Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
07 Sep 2024 | Pile concrete for left hand abutment portion executed. Pile concrete for left hand side retaining wall under process. Cofferdam work for the regulator portion under process with coconut pile driving and implementation of geotextile completed. Earth filling on the bund under progress. | Nithin J B |