| Abhinandh P T |
| Date: 25/09/2025 |
Work in progress | 25% Completed
|0% Completed
General Works – Earth filling is 95% complete, and the storytelling wall work is 90% finished. Truss work is in progress. Open Air Theater – Column concreting has been completed, plinth filling is done, and slab shuttering work is in progress. Pond Renovation – 70% of the laterite parapet wall around the pond has been completed, and 90% of the laterite steps have also been finished. Smithy Mandapam Renovation – The new truss work has been completed, MP tile work is finished, and electrical work is in progress.
| Abhinandh P T |
| Date: 09/09/2025 |
Work in progress | 21% Completed
|0% Completed
General Works – Earth filling is 95% complete, and the storytelling wall work is 90% finished. Open Air Theater – column concrete work completed . Pond Renovation – Laterite parapet wall work is in progress. Smithy Mandapam Renovation – Dismantling of MB tiles is finished, and dismantling of the roof truss completed . new truss work completed and MP tile work under progress
| Abhinandh P T |
| Date: 05/08/2025 |
Work in progress | 21% Completed
|0% Completed
General Works – Earth filling is 95% complete, and the storytelling wall work is 90% finished. Open Air Theater – column concrete work completed . Pond Renovation – Laterite parapet wall work is in progress. Smithy Mandapam Renovation – Dismantling of MB tiles is finished, and dismantling of the roof truss completed . new truss work completed and MP tile work under progress
| Abhinandh P T |
| Date: 18/07/2025 |
Work in progress | 21% Completed
|0% Completed
General Works – Earth filling is 95% complete, and the storytelling wall work is 90% finished. Open Air Theater – column concrete work completed . Pond Renovation – Laterite parapet wall work is in progress. Smithy Mandapam Renovation – Dismantling of MB tiles is finished, and dismantling of the roof truss completed . new truss work completed and MP tile work under progress
| Abhinandh P T |
| Date: 11/07/2025 |
Work in progress | 21% Completed
|0% Completed
General Works – Earth filling is 95% complete, and the storytelling wall work is 90% finished. Open Air Theater – column concrete work completed . Pond Renovation – Laterite parapet wall work is in progress. Smithy Mandapam Renovation – Dismantling of MB tiles is finished, and dismantling of the roof truss completed . new truss work completed and MP tile work under progress
| Abhinandh P T |
| Date: 23/06/2025 |
Work in progress | 21% Completed
|0% Completed
General Works – Earth filling is 95% complete, and the storytelling wall work is 90% finished. Open Air Theater – column concrete work completed . Pond Renovation – Laterite parapet wall work is in progress. Smithy Mandapam Renovation – Dismantling of MB tiles is finished, and dismantling of the roof truss completed . new truss work completed and MP tile work under progress
| Abhinandh P T |
| Date: 18/06/2025 |
Work in progress | 21% Completed
|0% Completed
General Works – Earth filling is 95% complete, and the storytelling wall work is 90% finished. Open Air Theater – column concrete work completed . Pond Renovation – Laterite parapet wall work is in progress. Smithy Mandapam Renovation – Dismantling of MB tiles is finished, and dismantling of the roof truss completed . new truss work completed and MP tile work under progress
| Abhinandh P T |
| Date: 09/06/2025 |
Work in progress | 21% Completed
|0% Completed
General Works – Earth filling is 95% complete, and the storytelling wall work is 90% finished. Open Air Theater – column concrete work completed . Pond Renovation – Laterite parapet wall work is in progress. Smithy Mandapam Renovation – Dismantling of MB tiles is finished, and dismantling of the roof truss completed . new truss work completed and MP tile work under progress
| Abhinandh P T |
| Date: 02/06/2025 |
Work in progress | 21% Completed
|0% Completed
Work in progress | 21% Completed | General Works – Earth filling is 95% complete, and the storytelling wall work is 90% finished. Open Air Theater – column concrete work completed . Pond Renovation – Laterite parapet wall work is in progress. Smithy Mandapam Renovation – Dismantling of MB tiles is finished, and dismantling of the roof truss completed . new truss work completed and MP tile work under progress
