Project | KIIFB Project- Beatification 0f Canals in Alappuzha-Modernizing water Transport in Alappuzha Town Canals and Cleaning of Kappithode Phase II |
---|---|
Project Code | ALPKIIFB012196P1 |
Main Project | KIIFB Project- Beautification of Canals in Alappuzha-Modernising water Transport in Alappuzha Town Canals and Cleaning of Kappithode Phase II |
Work Category | Funding Agency | KIIFB |
Client Department | Water Resource Department |
Description | KIIFB Project- Beatification 0f Canals in Alappuzha-Modernizing water Transport in Alappuzha Town Canals and Cleaning of Kappithode Phase II |
Status | On-going |
District | Alappuzha |
Executing Office | Office of GM1 |
TS Amount (Rs) | 481566195 |
TS Number | KIIDC/73/Alappuzha Canals-Ph-II/2021 |
Technical specification | |
Contractor | M/s TBAS Construction (Mob: 8547119550) |
Project Progress Status |
Project Progress Status |
Date of start of Package | Date is not specified |
---|---|
Scheduled date of Completion as per agreement | Date is not specified |
Expected date of Completion | Date is not specified |
TS Date | 16 Feb 2021 |
---|
# | Component Name | Component Amount | Updated Percentage | Updated Amount in Lakhs |
---|---|---|---|---|
1 | Improvements to sub canals and balance protection works to the main canals in alappuzha | 234384894.6 | 65 % | 210.95 L |
2 | demolition and construction of twin box culvert (3no.s) in A.S canal and 1 n. single box cul | 26938112.07 | 50 % | 0 |
3 | Improvements of kappithode in ambalappuzha L.A constituency at ambalappuzha | 86415849.52 | 95 % | 129.62 L |
4 | Improvements of A.S canal (balance portion) and madayanthodu | 61824790.25 | 80 % | 86.55 L |
Silppa R |
Date: 25/03/2025 |
Work in progress | 80% Completed
Appendix A: IMPROVEMENT TO SUB CANALS AND BALANCE PROTECTION WORKS TO THE MAIN` CANALS IN ALAPPUZHA TOWN -Side protection works including dismantling, reconstruction in main canals and sub-canals were completed. Appendix B: For Vellapally box culvert-88% of work completed, wing wall construction is under progress. For Arattuvazhi Box culvert - 45% of work completed, top slab concrete is complete, DR & RR work of wing wall is under progress. For Poppy Box culvert - 31% of work completed ,Bottom raft foundation & 2nd lift wall concrete is complete. Appendix C: IMPROVEMENTS OF KAPPITHODE IN AMBALAPUZHA LA CONSTITUENCY AT AMBALAPUZHA SOUTH AND NORTH PANCHAYATH: All work except at hindrance portion completed. Culvert at chainage 4930,6250, 6360, 9660,8580 and 4240 were completed , balance 2 nos to be done only after hindrance cleared. The work on the screen wall has been completed, and the work of covering it with checker plate is in progress(77%). .Appendix D: IMPROVEMENTS OF AS CANAL(BALANCE PORTION) AND MADAYANTHODU - At AS canal east side of protection wall at d/s of Kommadi bridge completed. Masonry protection work at LHS (west side), upstream of Pathirapally bridge completed . Pile and slab side protection protection work at road side(East) ,Desilting, Laying coir geo textile and protection work of Madayanthodu are completed. At Arimbu thode side protection work is under progress (53%) .
Attached images
Silppa R |
Date: 25/03/2025 |
Work in progress | 80% Completed
Appendix A: IMPROVEMENT TO SUB CANALS AND BALANCE PROTECTION WORKS TO THE MAIN` CANALS IN ALAPPUZHA TOWN -Side protection works including dismantling, reconstruction in main canals and sub-canals were completed. Appendix B: For Vellapally box culvert-88% of work completed, wing wall construction is under progress. For Arattuvazhi Box culvert - 45% of work completed, top slab concrete is complete, DR & RR work of wing wall is under progress. For Poppy Box culvert - 31% of work completed ,Bottom raft foundation & 2nd lift wall concrete is complete. Appendix C: IMPROVEMENTS OF KAPPITHODE IN AMBALAPUZHA LA CONSTITUENCY AT AMBALAPUZHA SOUTH AND NORTH PANCHAYATH: All work except at hindrance portion completed. Culvert at chainage 4930,6250, 6360, 9660,8580 and 4240 were completed , balance 2 nos to be done only after hindrance cleared. The work on the screen wall has been completed, and the work of covering it with checker plate is in progress(77%). .Appendix D: IMPROVEMENTS OF AS CANAL(BALANCE PORTION) AND MADAYANTHODU - At AS canal east side of protection wall at d/s of Kommadi bridge completed. Masonry protection work at LHS (west side), upstream of Pathirapally bridge completed . Pile and slab side protection protection work at road side(East) ,Desilting, Laying coir geo textile and protection work of Madayanthodu are completed. At Arimbu thode side protection work is under progress (53%) .
Attached images