Joel J Varghese
Date: 17/03/2025

Work in progress | 67% Completed

% APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed

% Electrification|0% Completed

% Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed

% Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed

% WELL ( 2 nos )|0% Completed

% PUMP ROOM (5x5)|0% Completed

% Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed

% APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed

% CHECK DAM AND SIDE PROTECTION WORKS|0% Completed

% APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed

% OVER HEAD WATER TANK (8x8)|0% Completed

% Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed

% POND (20x13)|0% Completed

% Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed

Well works near check dam in progress

Joel J Varghese
Date: 03/03/2025

Work in progress | 65% Completed

% PUMP ROOM (5x5)|0% Completed

% OVER HEAD WATER TANK (8x8)|0% Completed

% POND (20x13)|0% Completed

% Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed

% CHECK DAM AND SIDE PROTECTION WORKS|0% Completed

% Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed

% APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed

% APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed

% Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed

% APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed

% Electrification|0% Completed

% Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed

% Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed

% WELL ( 2 nos )|0% Completed

Check dam Abutment works completed Side protection 14 m u/s and d/s completed Well work started near the check dam

Joel J Varghese
Date: 03/03/2025

Work in progress | 65% Completed

% OVER HEAD WATER TANK (8x8)|0% Completed

% POND (20x13)|0% Completed

% Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed

% CHECK DAM AND SIDE PROTECTION WORKS|0% Completed

% Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed

% APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed

% APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed

% Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed

% APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed

% Electrification|0% Completed

% Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed

% WELL ( 2 nos )|0% Completed

% PUMP ROOM (5x5)|0% Completed

% Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed

Check dam Abutment works completed Side protection 14 m u/s and d/s completed Well work started near the check dam

Joel J Varghese
Date: 17/02/2025

Work in progress | 60% Completed

% PUMP ROOM (5x5)|0% Completed

% OVER HEAD WATER TANK (8x8)|0% Completed

% POND (20x13)|0% Completed

% Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed

% CHECK DAM AND SIDE PROTECTION WORKS|0% Completed

% Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed

% APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed

% APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed

% Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed

% APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed

% Electrification|0% Completed

% Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed

% Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed

% WELL ( 2 nos )|0% Completed

Physical progress is 60%. The pump room and overhead tank structure are completed, finishing works are pending. Check dam foundation and abutment are completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 60% Completed

% OVER HEAD WATER TANK (8x8)|0% Completed

% POND (20x13)|0% Completed

% Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed

% CHECK DAM AND SIDE PROTECTION WORKS|0% Completed

% Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed

% APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed

% APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed

% Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed

% APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed

% Electrification|0% Completed

% Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed

% Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed

% WELL ( 2 nos )|0% Completed

% PUMP ROOM (5x5)|0% Completed

Physical progress is 60% . The pump room and overhead tank structure careare completed, finishing works are pending. Check dam foundation and abutment are completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 60% Completed

% OVER HEAD WATER TANK (8x8)|0% Completed

% POND (20x13)|0% Completed

% Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed

% CHECK DAM AND SIDE PROTECTION WORKS|0% Completed

% Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed

% APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed

% APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed

% Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed

% APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed

% Electrification|0% Completed

% Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed

% Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed

% WELL ( 2 nos )|0% Completed

% PUMP ROOM (5x5)|0% Completed

Physical progress 60% .Pump room and over head tank structure completed,finishing works pending. Check dam foundation and abutment completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 60% Completed

% OVER HEAD WATER TANK (8x8)|0% Completed

% POND (20x13)|0% Completed

% Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed

% CHECK DAM AND SIDE PROTECTION WORKS|0% Completed

% Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed

% APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed

% APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed

% Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed

% APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed

% Electrification|0% Completed

% Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed

% Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed

% WELL ( 2 nos )|0% Completed

% PUMP ROOM (5x5)|0% Completed

Physical progress 60% .Pump room and over head tank structure completed,finishing works pending. Check dam foundation and abutment completed.DR retaining wall work in progress.

