Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
19 Sep 2022 | Main building Civil works completed, Road and ancillary works completed, Front gate, compound wall and security cabin works are completed. ELV works are at 98%, Electrical works are progressing, DG procured at site | Anjaly C R | |