Project | Improvements to Anthakarathode in Thrippunithura Municipality ,Ernakulam district |
---|---|
Project Code | EKMKIIFB041824P1 |
Main Project | Improvements to Anthakarathode in Thrippunithura Municipality ,Ernakulam district |
Work Category | Funding Agency | KIIFB |
Client Department | Water Resource Department |
Description | Anthakarathode is a thode in between Konothupuzha and Chambakkara kayal.Length of thode is 2.17 km.Project consists of cleaning and desilting of thode,side protection with pre cast pile-slab and DR masonry , construction of skew bridge,foot bridge and boat jetty.The main aim of the project is clean and improve the thodu and regain it to its past glory. The improved condition of the thodu is expected to give a boost to tourism, navigation, and flood control and become the main attraction of the town. |
Status | On-going |
District | Ernakulam |
Executing Office | Office of GM1 |
TS Amount (Rs) | 97851240 |
TS Number | T.S.No.2/TS/KIIDC/2018-19 |
Technical specification | |
Contractor | Southern Tech (Mob: 1234567890) |
Project Progress Status |
Project Progress Status |
Date of start of Package | 23/04/2018 |
---|---|
Scheduled date of Completion as per agreement | 07 Jan 2020 |
Expected date of Completion | 31/10/2022 |
TS Date | 04 Jun 2018 |
---|---|
Date Of Site Handover | 08 Oct 2018 |
# | Component Name | Component Amount | Updated Percentage | Updated Amount in Lakhs |
---|---|---|---|---|
1 | Thode Cleaning & Desiltation | 8267200 | 100 % | 62 L |
2 | Side Protection works | 39081478.5 | 100 % | 375.18 L |
3 | Roadway & Walkway | 26457294.5 | 100 % | 201.08 L |
4 | Construction of Skew Bridge | 3521421.34 | 100 % | 35.21 L |
5 | Foot Bridge | 863085.34 | 100 % | 8.63 L |
6 | Construction of Jetty | 364795.15 | 100 % | 3.65 L |
7 | Removing hyacinth & organic, Plastic meterials from Thode | 5000000 | 100 % | 38 L |
Joel J Varghese |
Date: 30/12/2024 |
Work has been completed | 100% Completed
Work has been Completed Waiting for Sang works to complete and to give completion Handing over pending .
Joel J Varghese |
Date: 30/12/2024 |
Work has been completed | 100% Completed
Work has been Completed Waiting for Sang works to complete and to give completion Handing over pending .