KIIFB PROJECT- THALASSERY HERITAGE PROJECT- PHASE 1- PAZHASSI CIRCUIT- KOTTIYOOR SIVA TEMPLE - TOURIST AMENITIES

Project KIIFB PROJECT- THALASSERY HERITAGE PROJECT- PHASE 1- PAZHASSI CIRCUIT- KOTTIYOOR SIVA TEMPLE - TOURIST AMENITIES
Project Code KNRKIIFB082016P1
Main Project KIIFB PROJECT- THALASSERY HERITAGE PROJECT- PHASE 1- PAZHASSI CIRCUIT- KOTTIYOOR SIVA TEMPLE - TOURIST AMENITIES
Work Category
Funding Agency KIIFB
Client Department Tourism Department
Description The project is titled “Thalassery Heritage Project”, as Thalassery city as the epicenter of the project boundary established. The destinations majorly lie along Kannur district under Thalassery, Kannur and a few stretches up to Mananthavady in Wayanad district and Vadakara in Kozhikode district. The project will enhance the tourism experiences of Kerala, and will open up an entirely new region for economic development
Status On-going
District Kannur
Executing Office Office of GM1
TS Amount (Rs) 17880000
TS Number KITDC/890/Thalassery Heritage-Phase1- Kottiyoor Siva Temple/2020
Technical specification
Contractor M/S Rubicon Project Management Pvt Ltd (Mob: 9400040280)

No project review have been added to this project

Project Progress Status

Project Progress Status

Duration & Sanction dates

Date of start of Package 09/08/2020
Scheduled date of Completion as per agreement 15 Sep 2022
Expected date of Completion Date is not specified

Processing Dates

TS Date 05 Nov 2020
Date Of Site Handover 08 Mar 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Component Progress Summary

# Component Name Component Amount Updated Percentage Updated Amount in Lakhs
1 kottiyoor shiva temple-tourist amenities 17491971.97 78 % 34.98 L

Project Status Updations See All Status Updations

Ebin Solomon
Date: 22/04/2024

Work in progress | 78% Completed

Dormitory roofing work completed. Plumbing and electrical work in progress .

Ebin Solomon
Date: 22/04/2024

Work in progress | 78% Completed

Dormitory roofing work completed. Plumbing and electrical work in progress .