CONSTRUCTION OF REGULATOR CUM BRIDGE ACROSS THOOTHAPUZHA AT KEEZHMURIKADAVU,MOOTHIKKAYAM IN MOORKKANAD PANCHAYATH,MALAPPURAM DISTRICT

Project CONSTRUCTION OF REGULATOR CUM BRIDGE ACROSS THOOTHAPUZHA AT KEEZHMURIKADAVU,MOOTHIKKAYAM IN MOORKKANAD PANCHAYATH,MALAPPURAM DISTRICT
Project Code MLPKIIFB09197P1
Main Project CONSTRUCTION OF REGULATOR CUM BRIDGE ACROSS THOOTHAPUZHA AT KEEZHMURIKADAVU,MOOTHIKKAYAM IN MOORKKANAD PANCHAYATH,MALAPPURAM DISTRICT.
Work Category
Funding Agency KIIFB
Client Department Water Resource Department
Description The Regulator cum bridge stores water which feeds several water supply system in nearby loacality.This project is proposed with a bridge having two way traffic connecting Palakkad and Malappuram district.it provides water for an effective ayacut area of 3950 Ha
Status On-going
District Malappuram
Executing Office Office of GM1
TS Amount (Rs) 669400000
TS Number 292/TS/KIIDC/2019-20
Technical specification
Contractor Paulose George Construction Company Pvt Ltd (Mob: 9846438199)

No project review have been added to this project

Project Progress Status

Project Progress Status

Duration & Sanction dates

Date of start of Package 07/09/2019
Scheduled date of Completion as per agreement 26 Mar 2022
Expected date of Completion 30/06/2023

Processing Dates

TS Date 22 Nov 2019
Date Of Site Handover 26 Sep 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Component Progress Summary

# Component Name Component Amount Updated Percentage Updated Amount in Lakhs
1 regulator cum bridge 240266044.74 82 % 0
2 side protect 222622367.99 67 % 890.49 L
3 lead regulator and side protection 25916935.12 40 % 0
4 Approach road and bank connection 37412871.56 0 % 0
5 Approach road 2685628.13 0 % 0
6 electrical (genrator) building 2795324.16 68 % 0
7 electrical work 3326709.17 0 % 0
8 mechanical 62564273.4 25 % 106.36 L

Project Status Updations See All Status Updations

Meenu .E. S
Date: 22/07/2024

Work in progress | 88% Completed

1.all civil work completed except Approach road and electrical work .

Attached images

img img img

Meenu .E. S
Date: 22/07/2024

Work in progress | 88% Completed

1.all civil work completed except Approach road and electrical work .

Attached images

img img img