Project | Providing Community Micro Irrigation in Navithankulam LIS Construction of Sump Fertigation Room Deepening and widening of pond and Electrification for Micro Irrigation Work at Navithankulam LIS-CIVIL PART |
---|---|
Project Code | PKDRKI062028P2 |
Main Project | Providing Community Micro Irrigation in Navithankulam LIS - at Navithankulam, Palakkad, District |
Work Category | Funding Agency | RKI |
Client Department | Water Resource Department |
Description | Providing Community Micro Irrigation in Navithankulam LIS Construction of Sump Fertigation Room Deepening and widening of pond and Electrification for Micro Irrigation Work at Navithankulam LIS-CIVIL PART |
Status | On-going |
District | Palakkad |
Executing Office | Office of GM2 |
TS Amount (Rs) | 8760000 |
TS Number | Order No.KIIDC/592/Micro Irrigation-Navithankulam LIS |
Technical specification | |
Contractor | JAIN IRRIGATION SYSTEMS LTD (Mob: 9443034530) |
Project Progress Status |
Project Progress Status |
Date of start of Package | 02/06/2020 |
---|---|
Scheduled date of Completion as per agreement | 25 Jun 2022 |
Expected date of Completion | 30/11/2022 |
TS Date | 04 Sep 2020 |
---|
# | Component Name | Component Amount | Updated Percentage | Updated Amount in Lakhs |
---|---|---|---|---|
1 | Sump Tank | 439470.8 | 0 % | 0 |
2 | Fertigation Room | 525765.54 | 78 % | 0 |
3 | Renovation of pond | 4428812.48 | 18 % | 0 |
4 | Electrification | 1112451.18 | 0 % | 0 |
Amal Padmu L P |
Date: 04/09/2023 |
Work in progress | 98% Completed
EB connection Pending.
Amal Padmu L P |
Date: 04/09/2023 |
Work in progress | 98% Completed
EB connection Pending.