CONSTRUCTION OF REGULATOR CUM BRIDGE ACROSS PUNOOR PUZHA NEAR KWA PUMPING HOUSE AT POOLAKKADAVU IN KURUVATTOOR GRAMA PANCHAYATH, KOZHIKODE DISTRICT

Project CONSTRUCTION OF REGULATOR CUM BRIDGE ACROSS PUNOOR PUZHA NEAR KWA PUMPING HOUSE AT POOLAKKADAVU IN KURUVATTOOR GRAMA PANCHAYATH, KOZHIKODE DISTRICT
Project Code CLTKIIFB032183P1
Main Project CONSTRUCTION OF REGULATOR CUM BRIDGE ACROSS PUNOOR PUZHA NEAR KWA PUMPING HOUSE AT POOLAKKADAVU IN KURUVATTOOR GRAMA PANCHAYATH, KOZHIKODE DISTRICT
Work Category
Funding Agency KIIFB
Client Department Water Resource Department
Description CONSTRUCTION OF REGULATOR CUM BRIDGE ACROSS PUNOOR PUZHA NEAR KWA PUMPING HOUSE AT POOLAKKADAVU IN KURUVATTOOR GRAMA PANCHAYATH, KOZHIKODE DISTRICT
Status On-going
District Kozhikkode
Executing Office Office of GM1
TS Amount (Rs) 251063602
TS Number KIIDC/122/RCB-Poonur-Poolakkadavu,Kozhikkode/2021
Technical specification
Contractor M/S Uralungal Labour Contract Co-op Society Ltd (Mob: 9446002401)

No project review have been added to this project

Project Progress Status

Project Progress Status

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement 26 Feb 2023
Expected date of Completion 26/02/2023

Processing Dates

TS Date 20 Feb 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Component Progress Summary

# Component Name Component Amount Updated Percentage Updated Amount in Lakhs
1 electrical room 1198535.54 0 % 0
2 regulator cum bridge 84671840.81 50 % 194.75 L
3 approach road 4944677.85 0 % 0
4 electrical work 1272580 0 % 0
5 side protection of rivers 55437699.6 1 % 0
6 approach road and bank connection 55854202 0 % 0
7 mechanical work 23466166.18 20 % 0

Project Status Updations See All Status Updations

ANUPAMA S
Date: 29/07/2024

Work in progress | 65% Completed

Work hindered due to heavy rain at the site.

ANUPAMA S
Date: 29/07/2024

Work in progress | 65% Completed

Work hindered due to heavy rain at the site.