Project | Construction of Regulator Cum Bridge at Kankakkadavu across Bharathapuzha in Kuttipuram Panchayath, Malappuram District |
---|---|
Project Code | MLPKIIFB032287P1 |
Main Project | Construction of Regulator Cum Bridge at Kankakkadavu across Bharathapuzha in Kuttipuram Panchayath, Malappuram District |
Work Category | Funding Agency | KIIFB |
Client Department | Water Resource Department |
Description | Construction of Regulator Cum Bridge at Kankakkadavu across Bharathapuzha in Kuttipuram Panchayath, Malappuram District |
Status | On-going |
District | Malappuram |
Executing Office | Office of GM1 |
TS Amount (Rs) | 1198780000 |
TS Number | KIIDC/91/2022-PE4 |
Technical specification | |
Contractor | Paulose George Construction Company Pvt Ltd (Mob: 9846438199) |
Project Progress Status |
Project Progress Status |
Date of start of Package | Date is not specified |
---|---|
Scheduled date of Completion as per agreement | Date is not specified |
Expected date of Completion | Date is not specified |
TS Date | 27 May 2022 |
---|
# | Component Name | Component Amount | Updated Percentage | Updated Amount in Lakhs |
---|---|---|---|---|
1 | Regulator | 556073032.4 | 80 % | 0 |
2 | Side protection works | 86792734.11 | 55 % | 0 |
3 | Deck slab | 68713993.89 | 85 % | 0 |
4 | Approach road | 128600745.92 | 0 % | 0 |
5 | Electrical works | 10402437 | 0 % | 0 |
6 | Mechanical works | 176686194.08 | 83 % | 0 |
Rahees P |
Date: 21/03/2025 |
Work in progress | 82% Completed
Retaing wall work ongoing Apron work completed Gabion and toe wall work progressing Land aqusition meeting conductedforadvance d possession .
Rahees P |
Date: 21/03/2025 |
Work in progress | 82% Completed
Retaing wall work ongoing Apron work completed Gabion and toe wall work progressing Land aqusition meeting conductedforadvance d possession .