Project | THALASSERY HERITAGE PROJECT - PHASE 2 - Pazhassi Circuit - Puralimala Temple at Maloor in Kannur District |
---|---|
Project Code | KNRKIIFB122095P1 |
Main Project | THALASSERY HERITAGE PROJECT - PHASE 2 - Pazhassi Circuit - Puralimala Temple at Maloor in Kannur District |
Work Category | Funding Agency | KIIFB |
Client Department | Tourism Department |
Description | THALASSERY HERITAGE PROJECT - PHASE 2 - Pazhassi Circuit - Puralimala Temple at Maloor in Kannur District |
Status | On-going |
District | Kannur |
Executing Office | Office of GM1 |
TS Amount (Rs) | 6502127 |
TS Number | KIIDC/51/THP-Phase 2-Puralimala Temple -Kannur/2021 |
Technical specification |
Project Progress Status |
Project Progress Status |
Date of start of Package | Date is not specified |
---|---|
Scheduled date of Completion as per agreement | Date is not specified |
Expected date of Completion | Date is not specified |
TS Date | 26 Feb 2021 |
---|---|
Tender Publish Date | 08 Jun 2021 |
Tender Opening Date | 25 Jun 2021 |
Technical Bid Opening Date | 25 Jun 2021 |
# | Component Name | Component Amount | Updated Percentage | Updated Amount in Lakhs |
---|---|---|---|---|
1 | puralimala temple | 6279215.13 | 45 % | 0 |
Sijo Varghese |
Date: 26/07/2024 |
Work in progress | 45% Completed
Office Block - Roof concreting completed, Plastering works, Parappet wall Construction, Electrical works Progressing. Toilet Block - Roof Concreting, Plastering & Tile works completed. Pathway - Laterite works completed. Nadapanthal - Fooring , Column RCC works completed. First Bill - 12.5 Lakhs - Pending. Works Delay Due to heavy rainfall..
Sijo Varghese |
Date: 26/07/2024 |
Work in progress | 45% Completed
Office Block - Roof concreting completed, Plastering works, Parappet wall Construction, Electrical works Progressing. Toilet Block - Roof Concreting, Plastering & Tile works completed. Pathway - Laterite works completed. Nadapanthal - Fooring , Column RCC works completed. First Bill - 12.5 Lakhs - Pending. Works Delay Due to heavy rainfall..