SETTING-UP OF STATE INSTITUTE OF HOTEL MANAGEMENT (SIHM) AT PALA, KOTTAYAM – CONSTRUCTION OF ACADEMIC BLOCK

Project SETTING-UP OF STATE INSTITUTE OF HOTEL MANAGEMENT (SIHM) AT PALA, KOTTAYAM – CONSTRUCTION OF ACADEMIC BLOCK
Project Code KTMTDK021439P1
Main Project SETTING-UP OF STATE INSTITUTE OF HOTEL MANAGEMENT (SIHM) AT PALA, KOTTAYAM – CONSTRUCTION OF ACADEMIC BLOCK
Work Category
Funding Agency TDK
Client Department Tourism Department
Description The project aims to establish the State Institute of Hotel Management; Catering Technology at Kottayam District for around 300 students per year in the land owned and possessed by Revenue Department.
Status On-going
District Kottayam
Executing Office Office of GM1
TS Amount (Rs) 146875833
TS Number Order No.KIIDC/SIHM/2015
Technical specification
Contractor Sitco Associates (Mob: 9846581300)

No project review have been added to this project

Project Progress Status

Project Progress Status

Duration & Sanction dates

Date of start of Package 26/02/2014
Scheduled date of Completion as per agreement 31 Oct 2017
Expected date of Completion 31/12/2021

Processing Dates

TS Date 27 Jan 2016
Date Of Site Handover 10 Mar 2016

Other details

Project Schedule View
Project Components View
Project Officers View

Component Progress Summary

# Component Name Component Amount Updated Percentage Updated Amount in Lakhs
1 Academic Block 134832015 77 % 0

Project Status Updations See All Status Updations

Atheesh.P. Mohan
Date: 11/06/2024

Work in progress | 77% Completed

Work stopped by the contractor due to request for enhancing the rate for the balance work. Meeting with director Tourism has decided to terminate the present contract and arrange the balance work in separate tender. But the minutes of above meeting is not yet received. The preparation of estimate for balance work completed and submitted to GM. meeting conducted at secretariat in the chamber of secretary of tourism department in order to discuss the status of the work on 14-09-2023. Conducted a meeting on 18-09-2023 and directed the architect to edit the drawings and conduct a joint meeting with IHMCT officials. Estimate and report submitted to to Tourism department. Revised DPR for the balance work prepared and submitted..

Attached images

img

Atheesh.P. Mohan
Date: 11/06/2024

Work in progress | 77% Completed

Work stopped by the contractor due to request for enhancing the rate for the balance work. Meeting with director Tourism has decided to terminate the present contract and arrange the balance work in separate tender. But the minutes of above meeting is not yet received. The preparation of estimate for balance work completed and submitted to GM. meeting conducted at secretariat in the chamber of secretary of tourism department in order to discuss the status of the work on 14-09-2023. Conducted a meeting on 18-09-2023 and directed the architect to edit the drawings and conduct a joint meeting with IHMCT officials. Estimate and report submitted to to Tourism department. Revised DPR for the balance work prepared and submitted..

Attached images

img