Teenu Augustine
Date: 25/07/2024

Work in progress | 17% Completed

% WELL ( 2 nos )|0% Completed

% OVER HEAD WATER TANK (8x8)|0% Completed

% POND (20x13)|0% Completed

% PUMP ROOM (5x5)|0% Completed

% Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed

% CHECK DAM AND SIDE PROTECTION WORKS|0% Completed

% Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed

% APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed

% APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed

% Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed

% APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed

% Electrification|0% Completed

% Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed

% Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 17% Completed

% OVER HEAD WATER TANK (8x8)|0% Completed

% POND (20x13)|0% Completed

% Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed

% CHECK DAM AND SIDE PROTECTION WORKS|0% Completed

% Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed

% APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed

% APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed

% Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed

% APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed

% Electrification|0% Completed

% Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed

% Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed

% WELL ( 2 nos )|0% Completed

% PUMP ROOM (5x5)|0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 17% Completed

% OVER HEAD WATER TANK (8x8)|0% Completed

% POND (20x13)|0% Completed

% Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed

% CHECK DAM AND SIDE PROTECTION WORKS|0% Completed

% Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed

% APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed

% APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed

% Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed

% APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed

% Electrification|0% Completed

% Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed

% Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed

% WELL ( 2 nos )|0% Completed

% PUMP ROOM (5x5)|0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 03/06/2024

Work in progress | 17% Completed

% APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed

% PUMP ROOM (5x5)|0% Completed

% WELL ( 2 nos )|0% Completed

% Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed

% Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed

% Electrification|0% Completed

% APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed

% Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed

% APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed

% Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed

% CHECK DAM AND SIDE PROTECTION WORKS|0% Completed

% Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed

% POND (20x13)|0% Completed

% OVER HEAD WATER TANK (8x8)|0% Completed

work delayed due to heavy rain

Teenu Augustine
Date: 27/05/2024

Work in progress | 17% Completed

% PUMP ROOM (5x5)|0% Completed

% OVER HEAD WATER TANK (8x8)|0% Completed

% POND (20x13)|0% Completed

% Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed

% CHECK DAM AND SIDE PROTECTION WORKS|0% Completed

% Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed

% APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed

% APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed

% Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed

% APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed

% Electrification|0% Completed

% Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed

% Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed

% WELL ( 2 nos )|0% Completed

work delayed due to heavy rain

Teenu Augustine
Date: 20/05/2024

Work in progress | 17% Completed

% APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed

% OVER HEAD WATER TANK (8x8)|0% Completed

% POND (20x13)|0% Completed

% Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed

% CHECK DAM AND SIDE PROTECTION WORKS|0% Completed

% Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed

% APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed

% Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed

% APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed

% Electrification|0% Completed

% Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed

% Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed

% WELL ( 2 nos )|0% Completed

% PUMP ROOM (5x5)|0% Completed

no work during last week.

