Improvements to Anthakarathode in Thrippunithura Municipality ,Ernakulam district

Project Improvements to Anthakarathode in Thrippunithura Municipality ,Ernakulam district
Project Code EKMKIIFB041824P1
Main Project Improvements to Anthakarathode in Thrippunithura Municipality ,Ernakulam district
Work Category
Funding Agency KIIFB
Client Department Water Resource Department
Description Anthakarathode is a thode in between Konothupuzha and Chambakkara kayal.Length of thode is 2.17 km.Project consists of cleaning and desilting of thode,side protection with pre cast pile-slab and DR masonry , construction of skew bridge,foot bridge and boat jetty.The main aim of the project is clean and improve the thodu and regain it to its past glory. The improved condition of the thodu is expected to give a boost to tourism, navigation, and flood control and become the main attraction of the town.
Status On-going
District Ernakulam
Executing Office Office of GM1
TS Amount (Rs) 97851240
TS Number T.S.No.2/TS/KIIDC/2018-19
Technical specification
Contractor Southern Tech (Mob: 1234567890)

No project review have been added to this project

Project Progress Status

Project Progress Status

Duration & Sanction dates

Date of start of Package 23/04/2018
Scheduled date of Completion as per agreement 07 Jan 2020
Expected date of Completion 31/10/2022

Processing Dates

TS Date 04 Jun 2018
Date Of Site Handover 08 Oct 2018

Other details

Project Schedule View
Project Components View
Project Officers View

Component Progress Summary

# Component Name Component Amount Updated Percentage Updated Amount in Lakhs
1 Thode Cleaning & Desiltation 8267200 100 % 62 L
2 Side Protection works 39081478.5 100 % 375.18 L
3 Roadway & Walkway 26457294.5 100 % 201.08 L
4 Construction of Skew Bridge 3521421.34 100 % 35.21 L
5 Foot Bridge 863085.34 100 % 8.63 L
6 Construction of Jetty 364795.15 100 % 3.65 L
7 Removing hyacinth & organic, Plastic meterials from Thode 5000000 100 % 38 L

Project Status Updations See All Status Updations

Joel J Varghese
Date: 30/12/2024

Work has been completed | 100% Completed

Work has been Completed Waiting for Sang works to complete and to give completion Handing over pending .

Joel J Varghese
Date: 30/12/2024

Work has been completed | 100% Completed

Work has been Completed Waiting for Sang works to complete and to give completion Handing over pending .