Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
17 Sep 2022 | 6nos Groynes completed out of 13nos,3 nos are in progress and 4nos to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ 28.06.2022 | Silppa R |