Ebin Solomon |
Date: 22/03/2025 |
Work has been completed | 100% Completed
Fertigation room|100% Completed
Lamp post|0% Completed
Sump Tank|100% Completed
Electrification|0% Completed
Completed
Ebin Solomon |
Date: 03/03/2025 |
Work has been completed | 100% Completed
Electrification|0% Completed
Lamp post|0% Completed
Sump Tank|100% Completed
Fertigation room|100% Completed
Physically completed
Ebin Solomon |
Date: 17/02/2025 |
Work has been completed | 100% Completed
Electrification|0% Completed
Lamp post|0% Completed
Sump Tank|100% Completed
Fertigation room|100% Completed
Completed
Ebin Solomon |
Date: 01/04/2024 |
Work in progress | 98% Completed
Electrification|0% Completed
Lamp post|0% Completed
Sump Tank|100% Completed
Fertigation room|100% Completed
Work in progress. 99% Completed Fertigation room 99% Completed Electrification 0% Completed Sump Tank - 96% Completed Lamp post - 0% Completed Fertigation room 99%
Ebin Solomon |
Date: 03/01/2024 |
Work in progress | 96% Completed
Electrification|0% Completed
Lamp post|0% Completed
Sump Tank|100% Completed
Fertigation room|100% Completed
Fertigation room | 99% Completed Electrification | 0% Completed Sump Tank | 96% Completed Lamp post | 0% Completed Civil Part has been completed
Joel J Varghese |
Date: 20/11/2023 |
Work in progress | 96% Completed
Electrification|0% Completed
Lamp post|0% Completed
Sump Tank|100% Completed
Fertigation room|100% Completed
Civil Part has been completed
Date: 24/06/2023 |
Work in progress | 95% Completed
Electrification|0% Completed
Lamp post|0% Completed
Sump Tank|100% Completed
Fertigation room|100% Completed
95% COMPLETED
Date: 20/05/2023 |
Work in progress | 95% Completed
Electrification|0% Completed
Lamp post|0% Completed
Sump Tank|100% Completed
Fertigation room|100% Completed
95% completed
Date: 13/05/2023 |
Work in progress | 95% Completed
Fertigation room|100% Completed
Lamp post|0% Completed
Sump Tank|100% Completed
Electrification|0% Completed
95% completed
Date: 08/05/2023 |
Work in progress | 95% Completed
Fertigation room|100% Completed
Lamp post|0% Completed
Sump Tank|100% Completed
Electrification|0% Completed
95% COMPLETED
Date: 24/04/2023 |
Work in progress | 95% Completed
Electrification|0% Completed
Lamp post|0% Completed
Sump Tank|100% Completed
Fertigation room|100% Completed
95% completed
Date: 10/04/2023 |
Work in progress | 95% Completed
Electrification|0% Completed
Lamp post|0% Completed
Sump Tank|100% Completed
Fertigation room|100% Completed
95%completed
Date: 03/04/2023 |
Work in progress | 95% Completed
Electrification|0% Completed
Lamp post|0% Completed
Sump Tank|100% Completed
Fertigation room|100% Completed
95% work completed
Date: 27/03/2023 |
Work in progress | 95% Completed
Electrification|0% Completed
Lamp post|0% Completed
Sump Tank|100% Completed
Fertigation room|100% Completed
95% COMPLETED
Date: 13/03/2023 |
Work in progress | 94% Completed
Electrification|0% Completed
Lamp post|0% Completed
Sump Tank|100% Completed
Fertigation room|100% Completed
94 % work completed
Date: 27/02/2023 |
Work in progress | 94% Completed
Electrification|0% Completed
Lamp post|0% Completed
Sump Tank|100% Completed
Fertigation room|100% Completed
95% completed
Date: 20/02/2023 |
Work in progress | 94% Completed
Electrification|0% Completed
Lamp post|0% Completed
Sump Tank|100% Completed
Fertigation room|100% Completed
Laying of pipe yet to done.
Date: 13/02/2023 |
Work in progress | 94% Completed
Electrification|0% Completed
Lamp post|0% Completed
Sump Tank|100% Completed
Fertigation room|100% Completed
Sump tank and fertigation room completed
Date: 06/02/2023 |
Work in progress | 94% Completed
Fertigation room|100% Completed
Electrification|0% Completed
Sump Tank|100% Completed
Lamp post|0% Completed
Fertigation room and Sump tank completed
Date: 30/01/2023 |
Work in progress | 94% Completed
Fertigation room|100% Completed
Lamp post|0% Completed
Sump Tank|100% Completed
Electrification|0% Completed
Ele work completed
Date: 23/01/2023 |
Work in progress | 94% Completed
Electrification|0% Completed
Lamp post|0% Completed
Sump Tank|100% Completed
Fertigation room|100% Completed
Ele work ongoing
Date: 16/01/2023 |
Date: 09/01/2023 |
Work in progress | 94% Completed
Electrification|0% Completed
Lamp post|0% Completed
Sump Tank|100% Completed
Fertigation room|100% Completed
Electrical work ongoing
Date: 02/01/2023 |
Work in progress | 94% Completed
Electrification|0% Completed
Lamp post|0% Completed
Sump Tank|100% Completed
Fertigation room|100% Completed
Ele work ongoing
Date: 26/12/2022 |
Work in progress | 94% Completed
Electrification|0% Completed
Lamp post|0% Completed
Sump Tank|100% Completed
Fertigation room|100% Completed
ele work ongoing
Date: 19/12/2022 |
Date: 12/12/2022 |
Date: 07/12/2022 |
Work in progress | 90% Completed
Electrification|0% Completed
Lamp post|0% Completed
Sump Tank|100% Completed
Fertigation room|100% Completed
Plastering ongoing
Date: 01/12/2022 |
Date: 03/11/2022 |
Date: 02/11/2022 |
Date: 01/11/2022 |
Work in progress | 0% Completed
Electrification|0% Completed
Lamp post|0% Completed
Sump Tank|100% Completed
Fertigation room|100% Completed
Fertigation room brick work up to lintel level completed
GPS Cordinates
Latitude : 11.6251225
Longitude : 76.1717202
Accuracy : 6.732999801635742
Attached images
Date: 25/10/2022 |
Date: 18/10/2022 |
Date: 15/10/2022 |
Date: 06/10/2022 |
Date: 05/10/2022 |