CONSTRUCTION OF Groyne at Arattupuzha in Alappuzha dst..

Project CONSTRUCTION OF Groyne at Arattupuzha in Alappuzha dst..
Project Code ALPKIIFB071918P1
Main Project CONSTRUCTION OF Groyne at Arattupuzha in Alappuzha dst..
Work Category
Funding Agency KIIFB
Client Department Water Resource Department
Description CONSTRUCTION OF 21 number Groynes and 40 m Sea wall in 1.2 kms length of seacoast at Arattupuzha in Haripad LA
Status On-going
District Alappuzha
Executing Office Office of GM1
TS Amount (Rs) 227900000
TS Number 254/KIIDC/KIIFB/GROYNE/ARATTUPUZHA/2017
Technical specification
Contractor M/S Ramalingam Construction Company Pvt.Ltd & Dharti Dredging and Infrastructure Ltd. (Mob: 8277366889)

No project review have been added to this project

Project Progress Status

Project Progress Status

Duration & Sanction dates

Date of start of Package 12/07/2019
Scheduled date of Completion as per agreement 29 Jan 2022
Expected date of Completion 15/02/2023

Processing Dates

TS Date 02 Jul 2019
Date Of Site Handover 30 Jul 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Component Progress Summary

# Component Name Component Amount Updated Percentage Updated Amount in Lakhs
1 Dismantling of stones 213255.9 98 % 1.81 L
2 Earthwork excavation 696626.23 0 % 0
3 Supplying and laying of Boulders 119695545 90 % 526.66 L
4 Casting of tetrapods 114433000 100 % 0
5 Laying of tetrapods 14997940 75 % 65.99 L
6 Laying of geomat 12294228 0 % 0

Project Status Updations See All Status Updations

M A Faseela Nasar
Date: 26/08/2024

Work in progress | 91% Completed

Out of 21 groynes. 18 numbers are completed and balance 3 numbers in progress. sea wall has to be done also.

M A Faseela Nasar
Date: 26/08/2024

Work in progress | 91% Completed

Out of 21 groynes. 18 numbers are completed and balance 3 numbers in progress. sea wall has to be done also.