Teenu Augustine
Date: 13/05/2024

Work in progress | 17% Completed

% PUMP ROOM (5x5)|0% Completed

% OVER HEAD WATER TANK (8x8)|0% Completed

% POND (20x13)|0% Completed

% Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed

% CHECK DAM AND SIDE PROTECTION WORKS|0% Completed

% Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed

% APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed

% APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed

% Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed

% APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed

% Electrification|0% Completed

% Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed

% Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed

% WELL ( 2 nos )|0% Completed

check dam works ongoing

Attached images

img img

Teenu Augustine
Date: 06/05/2024

Work in progress | 17% Completed

% Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed

% OVER HEAD WATER TANK (8x8)|0% Completed

% POND (20x13)|0% Completed

% Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed

% CHECK DAM AND SIDE PROTECTION WORKS|0% Completed

% Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed

% APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed

% PUMP ROOM (5x5)|0% Completed

% APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed

% Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed

% APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed

% Electrification|0% Completed

% Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed

% WELL ( 2 nos )|0% Completed

check dam and abutment superstructure works ongoing

Attached images

img img

Teenu Augustine
Date: 29/04/2024

Work in progress | 16% Completed

% PUMP ROOM (5x5)|0% Completed

% OVER HEAD WATER TANK (8x8)|0% Completed

% POND (20x13)|0% Completed

% Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed

% CHECK DAM AND SIDE PROTECTION WORKS|0% Completed

% Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed

% APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed

% APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed

% Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed

% APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed

% Electrification|0% Completed

% Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed

% Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed

% WELL ( 2 nos )|0% Completed

check dam foundation works

Attached images

img img

Teenu Augustine
Date: 22/04/2024

Work in progress | 15% Completed

% PUMP ROOM (5x5)|0% Completed

% OVER HEAD WATER TANK (8x8)|0% Completed

% POND (20x13)|0% Completed

% Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed

% CHECK DAM AND SIDE PROTECTION WORKS|0% Completed

% Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed

% APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed

% APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed

% Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed

% APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed

% Electrification|0% Completed

% Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed

% Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed

% WELL ( 2 nos )|0% Completed

check dam foundation works.

Attached images

img img

Teenu Augustine
Date: 15/04/2024

Work in progress | 15% Completed

% WELL ( 2 nos )|0% Completed

% OVER HEAD WATER TANK (8x8)|0% Completed

% POND (20x13)|0% Completed

% Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed

% CHECK DAM AND SIDE PROTECTION WORKS|0% Completed

% Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed

% APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed

% APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed

% Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed

% APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed

% Electrification|0% Completed

% Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed

% Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed

% PUMP ROOM (5x5)|0% Completed

check dam foundation works ongoing

Attached images

img img

Teenu Augustine
Date: 08/04/2024

Work in progress | 14% Completed

% APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed

% OVER HEAD WATER TANK (8x8)|0% Completed

% POND (20x13)|0% Completed

% Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed

% CHECK DAM AND SIDE PROTECTION WORKS|0% Completed

% Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed

% APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed

% Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed

% APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed

% Electrification|0% Completed

% Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed

% Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed

% WELL ( 2 nos )|0% Completed

% PUMP ROOM (5x5)|0% Completed

overhead water tank- beam at 3m - concreting completed check dam earthwork started

