ADDITIONAL WORK AT ECOLODGE CONSTRUCTED AT PEERUMEDU (CONSTRUCTION OF PARKING YARD, COMPOUND FENCING, SERVICE BLOCK, AMBIENT LIGHTING AND MODULAR KITCHEN AT ECOLODGE PEERUMEDU)

Project ADDITIONAL WORK AT ECOLODGE CONSTRUCTED AT PEERUMEDU (CONSTRUCTION OF PARKING YARD, COMPOUND FENCING, SERVICE BLOCK, AMBIENT LIGHTING AND MODULAR KITCHEN AT ECOLODGE PEERUMEDU)
Project Code IDKTDK012189P1
Main Project ADDITIONAL WORK AT ECOLODGE CONSTRUCTED AT PEERUMEDU (CONSTRUCTION OF PARKING YARD, COMPOUND FENCING, SERVICE BLOCK, AMBIENT LIGHTING AND MODULAR KITCHEN AT ECOLODGE PEERUMEDU)
Work Category
Funding Agency TDK
Client Department Tourism Department
Description ADDITIONAL WORK AT ECOLODGE CONSTRUCTED AT PEERUMEDU (CONSTRUCTION OF PARKING YARD, COMPOUND FENCING, SERVICE BLOCK, AMBIENT LIGHTING AND MODULAR KITCHEN AT ECOLODGE PEERUMEDU)
Status
District Idukki
Executing Office Office of GM1
TS Amount (Rs) 9750000
TS Number KIIDC/207/2021
Technical specification
Contractor Outlook communications pvt Ltd (Mob: 9388859571)

No project review have been added to this project

Project Progress Status

Project Progress Status

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion Date is not specified

Processing Dates

TS Date 18 Jun 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Component Progress Summary

# Component Name Component Amount Updated Percentage Updated Amount in Lakhs
1 Fencing 2619887.6 100 % 13.1 L
2 Service Block 1763459.85 100 % 15.87 L
3 Security Cabin 145829.72 100 % 1.31 L
4 EPABX Installation 124550 100 % 0
5 Electrical Works 1460894 100 % 0
6 Diesel Generator 400000 100 % 3.6 L
7 Deep Freezer 38000 0 % 0
8 Refrigerator 70000 0 % 0
9 Microwave Oven 20000 0 % 0
10 Modular Kitchen 1208900 100 % 10.88 L
11 Steel Almirah 64000 0 % 0
12 Generator Room 103236.85 100 % 0.52 L
13 Civil Work for Lamp Post 8923.96 0 % 0

Project Status Updations See All Status Updations

Teenu Augustine
Date: 04/12/2023

Work has been completed | 100% Completed

all works completed.

Attached images

img img img img

Teenu Augustine
Date: 04/12/2023

Work has been completed | 100% Completed

all works completed.

Attached images

img img img img