Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

KIIFB Project- Beatification 0f Canals in Alappuzha-Modernizing water Transport in Alappuzha Town Canals and Cleaning of Kappithode Phase II

Project KIIFB Project- Beatification 0f Canals in Alappuzha-Modernizing water Transport in Alappuzha Town Canals and Cleaning of Kappithode Phase II
Project Code ALPKIIFB012196P1
Main Project KIIFB Project- Beautification of Canals in Alappuzha-Modernising water Transport in Alappuzha Town Canals and Cleaning of Kappithode Phase II
Work Category
Funding Agency KIIFB
Client Department Water Resource Department
Description KIIFB Project- Beatification 0f Canals in Alappuzha-Modernizing water Transport in Alappuzha Town Canals and Cleaning of Kappithode Phase II
Status On-going
District Alappuzha
Executing Office Office of GM1
TS Amount (Rs) 481566195
TS Number KIIDC/73/Alappuzha Canals-Ph-II/2021
Technical specification
Contractor M/s TBAS Construction (Mob: 8547119550)

No project review have been added to this project

Project Progress Status

Project Progress Status

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion Date is not specified

Processing Dates

TS Date 16 Feb 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Component Progress Summary

# Component Name Component Amount Updated Percentage Updated Amount in Lakhs
1 Improvements to sub canals and balance protection works to the main canals in alappuzha 234384894.6 60 % 210.95 L
2 demolition and construction of twin box culvert (3no.s) in A.S canal and 1 n. single box cul 26938112.07 10 % 0
3 Improvements of kappithode in ambalappuzha L.A constituency at ambalappuzha 86415849.52 90 % 129.62 L
4 Improvements of A.S canal (balance portion) and madayanthodu 61824790.25 75 % 86.55 L

Project Status Updations See All Status Updations

JESNA BEEGUM S
Date: 23/09/2024

Work in progress | 52% Completed

The work site handed over to PMC (RITES) by DGM on 14th august 2023. Appendix A: IMPROVEMENT TO SUB CANALS AND BALANCE PROTECTION WORKS TO THE MAIN` CANALS IN ALAPPUZHA TOWN -Side protection works including dismantling, reconstruction in main canals almost completed. In case of sub canals works in Pazhaveedu, Thirumala, A.N Purarn, Kaithavana , Mullackal , Kalarcode, Palace wards were completed. Kalarcode and palace ward final levels to be completed..Works in Nehrutrophy, and MO wards are in progress. Final levels being taken at SDV Chira thodu and Malikachira thodu.Initials levels were reported. Silt trap at Ambalpuzha –Gandhivilasam thodu, Vadai canal and west junction canal approaches are completed. Protection work at Chungam, Vadaikanal completed. Appendix B: Demollition and construction of twin box culvert(3 N0s) in AS canal and 1 no single box culvert in Madayanthodu :-At Vellapally bridge, construction of bund for box culvert, as per the request of local MLA started. At Arattuvazhi old bridge dismantled, Raft foundation work completed. Old Poppy bridge dismantled. Due to heavy rain constructed ring bund fully dismantled. Work can commence only after monsoon. Appendix C: IMPROVEMENTS OF KAPPITHODE IN AMBALAPUZHA LA CONSTITUENCY AT AMBALAPUZHA SOUTH AND NORTH PANCHAYATH:. Final levels approved. All work except at hindrance portion completed. Culvert at chainage 4930,6250, 6360, 9660,8580 and 4240 were completed , balance 2 nos to be done only after hindrance cleared. Appendix D: IMPROVEMENTS OF AS CANAL(BALANCE PORTION) AND MADAYANTHODU - At AS canal east side of protection wall at d/s of Kommadi bridge completed. Masonry protection work at LHS (west side), upstream of Pathirapally bridge progressing. Pile and slab protection work at road side(East) progressing. Desilting,Laying coir geo textile and protection work of Madayanthodu almost completed.

Attached images

img img img

JESNA BEEGUM S
Date: 23/09/2024

Work in progress | 52% Completed

The work site handed over to PMC (RITES) by DGM on 14th august 2023. Appendix A: IMPROVEMENT TO SUB CANALS AND BALANCE PROTECTION WORKS TO THE MAIN` CANALS IN ALAPPUZHA TOWN -Side protection works including dismantling, reconstruction in main canals almost completed. In case of sub canals works in Pazhaveedu, Thirumala, A.N Purarn, Kaithavana , Mullackal , Kalarcode, Palace wards were completed. Kalarcode and palace ward final levels to be completed..Works in Nehrutrophy, and MO wards are in progress. Final levels being taken at SDV Chira thodu and Malikachira thodu.Initials levels were reported. Silt trap at Ambalpuzha –Gandhivilasam thodu, Vadai canal and west junction canal approaches are completed. Protection work at Chungam, Vadaikanal completed. Appendix B: Demollition and construction of twin box culvert(3 N0s) in AS canal and 1 no single box culvert in Madayanthodu :-At Vellapally bridge, construction of bund for box culvert, as per the request of local MLA started. At Arattuvazhi old bridge dismantled, Raft foundation work completed. Old Poppy bridge dismantled. Due to heavy rain constructed ring bund fully dismantled. Work can commence only after monsoon. Appendix C: IMPROVEMENTS OF KAPPITHODE IN AMBALAPUZHA LA CONSTITUENCY AT AMBALAPUZHA SOUTH AND NORTH PANCHAYATH:. Final levels approved. All work except at hindrance portion completed. Culvert at chainage 4930,6250, 6360, 9660,8580 and 4240 were completed , balance 2 nos to be done only after hindrance cleared. Appendix D: IMPROVEMENTS OF AS CANAL(BALANCE PORTION) AND MADAYANTHODU - At AS canal east side of protection wall at d/s of Kommadi bridge completed. Masonry protection work at LHS (west side), upstream of Pathirapally bridge progressing. Pile and slab protection work at road side(East) progressing. Desilting,Laying coir geo textile and protection work of Madayanthodu almost completed.

Attached images

img img img