Project | SETTING-UP OF STATE INSTITUTE OF HOTEL MANAGEMENT (SIHM) AT PALA, KOTTAYAM – CONSTRUCTION OF ACADEMIC BLOCK |
---|---|
Project Code | KTMTDK021439P1 |
Main Project | SETTING-UP OF STATE INSTITUTE OF HOTEL MANAGEMENT (SIHM) AT PALA, KOTTAYAM – CONSTRUCTION OF ACADEMIC BLOCK |
Work Category | Funding Agency | TDK |
Client Department | Tourism Department |
Description | The project aims to establish the State Institute of Hotel Management; Catering Technology at Kottayam District for around 300 students per year in the land owned and possessed by Revenue Department. |
Status | On-going |
District | Kottayam |
Executing Office | Office of GM1 |
TS Amount (Rs) | 146875833 |
TS Number | Order No.KIIDC/SIHM/2015 |
Technical specification | |
Contractor | Sitco Associates (Mob: 9846581300) |
Project Progress Status |
Project Progress Status |
Date of start of Package | 26/02/2014 |
---|---|
Scheduled date of Completion as per agreement | 31 Oct 2017 |
Expected date of Completion | 31/12/2021 |
TS Date | 27 Jan 2016 |
---|---|
Date Of Site Handover | 10 Mar 2016 |
# | Component Name | Component Amount | Updated Percentage | Updated Amount in Lakhs |
---|---|---|---|---|
1 | Academic Block | 134832015 | 77 % | 0 |
Atheesh.P. Mohan |
Date: 11/06/2024 |
Work in progress | 77% Completed
Work stopped by the contractor due to request for enhancing the rate for the balance work. Meeting with director Tourism has decided to terminate the present contract and arrange the balance work in separate tender. But the minutes of above meeting is not yet received. The preparation of estimate for balance work completed and submitted to GM. meeting conducted at secretariat in the chamber of secretary of tourism department in order to discuss the status of the work on 14-09-2023. Conducted a meeting on 18-09-2023 and directed the architect to edit the drawings and conduct a joint meeting with IHMCT officials. Estimate and report submitted to to Tourism department. Revised DPR for the balance work prepared and submitted..
Attached images
Atheesh.P. Mohan |
Date: 11/06/2024 |
Work in progress | 77% Completed
Work stopped by the contractor due to request for enhancing the rate for the balance work. Meeting with director Tourism has decided to terminate the present contract and arrange the balance work in separate tender. But the minutes of above meeting is not yet received. The preparation of estimate for balance work completed and submitted to GM. meeting conducted at secretariat in the chamber of secretary of tourism department in order to discuss the status of the work on 14-09-2023. Conducted a meeting on 18-09-2023 and directed the architect to edit the drawings and conduct a joint meeting with IHMCT officials. Estimate and report submitted to to Tourism department. Revised DPR for the balance work prepared and submitted..
Attached images