Attached images

img img

Teenu Augustine
Date: 01/04/2024

Work in progress | 12% Completed

% WELL ( 2 nos )|0% Completed

% OVER HEAD WATER TANK (8x8)|0% Completed

% POND (20x13)|0% Completed

% Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed

% CHECK DAM AND SIDE PROTECTION WORKS|0% Completed

% Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed

% APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed

% PUMP ROOM (5x5)|0% Completed

% APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed

% Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed

% APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed

% Electrification|0% Completed

% Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed

% Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed

overhead water tank- beam at 3m - steel and shuttering works ongoing

Attached images

img img img

Teenu Augustine
Date: 25/03/2024

Work in progress | 10% Completed

% PUMP ROOM (5x5)|0% Completed

% OVER HEAD WATER TANK (8x8)|0% Completed

% POND (20x13)|0% Completed

% Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed

% CHECK DAM AND SIDE PROTECTION WORKS|0% Completed

% Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed

% APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed

% APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed

% Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed

% APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed

% Electrification|0% Completed

% Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed

% Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed

% WELL ( 2 nos )|0% Completed

overhead water tank works ongoing

Attached images

img img img

Joel J Varghese
Date: 17/03/2025

Work in progress | 0% Completed

Well works near check dam in progress

Joel J Varghese
Date: 17/03/2025

Work in progress | 0% Completed

Well works near check dam in progress

Joel J Varghese
Date: 17/03/2025

Work in progress | 0% Completed

Well works near check dam in progress

Joel J Varghese
Date: 17/03/2025

Work in progress | 0% Completed

Well works near check dam in progress

Joel J Varghese
Date: 17/03/2025

Work in progress | 0% Completed

Well works near check dam in progress

Joel J Varghese
Date: 17/03/2025

Work in progress | 0% Completed

Well works near check dam in progress

Joel J Varghese
Date: 17/03/2025

Work in progress | 0% Completed

Well works near check dam in progress

Joel J Varghese
Date: 17/03/2025

Work in progress | 0% Completed

Well works near check dam in progress

Joel J Varghese
Date: 17/03/2025

Work in progress | 0% Completed

Well works near check dam in progress

Joel J Varghese
Date: 17/03/2025

Work in progress | 0% Completed

Well works near check dam in progress

Joel J Varghese
Date: 17/03/2025

Work in progress | 0% Completed

Well works near check dam in progress

Joel J Varghese
Date: 17/03/2025

Work in progress | 0% Completed

Well works near check dam in progress

Joel J Varghese
Date: 17/03/2025

Work in progress | 0% Completed

Well works near check dam in progress

Joel J Varghese
Date: 17/03/2025

Work in progress | 0% Completed

Well works near check dam in progress

Joel J Varghese
Date: 03/03/2025

Work in progress | 0% Completed

Check dam Abutment works completed Side protection 14 m u/s and d/s completed Well work started near the check dam

Joel J Varghese
Date: 03/03/2025

Work in progress | 0% Completed

Check dam Abutment works completed Side protection 14 m u/s and d/s completed Well work started near the check dam

Joel J Varghese
Date: 03/03/2025

Work in progress | 0% Completed

Check dam Abutment works completed Side protection 14 m u/s and d/s completed Well work started near the check dam

Joel J Varghese
Date: 03/03/2025

Work in progress | 0% Completed

Check dam Abutment works completed Side protection 14 m u/s and d/s completed Well work started near the check dam

Joel J Varghese
Date: 03/03/2025

Work in progress | 0% Completed

Check dam Abutment works completed Side protection 14 m u/s and d/s completed Well work started near the check dam

Joel J Varghese
Date: 03/03/2025

Work in progress | 0% Completed

Check dam Abutment works completed Side protection 14 m u/s and d/s completed Well work started near the check dam

Joel J Varghese
Date: 03/03/2025

Work in progress | 0% Completed

Check dam Abutment works completed Side protection 14 m u/s and d/s completed Well work started near the check dam

Joel J Varghese
Date: 03/03/2025

Work in progress | 0% Completed

Check dam Abutment works completed Side protection 14 m u/s and d/s completed Well work started near the check dam

Joel J Varghese
Date: 03/03/2025

Work in progress | 0% Completed

Check dam Abutment works completed Side protection 14 m u/s and d/s completed Well work started near the check dam

Joel J Varghese
Date: 03/03/2025

Work in progress | 0% Completed

Check dam Abutment works completed Side protection 14 m u/s and d/s completed Well work started near the check dam

Joel J Varghese
Date: 03/03/2025

Work in progress | 0% Completed

Check dam Abutment works completed Side protection 14 m u/s and d/s completed Well work started near the check dam

Joel J Varghese
Date: 03/03/2025

Work in progress | 0% Completed

Check dam Abutment works completed Side protection 14 m u/s and d/s completed Well work started near the check dam

Joel J Varghese
Date: 03/03/2025

Work in progress | 0% Completed

Check dam Abutment works completed Side protection 14 m u/s and d/s completed Well work started near the check dam

Joel J Varghese
Date: 03/03/2025

Work in progress | 0% Completed

Check dam Abutment works completed Side protection 14 m u/s and d/s completed Well work started near the check dam

Joel J Varghese
Date: 03/03/2025

Work in progress | 0% Completed

Check dam Abutment works completed Side protection 14 m u/s and d/s completed Well work started near the check dam

Joel J Varghese
Date: 03/03/2025

Work in progress | 0% Completed

Check dam Abutment works completed Side protection 14 m u/s and d/s completed Well work started near the check dam

