Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Joel J Varghese
Date: 20/03/2025

Work in progress | 5% Completed

% |0% Completed

Work has been stopped due to stakeholders' issues.Presently no works are ongoing

Joel J Varghese
Date: 03/03/2025

Work in progress | 5% Completed

% |0% Completed

Work stopped due to issues with Stakeholders Clarification in content received After the latest meeting, it has been decided to restart the work from 06/03/2025

Joel J Varghese
Date: 03/03/2025

Work in progress | 5% Completed

% |0% Completed

Work stopped due to issues with Stakeholders Clarification in content received After the latest meeting, it has been decided to restart the work from 06/03/2025

Joel J Varghese
Date: 17/02/2025

Work in progress | 5% Completed

% |0% Completed

Work has been delayed due to stakeholders' issues during the laying of the mainline All other works are delayed due to this issue Pipe laid in one land has to be removed

Attached images

img img

Joel J Varghese
Date: 30/12/2024

Work in progress | 2% Completed

% |0% Completed

Micro Part Main Line all materials arrived User association Registerd Work has been stopped due to Stakeholders issue and will resume on 01/01/2025 Civil Part Filter Room Land Registration to KIIDC Way to Filter Room not Finalized Civil works will start after this Pond Renovation and desilting will only done when the water level in the field decrease Electrical Part The Permenent Connect Estimate has been provided by KSEB soon,The boundary for laying Electric Posts has finalized

Joel J Varghese
Date: 20/03/2025

Work in progress | 0% Completed

Work has been stopped due to stakeholders' issues.Presently no works are ongoing

Joel J Varghese
Date: 03/03/2025

Work in progress | 0% Completed

Work stopped due to issues with Stakeholders Clarification in content received After the latest meeting, it has been decided to restart the work from 06/03/2025

Joel J Varghese
Date: 03/03/2025

Work in progress | 0% Completed

Work stopped due to issues with Stakeholders Clarification in content received After the latest meeting, it has been decided to restart the work from 06/03/2025

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Work has been delayed due to stakeholders' issues during the laying of the mainline All other works are delayed due to this issue Pipe laid in one land has to be removed

Attached images

img img

Joel J Varghese
Date: 30/12/2024

Work in progress | 0% Completed

Micro Part Main Line all materials arrived User association Registerd Work has been stopped due to Stakeholders issue and will resume on 01/01/2025 Civil Part Filter Room Land Registration to KIIDC Way to Filter Room not Finalized Civil works will start after this Pond Renovation and desilting will only done when the water level in the field decrease Electrical Part The Permenent Connect Estimate has been provided by KSEB soon,The boundary for laying Electric Posts has finalized