Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
04 Mar 2025 | Aqueduct super structure and pond renovation works are progressing at site | DIDI RAVINDRAN | |
19 Feb 2025 | Canal over embankment works, aqueduct pier lift works and tunnel works are ongoing at site | DIDI RAVINDRAN | |
25 Jul 2024 | PCC work at chainage 3+970 to 3+950 | DIDI RAVINDRAN | |
04 Jul 2024 | Backfill and compaction at 4350 to 4+270 | DIDI RAVINDRAN | |
20 Jun 2024 | 4+135 to 4+105 raft reinforcement work | DIDI RAVINDRAN | |
03 Jun 2024 | Pier lift for P 68,P69 | DIDI RAVINDRAN | |
23 May 2024 | P73 second lift | DIDI RAVINDRAN | |
13 May 2024 | 4350 to 4380 wall and slab reinforcement work | DIDI RAVINDRAN | |
06 May 2024 | P 75 pier lift | DIDI RAVINDRAN | |
02 May 2024 | Pier 113 backfilling and compaction | DIDI RAVINDRAN |