Project | Ecolodge Peerumedu - Final Estimate for Functional Operation - General Civil Work |
---|---|
Project Code | IDKTDK0623104P1 |
Main Project | Ecolodge Peerumedu - Final Estimate for Functional Operation - General Civil Work |
Work Category | Funding Agency | TDK |
Client Department | Tourism Department |
Description | Ecolodge Peerumedu - Final Estimate for Functional Operation - General Civil Work |
Status | |
District | Idukki |
Executing Office | Office of GM1 |
TS Amount (Rs) | 13640000 |
TS Number | Order No. IRR/KIIDC/EST_TS/2083_5_1_1 dated 11/07/2023 |
Technical specification |
Project Progress Status |
Project Progress Status |
Date of start of Package | 04/10/2023 |
---|---|
Scheduled date of Completion as per agreement | 03 Apr 2024 |
Expected date of Completion | 03/04/2024 |
TS Date | 11 Jul 2023 |
---|---|
Date Of Site Handover | 04 Oct 2023 |
Teenu Augustine |
Date: 26/07/2024 |
Work in progress | 80% Completed
Parking yard-100% ,Retaining wall & fencing-60% , .pathway to Ecolodge-95% ,Front path way,Garden& play area -80% , Interelock around ecolodge-100% , Courtyard-70% ,Passage to ADA rest room-removed, ecolodge & service block-80% completed, Eco lodage & service block accessories-0% completed, readymade biogas plant-0% completed, rain water harvesting arrangements-0% completed, renovation of gate-0% completed, Arch with logo at entrance-20% completed, Signage boards-0% completed,Electrification-60% completed.