Construction of Regulator Cum Bridge across Ummenchira River at Chekkupalam in Pinarayi grama Panchayath in Kannur District

Project Construction of Regulator Cum Bridge across Ummenchira River at Chekkupalam in Pinarayi grama Panchayath in Kannur District
Project Code KNRKIIFB092190P1
Main Project Construction of Regulator Cum Bridge across Ummenchira River at Chekkupalam in Pinarayi grama Panchayath in Kannur District
Work Category
Funding Agency KIIFB
Client Department Water Resource Department
Description Construction of Regulator Cum Bridge across Ummenchira River at Chekkupalam in Pinarayi grama Panchayath in Kannur District
Status On-going
District Kannur
Executing Office Office of GM1
TS Amount (Rs) 354173800
TS Number KIIDC/419/2021-PE4
Technical specification
Contractor Paulose George Construction Company Pvt Ltd (Mob: 9846438199)

No project review have been added to this project

Project Progress Status

Project Progress Status

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement 13 Nov 2023
Expected date of Completion 13/11/2023

Processing Dates

TS Date 27 Nov 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Component Progress Summary

# Component Name Component Amount Updated Percentage Updated Amount in Lakhs
1 Ring bund 5998282.46 99 % 0
2 Foundation and Apron 92842530.76 100 % 0
3 Abutment, pier and road slab 36618826.65 95 % 29.3 L
4 Generator room 2556813.47 90 % 0
5 Protection Bund 98825477.35 80 % 49.41 L
6 Mechanical Work 19629424.53 90 % 0

Project Status Updations See All Status Updations

Vishnu R
Date: 20/03/2025

Work in progress | 98% Completed

 Right Bank & Left Bank Steel Crash Barrier D/S Side 185 M Need to Be Done.  Paver Block, Need to Be Done for approach road.  Park Reconstruction Work.  Natural Protection Need to Be Done. .

Attached images

img

Vishnu R
Date: 20/03/2025

Work in progress | 98% Completed

 Right Bank & Left Bank Steel Crash Barrier D/S Side 185 M Need to Be Done.  Paver Block, Need to Be Done for approach road.  Park Reconstruction Work.  Natural Protection Need to Be Done. .

Attached images