| Project | KIIFB PROJECT- THALASSERY HERITAGE PROJECT - PHASE II- FOLKLORE CIRCUIT - SREE THACHOLI MANIKOTHU TEMPLE IN VADAKARA, KOZHIKODU |
|---|---|
| Project Code | CLTKIIFB1220112P1 |
| Main Project | KIIFB PROJECT- THALASSERY HERITAGE PROJECT - PHASE II- FOLKLORE CIRCUIT - SREE THACHOLI MANIKOTHU TEMPLE IN VADAKARA, KOZHIKODU |
| Work Category | Funding Agency | KIIFB |
| Client Department | Tourism Department |
| Description | KIIFB PROJECT- THALASSERY HERITAGE PROJECT - PHASE II- FOLKLORE CIRCUIT - SREE THACHOLI MANIKOTHU TEMPLE IN VADAKARA, KOZHIKODU |
| Status | |
| District | Kozhikkode |
| Executing Office | Office of GM1 |
| TS Amount (Rs) | 20298000 |
| TS Number | KIIDC/87/2021-PE15 |
| Technical specification |
Project Progress Status |
Project Progress Status |
| Date of start of Package | 31/07/2023 |
|---|---|
| Scheduled date of Completion as per agreement | Date is not specified |
| Expected date of Completion | Date is not specified |
| TS Date | 20 Dec 2022 |
|---|---|
| Tender Publish Date | 23 Dec 2022 |
| Tender Opening Date | 10 Jan 2023 |
| Technical Bid Opening Date | 10 Jan 2023 |
| Financial Bid Opening Date | 24 Jan 2023 |
| Selection Notice Issued Date | 28 Mar 2023 |
| ANUPAMA S |
| Date: 15/09/2025 |
Work in progress | 90% Completed
No activities at site .
| ANUPAMA S |
| Date: 08/09/2025 |
Work in progress | 90% Completed
No activities at site .