ADDITIONAL WORK II OF ECO LODGE, IDUKKI (CONSTRUCTION OF SUMP TANK, PUMP HOUSE,SECURITY ROOM, FENCING, LANDSCAPING, ELECTRIFICATION)

Project ADDITIONAL WORK II OF ECO LODGE, IDUKKI (CONSTRUCTION OF SUMP TANK, PUMP HOUSE,SECURITY ROOM, FENCING, LANDSCAPING, ELECTRIFICATION)
Project Code IDKTDK052036
Work Category Tourism
Funding Agency TDK
Client Department Tourism Department
Description Scope of the project is to facilitate functioning of eco-lodge at Idukki, constructed by KIIDC by providing water supply, electrification and improving security features by providing security cabin, fencing, and beautification of the work by landscaping.
Status Physically Completed
District Idukki
Executing Office Office of GM1
AS Amount (Rs) 5985426
AS Number Order No.HB4-12769/2018(1)
TS Amount (Rs) 5372000
TS Number Order No.KIIDC/560/Additional Works II/Ecolodge Construction at Idukki/2020
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
1 ADDITIONAL WORK II OF ECO LODGE, IDUKKI (CONSTRUCTION OF SUMP TANK, PUMP HOUSE,SECURITY ROOM, FENCING, LANDSCAPING, ELECTRIFICATION) Office of GM1

No status have been added to this project

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 29/05/2020
Scheduled date of Completion of the Project 07 Jul 2021
Expected date of Completion Date is not specified

Processing Dates

AS Date 04 Jan 2021
TS Date 22 Jun 2020

Other details

Project Officers View