Joel J Varghese
Date: 03/03/2025

Work in progress | 0% Completed

Check dam Abutment works completed Side protection 14 m u/s and d/s completed Well work started near the check dam

Joel J Varghese
Date: 03/03/2025

Work in progress | 0% Completed

Check dam Abutment works completed Side protection 14 m u/s and d/s completed Well work started near the check dam

Joel J Varghese
Date: 03/03/2025

Work in progress | 0% Completed

Check dam Abutment works completed Side protection 14 m u/s and d/s completed Well work started near the check dam

Joel J Varghese
Date: 03/03/2025

Work in progress | 0% Completed

Check dam Abutment works completed Side protection 14 m u/s and d/s completed Well work started near the check dam

Joel J Varghese
Date: 03/03/2025

Work in progress | 0% Completed

Check dam Abutment works completed Side protection 14 m u/s and d/s completed Well work started near the check dam

Joel J Varghese
Date: 03/03/2025

Work in progress | 0% Completed

Check dam Abutment works completed Side protection 14 m u/s and d/s completed Well work started near the check dam

Joel J Varghese
Date: 03/03/2025

Work in progress | 0% Completed

Check dam Abutment works completed Side protection 14 m u/s and d/s completed Well work started near the check dam

Joel J Varghese
Date: 03/03/2025

Work in progress | 0% Completed

Check dam Abutment works completed Side protection 14 m u/s and d/s completed Well work started near the check dam

Joel J Varghese
Date: 03/03/2025

Work in progress | 0% Completed

Check dam Abutment works completed Side protection 14 m u/s and d/s completed Well work started near the check dam

Joel J Varghese
Date: 03/03/2025

Work in progress | 0% Completed

Check dam Abutment works completed Side protection 14 m u/s and d/s completed Well work started near the check dam

Joel J Varghese
Date: 03/03/2025

Work in progress | 0% Completed

Check dam Abutment works completed Side protection 14 m u/s and d/s completed Well work started near the check dam

Joel J Varghese
Date: 03/03/2025

Work in progress | 0% Completed

Check dam Abutment works completed Side protection 14 m u/s and d/s completed Well work started near the check dam

