Abhinandh P T |
Date: 17/03/2025 |
Work in progress | 16% Completed
|0% Completed
General Works – Earth filling is 95% complete, and storytelling wall work is 90% finished. Pond Renovation – Laterite step work is in progress. OAT foundation PCC completed overall all status -16% Financial Progress-14%
Abhinandh P T |
Date: 05/03/2025 |
Work in progress | 11% Completed
|0% Completed
General Works – Earth filling is 95% complete, and storytelling wall work is 50% finished. Pond Renovation – Laterite step work is in progress. overall all status -10% Financial Progress-0% open air theater- PCC ongoing
Abhinandh P T |
Date: 18/02/2025 |
Abhinandh P T |
Date: 18/02/2025 |
Work in progress | 9% Completed
|0% Completed
General Works – Earth filling is 95% complete, and storytelling wall work is 50% finished. Pond Renovation – Laterite step work is in progress. overall all status -10% Financial Progress-0%
Abhinandh P T |
Date: 10/02/2025 |
Work in progress | 8% Completed
|0% Completed
story telling wall laterite work completed
Abhinandh P T |
Date: 07/02/2025 |
Work in progress | 8% Completed
|0% Completed
story telling wall laterite work completed
Abhinandh P T |
Date: 22/01/2025 |
Work in progress | 5% Completed
|0% Completed
story telling wall work under progress
Abhinandh P T |
Date: 03/01/2025 |
Work in progress | 5% Completed
|0% Completed
earth filling completed 80%
Abhinandh P T |
Date: 12/12/2024 |
Work in progress | 5% Completed
|0% Completed
earth filling completed 80%
Abhinandh P T |
Date: 14/11/2024 |
Work in progress | 4% Completed
|0% Completed
earth filling and demolishing work under progress