Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
19 Sep 2022 | The remaining civil works were affected due to heavy rain and consequent flood. Mechanical Works, Gate type-1, 3 nos fabrication completed in fabrication Yard, Trichy. welding is in progress | Sethu Madhavan K | |
19 Sep 2022 | The remaining civil works were affected due to heavy rain and consequent flood Mechanical Works. Gate type-1, 3 nos fabrication completed in fabrication Yard, Trichy. welding is in progress | Sethu Madhavan K |