Overall Project Status

Status Date Overall Project Status Project Officer Contact
17 Feb 2025 [1] Pavement and pathway 88.00% [2] Welcome fountain 75.00% [3] Children play area 70.00% [4] Seating 99.00% [5] Security room & cloak room 98.00% [6] Pavilion 94.00% [7] Railing 98.00% [8] View point 90.00% [9] Building renovation 96.00% [10] Toilet renovation 25.00% [11] Shed to shop conversion 98.00% [12] Shops 98.00% [13] Gathering Space 35.00% [14] Coir Mat 95.00% [15] Benches 50.00% [16] Dustbin and sinage 0.00% [17] Toilet block 95.00% [18] Electrification 70.00% [19] Microirrigation 25.00% [20] Provision for steel bridge 100.00% [21] Soft landscaping 70.00% [22] Fencing 100.00% [23] Water tank 95.00% [24] Plumbing 65.00% [25] Gate 60.00% [26] Pump house and sump well 70.00% MIDHUN DAS
25 Sep 2023 1 Appendix A - Pavement and pathway 80.00% Area clearing and site preparation for laying of interlocking paver block. 2 Appendix B - Welcome fountain 65.00% Welcome fountain foundation and water tank completed. Plastering work of fountain completed. Trench making for draining wastewater. 3 Appendix C - Pergola - 4 Appendix D - Children play area 35.00% site clearing works completed. 5 Appendix E - Seating 96.00% Floor tiles fixing in progress. seating top granite works completed. Painting work not completed. 6 Appendix F - Security room & cloak room 98.00% Room-exterior and interior plastering completed. Tile work completed. Window door frame fixing completed. Floor tiling work completed. Roof tile(shringles) laying completed. Exterior and interior works except fixing of doors completed. Sanitary fitting work not completed. 7 Appendix G - Pavilion 93.00% Floor granite fixing works completed. Painting work not completed. 8 Appendix H - Photo point cancelled 9 Appendix I - Railing 93.00% Handrail fixing completed. Painting works remaining. 10 Appendix J - View point 70.00% Foundation work completed. Floor concreting completed. SS handrail and plastering work not completed. 11 Appendix K - Building renovation 96.00% Roof tile laying works completed. Exterior and interior works in progress. 12 Appendix L - Toilet renovation 2.00% clearance completed 13 Appendix M - Shed to shop conversion 98.00% Roof tile laying works completed. Exterior and interior painting works completed. Rolling Shutter work completed. 14 Appendix N - Shops 98.00% Roof tile laying works completed. Exterior and interior painting works completed. Rolling Shutter work completed. 15 Appendix O - Gathering Space 35.00% Clearance completed 16 Appendix P - Coir Mat 40.00% Area clearance and Surface dressing work in progress 17 Appendix Q - Benches 20.00% Material procurement in progress 18 Appendix R - Dustbin and signage 0.00% 19 Appendix S - Toilet block 95.00% Roof tile laying works completed. Exterior and interior painting works completed. Door, window, and sanitary fittings fixing not completed. 20 Appendix T - Electrification 65.00% Building electrical work completed 21 Appendix U - Micro irrigation 25.00% Clearance completed 22 Appendix V - Provision for steel bridge 99.00% Provision for Steel Bridge (82%)-bridge handrails fixing completed, remaining works are in progress. 23 Appendix W - Soft landscaping 30.00% Grass planting in progress. 24 Appendix X - Fencing 30.00% Fencing around water tank area in progress. 25 Appendix Y - Water tank 99.00% Finishing works completed. 26 Appendix Z- Plumbing 50.00% Building plumbing works completed 27 Appendix ZA - Gates 30.00% Pillar concreting second lift completed Vishnu Thulasi
16 Sep 2022 STATUS OF WORKS IN TERMS OF COMPONENTS Appendix A- Pavement and pathway(68%) Appendix B- Welcome fountain(13%) Appendix C- Pergola (0%) Appendix D-Childrens play area(15%) Appendix E- Seating(10%) Appendix F- Security& cloak room(78%) Appendix G-Pavilion(83%) Appendix H- Photo point(cancelled) Appendix I- Railing(25%) Appendix J- View point(36%) Appendix k- Building renovation(75%) Appendix L- Toilet renovation(0%) Appendix M-Shed to shop conversion(65%) Appendix N-Shop(70%) Appendix S-Toilet(70%) Appendix T-Electrification(0%) Appendix U- Micro Irrigation(0%) Appendix V- Provision for Steel Bridge(0%) Appendix W- Soft Landscaping(0%) APPENDIX X- FENCING(0%) APPENDIX Y - WATER TANK(85%) APPENDIX Z- PLUMBING(17%) APPENDIX ZA- GATES(0%) 1.Pavilion-Around step work brick work completed.plastering completed. 2.Toilet – exterior and interior plastering completed.floor tiling and wall tiling completed. 3.Security cabin& Cloak room-exterior and interior plastering completed.window door frame fixing completed.floor tiling work in progress 4.Pavement and pathway –remaining pathway pcc completed.pathway tiling work in progress 5.Welcome fountain –site clearance completed.backside retaining wall RR work in progress 6.Seating-site clearance completed.backside retaining wall rr work completed. 7.Childrens play area- site clearance completed.back side of play area retaining wall foundation work in progress. 8.View point- brick work completed.filling completed 9.Shops-exterior and interior plastering completed.shop rolling shuttering work in progress.floor tile work in progress. 10.Shed to shop-pathwork completed.rolling shuttering work completed.floor tile work in progress 11.Building renovation-exterior and interior plastering completed. .rolling shuttering work completed.floor tile work in progress.side ramp work in progress 12.Railing- foundation concrete work in progress.handrails welding work in progress. Meenu .E. S