PANCHALIMEDU TOURISM PROJECT PHASE II AT PERUVANTHANAM VILLAGE, PEERUMEDU TALUK, IDUKKI DISTRICT
Project
PANCHALIMEDU TOURISM PROJECT PHASE II AT PERUVANTHANAM VILLAGE, PEERUMEDU TALUK, IDUKKI DISTRICT
Project Code
IDKTDK091934P1
Main Project
PANCHALIMEDU TOURISM PROJECT PHASE II AT PERUVANTHANAM VILLAGE, PEERUMEDU TALUK, IDUKKI DISTRICT
Work Category
Funding Agency
TDK
Client Department
Tourism Department
Description
The main aim of this projcts are renovation of Panchalikulam and to protect the natural
resources, develop the basic infrastructures facilities and economic development. This
project can Improve the quality of life in local community by attracting new tourism
related businesses.
Status
On-going
District
Idukki
Executing Office
Office of GM1
TS Amount (Rs)
30000000
TS Number
Order No.KIIDC/537/TSM/Panchalimedu-Idukki/2020
Technical specification
Contractor
Easy Infra (Mob: 9745285555)
No project review have been added to this project
Project Progress Status
Project Progress Status
Duration & Sanction dates
Date of start of Package
16/09/2019
Scheduled date of Completion as per agreement
31 Dec 2021
Expected date of Completion
31/03/2023
Processing Dates
TS Date
10 Jul 2020
Date Of Site Handover
01 Jan 2021
Other details
Project Schedule
View
Project Components
View
Project Officers
View
Component Progress Summary
#
Component Name
Component Amount
Updated Percentage
Updated Amount in Lakhs
1
Renovation of Panchalikulam
3981768.37
98 %
19.91 L
2
Construction of Pathway
3888259.54
85 %
19.44 L
3
Proposed Check Dam
7187475.44
80 %
17.25 L
4
Construction of Parking
3334479.48
0 %
0
5
Proposed Lighting System
2007817.25
60 %
0
6
Sitting Benches
363880.44
0 %
0
7
Landscaping
646689.3
60 %
0
8
Boat Jetty
545826.55
0 %
0
9
Burma Bridge
1236730.64
0 %
0
10
Rope Cycling
1206513.76
0 %
0
Teenu Augustine
Date: 25/07/2024
Work in progress | 90% Completed
work stopped due to pending part bill from tourism department..
Attached images
Teenu Augustine
Date: 25/07/2024
Work in progress | 90% Completed
work stopped due to pending part bill from tourism department..