Project | KARAPUZHA PHASE III - CONSTRUCTION OF VIEWING TOWER, BAMBOO PAVILIONS, BRIDGE IN WAYANAD DISTRICT |
---|---|
Project Code | WYDTDK031731P1 |
Main Project | KARAPUZHA PHASE III - CONSTRUCTION OF VIEWING TOWER, BAMBOO PAVILIONS, BRIDGE IN WAYANAD DISTRICT |
Work Category | Funding Agency | TDK |
Client Department | Tourism Department |
Description | Karapuzha dam is located in the Wayanad District; the dam's reservoir with partially submerged hills and lush green islands. The project aims to develop the Karapuzha dam and surroundings into major tourist destination. |
Status | On-going |
District | Wayanad |
Executing Office | Office of GM1 |
TS Amount (Rs) | 7250000 |
TS Number | Order No.KIIDC/222/2017 |
Technical specification |
Project Progress Status |
Project Progress Status |
Date of start of Package | 25/03/2017 |
---|---|
Scheduled date of Completion as per agreement | 29 Oct 2018 |
Expected date of Completion | Date is not specified |
TS Date | 20 Oct 2017 |
---|---|
Date Of Site Handover | 29 Dec 2017 |