Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

UP GRADATION OF GOVT ITI ETTUMANOOR ON PAR WITH INTERNATIONAL STANDARDS

Project UP GRADATION OF GOVT ITI ETTUMANOOR ON PAR WITH INTERNATIONAL STANDARDS
Project Code KTMGOK121645P1
Main Project UP GRADATION OF GOVT ITI ETTUMANOOR ON PAR WITH INTERNATIONAL STANDARDS
Work Category
Funding Agency KIIFB
Client Department KASE
Description It aims in providing Modern facilities in campus including International standard roads, pathways, gardens, lighting etc. Construction of a new Main building with Smart Class Rooms with integrated provisions for learning including modernized IT ready classrooms. The new Main building serves as an upgraded Administration Block for the Institute with all facilities ready to welcome International guests, Multinational Companies for setting up Production Centres.
Status On-going
District Kottayam
Executing Office Office of GM1
TS Amount (Rs) 76203000
TS Number KASE-20/2016
Technical specification
Contractor M/s SWATHY CONSTRUCTIONS (Mob: 7356885163)

No project review have been added to this project

Project Progress Status

Project Progress Status

Duration & Sanction dates

Date of start of Package 23/12/2016
Scheduled date of Completion as per agreement 08 Sep 2021
Expected date of Completion 05/11/2022

Processing Dates

TS Date 15 Feb 2020
Date Of Site Handover 08 Oct 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Component Progress Summary

# Component Name Component Amount Updated Percentage Updated Amount in Lakhs
1 ITI ETTUMANOOR 69525558 100 % 646.59 L

Project Status Updations See All Status Updations

Atheesh.P. Mohan
Date: 11/06/2024

Work has been completed | 100% Completed

All works completed. Site Handed over by sri S S Namboodiri sir ( PD, KASE) to smt. Susi Antony ( Principal, ITI Ettumanoor ) in presence of Kase, kiidc and ITI officials on 13 th April 2023. A revised estimate submitted to KASE, it is under the scrutiny of KIIFB.

Attached images

img

Atheesh.P. Mohan
Date: 11/06/2024

Work has been completed | 100% Completed

All works completed. Site Handed over by sri S S Namboodiri sir ( PD, KASE) to smt. Susi Antony ( Principal, ITI Ettumanoor ) in presence of Kase, kiidc and ITI officials on 13 th April 2023. A revised estimate submitted to KASE, it is under the scrutiny of KIIFB.

Attached images

img