KIIFB- CONSTRUCTION OF REGULATOR ACROSS CHITTUR PUZHA AT VADAKARAPALLY PALATHULLI IN PERUVEMBU GRAMA PANCHAYATH IN PALAKKAD DISTRICT.

Project KIIFB- CONSTRUCTION OF REGULATOR ACROSS CHITTUR PUZHA AT VADAKARAPALLY PALATHULLI IN PERUVEMBU GRAMA PANCHAYATH IN PALAKKAD DISTRICT.
Project Code PKDKIIFB07205
Work Category RCB(Regulator Cum Bridge)
Funding Agency KIIFB
Client Department Water Resource Department
Description This Project is to construct a Regulator across Chittur Puzha at Vadakarapally Palathulli in Peruvembu Grama Panchayt in Palakkad District. The main aim of the project is to keep up the sub soil water table above and there by enriching the wells in the nearby locality. The realization of this regulator will strengthen the ayacuts of Chittur Puzha Project. An assured quantity of drinking water can be supplied to the Villages on both banks of the river. Also private pumping can be allowed which will increase the cultivation of cash crops. By the construction of the regulator, the reservoir thus created will help in fish farming
Status Physically Completed
District Palakkad
Executing Office Office of GM2
AS Amount (Rs) 198400000
AS Number WRD022-09/APR-6/2020/KIIFB
TS Amount (Rs) 198400000
TS Number KIIDC/315/KIIFB-RCB-VDKRPLY/2018
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
1 KIIFB- CONSTRUCTION OF REGULATOR ACROSS CHITTUR PUZHA AT VADAKARAPALLY PALATHULLI IN PERUVEMBU GRAMA PANCHAYATH IN PALAKKAD DISTRICT. Office of GM2

Overall Project Status

Status Date Overall Project Status Project Officer Contact
31 Jul 2023 Civil works, mechanical works, electrical works 100% completed. Nithin J B
15 May 2023 Civil works, mechanical works, electrical works 100% completed. Nithin J B
09 May 2023 Civil works, mechanical works, electrical works 100% completed. Nithin J B
25 Sep 2022 Civil 95% (30m retaining wall yet to complete) Mechanical 85% (6 vent secondary and erection yet to complete). Nithin J B

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 28/07/2020
Scheduled date of Completion of the Project 12 Jul 2022
Expected date of Completion 12/11/2022

Processing Dates

AS Date 28 Jul 2020
TS Date 24 Aug 2020

Other details