Project | UPGRADATION OF GOVT. ITI KANNUR ON PAR WITH INTERNATIONAL STANDARDS |
---|---|
Project Code | KNRKIIFB121647P1 |
Main Project | UPGRADATION OF GOVT. ITI KANNUR ON PAR WITH INTERNATIONAL STANDARDS |
Work Category | Funding Agency | KIIFB |
Client Department | KASE |
Description | Upgradation of Govt ITI to International standard by Providing Modern facilities in campus including International standard roads, pathways, gardens, lighting etc. proposed. Elegant entrance Gateways with pathways wherever indicated.Establishing an infrastructure capable enough to welcome International trainees and trainers through exchange programs.With the establishment of new infrastructure , the present intake capacity can be enhanced coupled with new and emerging trades which thereby enables more students to be employable in various skill segments. |
Status | On-going |
District | Kannur |
Executing Office | Office of GM1 |
TS Amount (Rs) | 40860000 |
TS Number | KASE-20/2016 |
Technical specification | |
Contractor | Shri. Shameer M A (Mob: 9447010007) |
Project Progress Status |
Project Progress Status |
Date of start of Package | 23/12/2016 |
---|---|
Scheduled date of Completion as per agreement | 05 Mar 2021 |
Expected date of Completion | 12/12/2022 |
TS Date | 15 Feb 2020 |
---|---|
Date Of Site Handover | 09 Sep 2020 |
# | Component Name | Component Amount | Updated Percentage | Updated Amount in Lakhs |
---|---|---|---|---|
1 | CIVIL | 28599190.09 | 100 % | 174.46 L |
2 | MECHANICAL | 558040.45 | 100 % | 0 |
3 | ELECTRICAL | 4936707.43 | 100 % | 0 |
VIMAL T T |
Date: 28/10/2024 |
Work has been completed | 100% Completed
Project finished..
VIMAL T T |
Date: 28/10/2024 |
Work has been completed | 100% Completed
Project finished..