| Abhinandh P T |
| Date: 30/05/2025 |
Work in progress | 19% Completed
|0% Completed
Work in progress | 19% Completed | 19/05/2025 General Works– Earth filling is 95% complete, and the storytelling wall work is 90% finished. Open Air Theater – column concrete work completed . Pond Renovation – Laterite parapet wall work is in progress. Smithy Mandapam Renovation – Dismantling of MB tiles is finished, and dismantling of the roof truss completed . new truss work is under progress
| Abhinandh P T |
| Date: 19/05/2025 |
Work in progress | 19% Completed
|0% Completed
General Works– Earth filling is 95% complete, and the storytelling wall work is 90% finished. Open Air Theater – column concrete work completed . Pond Renovation – Laterite parapet wall work is in progress. Smithy Mandapam Renovation – Dismantling of MB tiles is finished, and dismantling of the roof truss completed . new truss work is under progress
| Abhinandh P T |
| Date: 06/05/2025 |
Work in progress | 18% Completed
|0% Completed
General Works– Earth filling is 95% complete, and the storytelling wall work is 90% finished. Open Air Theater – PB concrete work completed . Pond Renovation – Laterite parapet wall work is in progress. Smithy Mandapam Renovation – Dismantling of MB tiles is finished, and dismantling of the roof truss completed . new truss work is under progress
| Abhinandh P T |
| Date: 28/04/2025 |
Work in progress | 17% Completed
|0% Completed
General Works– Earth filling is 95% complete, and the storytelling wall work is 90% finished. Open Air Theater – PB reinforcement work is in progress. Pond Renovation – Laterite step work is in progress. Smithy Mandapam Renovation – Dismantling of MB tiles is finished, and dismantling of the roof truss completed
| Abhinandh P T |
| Date: 10/04/2025 |
Work in progress | 16% Completed
|0% Completed
General Works– Earth filling is 95% complete, and the storytelling wall work is 90% finished. Open Air Theater – Foundation reinforcement work is in progress. Pond Renovation – Laterite step work is in progress. Smrithy Mandapam Renovation – Dismantling of MB tiles is finished, and dismantling of the roof truss is in progress
| Abhinandh P T |
| Date: 01/04/2025 |
Work in progress | 16% Completed
|0% Completed
General Works– Earth filling is 95% complete, and the storytelling wall work is 90% finished. Open Air Theater – Foundation reinforcement work is in progress. Pond Renovation – Laterite step work is in progress. Smrithy Mandapam Renovation – Dismantling of MB tiles is finished, and dismantling of the roof truss is in progress
| Abhinandh P T |
| Date: 17/03/2025 |
Work in progress | 16% Completed
|0% Completed
General Works – Earth filling is 95% complete, and storytelling wall work is 90% finished. Pond Renovation – Laterite step work is in progress. OAT foundation PCC completed overall all status -16% Financial Progress-14%
| Abhinandh P T |
| Date: 05/03/2025 |
Work in progress | 11% Completed
|0% Completed
General Works – Earth filling is 95% complete, and storytelling wall work is 50% finished. Pond Renovation – Laterite step work is in progress. overall all status -10% Financial Progress-0% open air theater- PCC ongoing
| Abhinandh P T |
| Date: 18/02/2025 |
| Abhinandh P T |
| Date: 18/02/2025 |
Work in progress | 9% Completed
|0% Completed
General Works – Earth filling is 95% complete, and storytelling wall work is 50% finished. Pond Renovation – Laterite step work is in progress. overall all status -10% Financial Progress-0%
| Abhinandh P T |
| Date: 10/02/2025 |
Work in progress | 8% Completed
|0% Completed
story telling wall laterite work completed
| Abhinandh P T |
| Date: 07/02/2025 |
Work in progress | 8% Completed
|0% Completed
story telling wall laterite work completed
| Abhinandh P T |
| Date: 22/01/2025 |
Work in progress | 5% Completed
|0% Completed
story telling wall work under progress
| Abhinandh P T |
| Date: 03/01/2025 |
Work in progress | 5% Completed
|0% Completed
earth filling completed 80%
| Abhinandh P T |
| Date: 12/12/2024 |
Work in progress | 5% Completed
|0% Completed
earth filling completed 80%
| Abhinandh P T |
| Date: 14/11/2024 |
Work in progress | 4% Completed
|0% Completed
earth filling and demolishing work under progress