Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
20 Jul 2023 | Work on hold | Nithish C | |
10 Jul 2023 | Work on hold | Nithish C | |
03 Jul 2023 | Closing the lift openings with blockwork | Nithish C | |
26 Jun 2023 | Closing the lift openings with blockwork | Nithish C | |
19 Jun 2023 | Primer applying at first floor | Nithish C | |
12 Jun 2023 | Closing the lift openings with blockwork | Nithish C | |
05 Jun 2023 | 1.Closing the lift openings with blockwork 2. Plastering of first floor seating area (cantilever projection). 3. Plastering of parapet wall. | Nithish C | |
29 May 2023 | Primer applying at UGF | Nithish C | |
23 May 2023 | ELV work progressing | Nithish C | |
17 May 2023 | ELV work progressing | Nithish C |