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress is 60%. The pump room and overhead tank structure are completed, finishing works are pending. Check dam foundation and abutment are completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress is 60% . The pump room and overhead tank structure careare completed, finishing works are pending. Check dam foundation and abutment are completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress is 60% . The pump room and overhead tank structure careare completed, finishing works are pending. Check dam foundation and abutment are completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress is 60% . The pump room and overhead tank structure careare completed, finishing works are pending. Check dam foundation and abutment are completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress 60% .Pump room and over head tank structure completed,finishing works pending. Check dam foundation and abutment completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress 60% .Pump room and over head tank structure completed,finishing works pending. Check dam foundation and abutment completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress 60% .Pump room and over head tank structure completed,finishing works pending. Check dam foundation and abutment completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress 60% .Pump room and over head tank structure completed,finishing works pending. Check dam foundation and abutment completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress 60% .Pump room and over head tank structure completed,finishing works pending. Check dam foundation and abutment completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress 60% .Pump room and over head tank structure completed,finishing works pending. Check dam foundation and abutment completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress 60% .Pump room and over head tank structure completed,finishing works pending. Check dam foundation and abutment completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress 60% .Pump room and over head tank structure completed,finishing works pending. Check dam foundation and abutment completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress 60% .Pump room and over head tank structure completed,finishing works pending. Check dam foundation and abutment completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress 60% .Pump room and over head tank structure completed,finishing works pending. Check dam foundation and abutment completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress 60% .Pump room and over head tank structure completed,finishing works pending. Check dam foundation and abutment completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress 60% .Pump room and over head tank structure completed,finishing works pending. Check dam foundation and abutment completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress 60% .Pump room and over head tank structure completed,finishing works pending. Check dam foundation and abutment completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress 60% .Pump room and over head tank structure completed,finishing works pending. Check dam foundation and abutment completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress 60% .Pump room and over head tank structure completed,finishing works pending. Check dam foundation and abutment completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress 60% .Pump room and over head tank structure completed,finishing works pending. Check dam foundation and abutment completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress 60% .Pump room and over head tank structure completed,finishing works pending. Check dam foundation and abutment completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress 60% .Pump room and over head tank structure completed,finishing works pending. Check dam foundation and abutment completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress 60% .Pump room and over head tank structure completed,finishing works pending. Check dam foundation and abutment completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress 60% .Pump room and over head tank structure completed,finishing works pending. Check dam foundation and abutment completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress 60% .Pump room and over head tank structure completed,finishing works pending. Check dam foundation and abutment completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress 60% .Pump room and over head tank structure completed,finishing works pending. Check dam foundation and abutment completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress 60% .Pump room and over head tank structure completed,finishing works pending. Check dam foundation and abutment completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress 60% .Pump room and over head tank structure completed,finishing works pending. Check dam foundation and abutment completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress 60% .Pump room and over head tank structure completed,finishing works pending. Check dam foundation and abutment completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress 60% .Pump room and over head tank structure completed,finishing works pending. Check dam foundation and abutment completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress 60% .Pump room and over head tank structure completed,finishing works pending. Check dam foundation and abutment completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress 60% .Pump room and over head tank structure completed,finishing works pending. Check dam foundation and abutment completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress is 60%. The pump room and overhead tank structure are completed, finishing works are pending. Check dam foundation and abutment are completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress is 60%. The pump room and overhead tank structure are completed, finishing works are pending. Check dam foundation and abutment are completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress is 60%. The pump room and overhead tank structure are completed, finishing works are pending. Check dam foundation and abutment are completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress is 60%. The pump room and overhead tank structure are completed, finishing works are pending. Check dam foundation and abutment are completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress is 60%. The pump room and overhead tank structure are completed, finishing works are pending. Check dam foundation and abutment are completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress is 60%. The pump room and overhead tank structure are completed, finishing works are pending. Check dam foundation and abutment are completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress is 60%. The pump room and overhead tank structure are completed, finishing works are pending. Check dam foundation and abutment are completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress is 60%. The pump room and overhead tank structure are completed, finishing works are pending. Check dam foundation and abutment are completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress is 60%. The pump room and overhead tank structure are completed, finishing works are pending. Check dam foundation and abutment are completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress is 60%. The pump room and overhead tank structure are completed, finishing works are pending. Check dam foundation and abutment are completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress is 60%. The pump room and overhead tank structure are completed, finishing works are pending. Check dam foundation and abutment are completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress is 60%. The pump room and overhead tank structure are completed, finishing works are pending. Check dam foundation and abutment are completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress is 60%. The pump room and overhead tank structure are completed, finishing works are pending. Check dam foundation and abutment are completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress is 60% . The pump room and overhead tank structure careare completed, finishing works are pending. Check dam foundation and abutment are completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress is 60% . The pump room and overhead tank structure careare completed, finishing works are pending. Check dam foundation and abutment are completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress is 60% . The pump room and overhead tank structure careare completed, finishing works are pending. Check dam foundation and abutment are completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress is 60% . The pump room and overhead tank structure careare completed, finishing works are pending. Check dam foundation and abutment are completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress is 60% . The pump room and overhead tank structure careare completed, finishing works are pending. Check dam foundation and abutment are completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress is 60% . The pump room and overhead tank structure careare completed, finishing works are pending. Check dam foundation and abutment are completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress is 60% . The pump room and overhead tank structure careare completed, finishing works are pending. Check dam foundation and abutment are completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress is 60% . The pump room and overhead tank structure careare completed, finishing works are pending. Check dam foundation and abutment are completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress is 60% . The pump room and overhead tank structure careare completed, finishing works are pending. Check dam foundation and abutment are completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress is 60% . The pump room and overhead tank structure careare completed, finishing works are pending. Check dam foundation and abutment are completed.DR retaining wall work in progress.

