Project | Ecolodge Peerumedu - Final Estimate for Functional Operation - General Civil Work |
---|---|
Project Code | IDKTDK0623104P1 |
Main Project | Ecolodge Peerumedu - Final Estimate for Functional Operation - General Civil Work |
Work Category | Funding Agency | TDK |
Client Department | Tourism Department |
Description | Ecolodge Peerumedu - Final Estimate for Functional Operation - General Civil Work |
Status | |
District | Idukki |
Executing Office | Office of GM1 |
TS Amount (Rs) | 13640000 |
TS Number | Order No. IRR/KIIDC/EST_TS/2083_5_1_1 dated 11/07/2023 |
Technical specification |
Project Progress Status |
Project Progress Status |
Date of start of Package | 04/10/2023 |
---|---|
Scheduled date of Completion as per agreement | 03 Apr 2024 |
Expected date of Completion | 03/04/2024 |
TS Date | 11 Jul 2023 |
---|---|
Date Of Site Handover | 04 Oct 2023 |
Joel J Varghese |
Date: 20/03/2025 |
Work has been completed | 100% Completed
Works have been completed.
Joel J Varghese |
Date: 03/03/2025 |
Work has been completed | 100% Completed
Works have been completed .