Abhinandh P T
Date: 17/03/2025

Work in progress | 16% Completed

% |0% Completed

General Works – Earth filling is 95% complete, and storytelling wall work is 90% finished. Pond Renovation – Laterite step work is in progress. OAT foundation PCC completed overall all status -16% Financial Progress-14%

Abhinandh P T
Date: 05/03/2025

Work in progress | 11% Completed

% |0% Completed

General Works – Earth filling is 95% complete, and storytelling wall work is 50% finished. Pond Renovation – Laterite step work is in progress. overall all status -10% Financial Progress-0% open air theater- PCC ongoing

Abhinandh P T
Date: 18/02/2025

Work in progress | 10% Completed

% |0% Completed

General Works – Earth filling is 95% complete, and storytelling wall work is 50% finished. Pond Renovation – Laterite step work is in progress. overall all status -10% Financial Progress-0%

Attached images

img

Abhinandh P T
Date: 18/02/2025

Work in progress | 9% Completed

% |0% Completed

General Works – Earth filling is 95% complete, and storytelling wall work is 50% finished. Pond Renovation – Laterite step work is in progress. overall all status -10% Financial Progress-0%

Abhinandh P T
Date: 10/02/2025

Work in progress | 8% Completed

% |0% Completed

story telling wall laterite work completed

Abhinandh P T
Date: 07/02/2025

Work in progress | 8% Completed

% |0% Completed

story telling wall laterite work completed

Abhinandh P T
Date: 22/01/2025

Work in progress | 5% Completed

% |0% Completed

story telling wall work under progress

Abhinandh P T
Date: 03/01/2025

Work in progress | 5% Completed

% |0% Completed

earth filling completed 80%

Abhinandh P T
Date: 12/12/2024

Work in progress | 5% Completed

% |0% Completed

earth filling completed 80%

Abhinandh P T
Date: 14/11/2024

Work in progress | 4% Completed

% |0% Completed

earth filling and demolishing work under progress

Abhinandh P T
Date: 17/03/2025

Work in progress | 0% Completed

General Works – Earth filling is 95% complete, and storytelling wall work is 90% finished. Pond Renovation – Laterite step work is in progress. OAT foundation PCC completed overall all status -16% Financial Progress-14%

Abhinandh P T
Date: 05/03/2025

Work in progress | 0% Completed

General Works – Earth filling is 95% complete, and storytelling wall work is 50% finished. Pond Renovation – Laterite step work is in progress. overall all status -10% Financial Progress-0% open air theater- PCC ongoing

Abhinandh P T
Date: 18/02/2025

Work in progress | 0% Completed

General Works – Earth filling is 95% complete, and storytelling wall work is 50% finished. Pond Renovation – Laterite step work is in progress. overall all status -10% Financial Progress-0%

Attached images

img

Abhinandh P T
Date: 18/02/2025

Work in progress | 0% Completed

General Works – Earth filling is 95% complete, and storytelling wall work is 50% finished. Pond Renovation – Laterite step work is in progress. overall all status -10% Financial Progress-0%

Abhinandh P T
Date: 10/02/2025

Work in progress | 0% Completed

story telling wall laterite work completed

Abhinandh P T
Date: 07/02/2025

Work in progress | 0% Completed

story telling wall laterite work completed

Abhinandh P T
Date: 22/01/2025

Work in progress | 0% Completed

story telling wall work under progress

Abhinandh P T
Date: 03/01/2025

Work in progress | 0% Completed

earth filling completed 80%

Abhinandh P T
Date: 12/12/2024

Work in progress | 0% Completed

earth filling completed 80%

Abhinandh P T
Date: 14/11/2024

Work in progress | 0% Completed

earth filling and demolishing work under progress