached images

img

Nithish C
Date: 16/10/2023

Work in progress | 0% Completed

Sand loading to lorry

Attached images

img

Nithish C
Date: 11/10/2023

Work in progress | 0% Completed

Sand loading to tipper

Attached images

img

Nithish C
Date: 04/10/2023

Work in progress | 0% Completed

Sand loading to lorry

Attached images

img

Nithish C
Date: 19/09/2023

Work in progress | 0% Completed

Sand loading at lorry

Attached images

img

Nithish C
Date: 12/09/2023

Work in progress | 0% Completed

Sand loading in tipper

Attached images

img

Nithish C
Date: 05/09/2023

Work in progress | 0% Completed

Sand seperation at grid number 440

Attached images

img

Nithish C
Date: 22/08/2023

Work in progress | 0% Completed

Silt excavation proceess ongoing

Nithish C
Date: 15/08/2023

Work in progress | 0% Completed

Soil excavation at grid number 643

Attached images

img

Nithish C
Date: 08/08/2023

Work in progress | 0% Completed

Soil excavation at grid number 438

Attached images

img

Nithish C
Date: 01/08/2023

Work in progress | 0% Completed

Silt excavation for sand

Attached images

img

Nithish C
Date: 24/07/2023

Work in progress | 0% Completed

Excavation at grid numbers 271 and 272 ongoing

Attached images

img

Nithish C
Date: 02/05/2023

Work in progress | 0% Completed

Clay excavation at grid numbers 488 ,492

Attached images

img

Nithish C
Date: 26/04/2023

Work in progress | 0% Completed

Excavation of clay at grid numbers 488,492

Attached images

img

Nithish C
Date: 17/04/2023

Work in progress | 0% Completed

Clay excavation at grid numbers 488 and 492

Attached images

img

Nithish C
Date: 10/04/2023

Work in progress | 0% Completed

Silt excavation at grid numbers 438,440

Attached images

img

Nithish C
Date: 03/04/2023

Work in progress | 0% Completed

Silt excavation at grid number 438,440

Attached images

img

Nithish C
Date: 28/03/2023

Work in progress | 0% Completed

Clay excavation at grid numbers 487,491

Attached images

img

Nithish C
Date: 20/03/2023

Work in progress | 0% Completed

Excavation of clay at grid numbers 487,491

Attached images

img

Nithish C
Date: 06/03/2023

Work in progress | 0% Completed

Excavation at grid numbers 508,538

Attached images

img

Nithish C
Date: 27/02/2023

Work in progress | 0% Completed

Excavation at grid numbers 534,538

Attached images

img

Nithish C
Date: 27/02/2023

Work in progress | 0% Completed

Excavation at grid number 534,538

Attached images

img

Nithish C
Date: 20/02/2023

Work in progress | 0% Completed

Excavation at grid numbers 534 and 538

Attached images

img

Nithish C
Date: 13/02/2023

Work in progress | 0% Completed

Exacavation at grid number 512,513

Attached images

img

Nithish C
Date: 06/02/2023

Work in progress | 0% Completed

Excavation of clay at grid numbers 614,617 and 620

Attached images

img

Nithish C
Date: 31/01/2023

Work in progress | 0% Completed

Excavations at grid numbers 614,617,621,530

Attached images

img

Nithish C
Date: 23/01/2023

Work in progress | 0% Completed

Excavation at grid 674,675

Attached images

img

Nithish C
Date: 16/01/2023

Work in progress | 0% Completed

Seperation plant trial running

Attached images

img

Nithish C
Date: 11/01/2023

Work in progress | 0% Completed

Dry and wet excavation at grid numbers 637,638,632,633,636,634,620,619,616,617,613,614,680,678,676,642 and 655

Attached images

img