UP-GRADATION OF GOVT ITI CHANDANATHOPE ON PAR WITH INTERNATIONAL STANDARDS - PHASE 1

Project UP-GRADATION OF GOVT ITI CHANDANATHOPE ON PAR WITH INTERNATIONAL STANDARDS - PHASE 1
Project Code KLMGOK121643
Work Category Buildings
Funding Agency KIIFB
Client Department KASE
Description It aims in providing Modern facilities in campus including International standard roads, pathways, gardens, lighting etc. Construction of a new Main building with Smart Class Rooms with integrated provisions for learning including modernized IT ready classrooms. The new Main building serves as an upgraded Administration Block for the Institute with all facilities ready to welcome International guests, Multinational Companies for setting up Production Centres.
Status On-going
District Kollam
Executing Office Office of GM1
AS Amount (Rs) 88430000
AS Number GO(Rt) No.1568/2016LBR
TS Amount (Rs) 40724281
TS Number KASE-20/2016
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
1 UP-GRADATION OF GOVT ITI CHANDANATHOPE ON PAR WITH INTERNATIONAL STANDARDS - PHASE 1 Office of GM1

Overall Project Status

Status Date Overall Project Status Project Officer Contact
18 Sep 2022 1.main building civil work -89% completed.electrical work on going.. 2.road work -WMM Laying completed 3.compund wall -plastering completed 4.front gate -ACP WORK IN PROGRESS Meenu .E. S

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 23/12/2016
Scheduled date of Completion of the Project 23 Aug 2021
Expected date of Completion 30/10/2022

Processing Dates

AS Date 23 Dec 2016
TS Date 15 Feb 2020

Other details

Project Officers View