KIIFB Project- Beatification 0f Canals in Alappuzha-Modernizing water Transport in Alappuzha Town Canals and Cleaning of Kappithode Phase II

Project KIIFB Project- Beatification 0f Canals in Alappuzha-Modernizing water Transport in Alappuzha Town Canals and Cleaning of Kappithode Phase II
Project Code ALPKIIFB012196P1
Main Project KIIFB Project- Beautification of Canals in Alappuzha-Modernising water Transport in Alappuzha Town Canals and Cleaning of Kappithode Phase II
Work Category
Funding Agency KIIFB
Client Department Water Resource Department
Description KIIFB Project- Beatification 0f Canals in Alappuzha-Modernizing water Transport in Alappuzha Town Canals and Cleaning of Kappithode Phase II
Status On-going
District Alappuzha
Executing Office Office of GM1
TS Amount (Rs) 481566195
TS Number KIIDC/73/Alappuzha Canals-Ph-II/2021
Technical specification
Contractor M/s TBAS Construction (Mob: 8547119550)

No project review have been added to this project

Project Progress Status

Project Progress Status

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion Date is not specified

Processing Dates

TS Date 16 Feb 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Component Progress Summary

# Component Name Component Amount Updated Percentage Updated Amount in Lakhs
1 Improvements to sub canals and balance protection works to the main canals in alappuzha 234384894.6 65 % 210.95 L
2 demolition and construction of twin box culvert (3no.s) in A.S canal and 1 n. single box cul 26938112.07 50 % 0
3 Improvements of kappithode in ambalappuzha L.A constituency at ambalappuzha 86415849.52 95 % 129.62 L
4 Improvements of A.S canal (balance portion) and madayanthodu 61824790.25 80 % 86.55 L

Project Status Updations See All Status Updations

Silppa R
Date: 25/03/2025

Work in progress | 80% Completed

Appendix A: IMPROVEMENT TO SUB CANALS AND BALANCE PROTECTION WORKS TO THE MAIN` CANALS IN ALAPPUZHA TOWN -Side protection works including dismantling, reconstruction in main canals and sub-canals were completed. Appendix B: For Vellapally box culvert-88% of work completed, wing wall construction is under progress. For Arattuvazhi Box culvert - 45% of work completed, top slab concrete is complete, DR & RR work of wing wall is under progress. For Poppy Box culvert - 31% of work completed ,Bottom raft foundation & 2nd lift wall concrete is complete. Appendix C: IMPROVEMENTS OF KAPPITHODE IN AMBALAPUZHA LA CONSTITUENCY AT AMBALAPUZHA SOUTH AND NORTH PANCHAYATH: All work except at hindrance portion completed. Culvert at chainage 4930,6250, 6360, 9660,8580 and 4240 were completed , balance 2 nos to be done only after hindrance cleared. The work on the screen wall has been completed, and the work of covering it with checker plate is in progress(77%). .Appendix D: IMPROVEMENTS OF AS CANAL(BALANCE PORTION) AND MADAYANTHODU - At AS canal east side of protection wall at d/s of Kommadi bridge completed. Masonry protection work at LHS (west side), upstream of Pathirapally bridge completed . Pile and slab side protection protection work at road side(East) ,Desilting, Laying coir geo textile and protection work of Madayanthodu are completed. At Arimbu thode side protection work is under progress (53%) .

Attached images

img

Silppa R
Date: 25/03/2025

Work in progress | 80% Completed

Appendix A: IMPROVEMENT TO SUB CANALS AND BALANCE PROTECTION WORKS TO THE MAIN` CANALS IN ALAPPUZHA TOWN -Side protection works including dismantling, reconstruction in main canals and sub-canals were completed. Appendix B: For Vellapally box culvert-88% of work completed, wing wall construction is under progress. For Arattuvazhi Box culvert - 45% of work completed, top slab concrete is complete, DR & RR work of wing wall is under progress. For Poppy Box culvert - 31% of work completed ,Bottom raft foundation & 2nd lift wall concrete is complete. Appendix C: IMPROVEMENTS OF KAPPITHODE IN AMBALAPUZHA LA CONSTITUENCY AT AMBALAPUZHA SOUTH AND NORTH PANCHAYATH: All work except at hindrance portion completed. Culvert at chainage 4930,6250, 6360, 9660,8580 and 4240 were completed , balance 2 nos to be done only after hindrance cleared. The work on the screen wall has been completed, and the work of covering it with checker plate is in progress(77%). .Appendix D: IMPROVEMENTS OF AS CANAL(BALANCE PORTION) AND MADAYANTHODU - At AS canal east side of protection wall at d/s of Kommadi bridge completed. Masonry protection work at LHS (west side), upstream of Pathirapally bridge completed . Pile and slab side protection protection work at road side(East) ,Desilting, Laying coir geo textile and protection work of Madayanthodu are completed. At Arimbu thode side protection work is under progress (53%) .

Attached images

img