CONSTRUCTION OF REGULATOR CUM BRIDGE ACROSS THOOTHAPUZHA AT KEEZHMURIKADAVU,MOOTHIKKAYAM IN MOORKKANAD PANCHAYATH,MALAPPURAM DISTRICT
Project
CONSTRUCTION OF REGULATOR CUM BRIDGE ACROSS THOOTHAPUZHA AT KEEZHMURIKADAVU,MOOTHIKKAYAM IN MOORKKANAD PANCHAYATH,MALAPPURAM DISTRICT
Project Code
MLPKIIFB09197P1
Main Project
CONSTRUCTION OF REGULATOR CUM BRIDGE ACROSS THOOTHAPUZHA AT KEEZHMURIKADAVU,MOOTHIKKAYAM IN MOORKKANAD PANCHAYATH,MALAPPURAM DISTRICT.
Work Category
Funding Agency
KIIFB
Client Department
Water Resource Department
Description
The Regulator cum bridge stores water which feeds several water supply system in
nearby loacality.This project is proposed with a bridge having two way traffic connecting
Palakkad and Malappuram district.it provides water for an effective ayacut area of 3950
Ha
Status
On-going
District
Malappuram
Executing Office
Office of GM1
TS Amount (Rs)
669400000
TS Number
292/TS/KIIDC/2019-20
Technical specification
Contractor
Paulose George Construction Company Pvt Ltd (Mob: 9846438199)
No project review have been added to this project
Project Progress Status
Project Progress Status
Duration & Sanction dates
Date of start of Package
07/09/2019
Scheduled date of Completion as per agreement
26 Mar 2022
Expected date of Completion
30/06/2023
Processing Dates
TS Date
22 Nov 2019
Date Of Site Handover
26 Sep 2020
Other details
Project Schedule
View
Project Components
View
Project Officers
View
Component Progress Summary
#
Component Name
Component Amount
Updated Percentage
Updated Amount in Lakhs
1
regulator cum bridge
240266044.74
82 %
0
2
side protect
222622367.99
67 %
890.49 L
3
lead regulator and side protection
25916935.12
40 %
0
4
Approach road and bank connection
37412871.56
0 %
0
5
Approach road
2685628.13
0 %
0
6
electrical (genrator) building
2795324.16
68 %
0
7
electrical work
3326709.17
0 %
0
8
mechanical
62564273.4
25 %
106.36 L
Meenu .E. S
Date: 22/07/2024
Work in progress | 88% Completed
1.all civil work completed except Approach road and electrical work .
Attached images
Meenu .E. S
Date: 22/07/2024
Work in progress | 88% Completed
1.all civil work completed except Approach road and electrical work .