Joel J Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Physical progress is 60% . The pump room and overhead tank structure careare completed, finishing works are pending. Check dam foundation and abutment are completed.DR retaining wall work in progress.

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 25/07/2024

Work in progress | 0% Completed

over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain

Teenu Augustine
Date: 03/06/2024

Work in progress | 0% Completed

work delayed due to heavy rain

Teenu Augustine
Date: 03/06/2024

Work in progress | 0% Completed

work delayed due to heavy rain

Teenu Augustine
Date: 03/06/2024

Work in progress | 0% Completed

work delayed due to heavy rain

Teenu Augustine
Date: 03/06/2024

Work in progress | 0% Completed

work delayed due to heavy rain

Teenu Augustine
Date: 03/06/2024

Work in progress | 0% Completed

work delayed due to heavy rain

Teenu Augustine
Date: 03/06/2024

Work in progress | 0% Completed

work delayed due to heavy rain

Teenu Augustine
Date: 03/06/2024

Work in progress | 0% Completed

work delayed due to heavy rain

Teenu Augustine
Date: 03/06/2024

Work in progress | 0% Completed

work delayed due to heavy rain

Teenu Augustine
Date: 03/06/2024

Work in progress | 0% Completed

work delayed due to heavy rain

Teenu Augustine
Date: 03/06/2024

Work in progress | 0% Completed

work delayed due to heavy rain

Teenu Augustine
Date: 03/06/2024

Work in progress | 0% Completed

work delayed due to heavy rain

Teenu Augustine
Date: 03/06/2024

Work in progress | 0% Completed

work delayed due to heavy rain

Teenu Augustine
Date: 03/06/2024

Work in progress | 0% Completed

work delayed due to heavy rain

Teenu Augustine
Date: 03/06/2024

Work in progress | 0% Completed

work delayed due to heavy rain

Teenu Augustine
Date: 27/05/2024

Work in progress | 0% Completed

work delayed due to heavy rain

Teenu Augustine
Date: 27/05/2024

Work in progress | 0% Completed

work delayed due to heavy rain

Teenu Augustine
Date: 27/05/2024

Work in progress | 0% Completed

work delayed due to heavy rain

Teenu Augustine
Date: 27/05/2024

Work in progress | 0% Completed

work delayed due to heavy rain

Teenu Augustine
Date: 27/05/2024

Work in progress | 0% Completed

work delayed due to heavy rain

Teenu Augustine
Date: 27/05/2024

Work in progress | 0% Completed

work delayed due to heavy rain

Teenu Augustine
Date: 27/05/2024

Work in progress | 0% Completed

work delayed due to heavy rain

Teenu Augustine
Date: 27/05/2024

Work in progress | 0% Completed

work delayed due to heavy rain

Teenu Augustine
Date: 27/05/2024

Work in progress | 0% Completed

work delayed due to heavy rain

Teenu Augustine
Date: 27/05/2024

Work in progress | 0% Completed

work delayed due to heavy rain

Teenu Augustine
Date: 27/05/2024

Work in progress | 0% Completed

work delayed due to heavy rain

Teenu Augustine
Date: 27/05/2024

Work in progress | 0% Completed

work delayed due to heavy rain

Teenu Augustine
Date: 27/05/2024

Work in progress | 0% Completed

work delayed due to heavy rain

Teenu Augustine
Date: 27/05/2024

Work in progress | 0% Completed

work delayed due to heavy rain

Teenu Augustine
Date: 20/05/2024

Work in progress | 0% Completed

no work during last week.

Teenu Augustine
Date: 20/05/2024

Work in progress | 0% Completed

no work during last week.

Teenu Augustine
Date: 20/05/2024

Work in progress | 0% Completed

no work during last week.

Teenu Augustine
Date: 20/05/2024

Work in progress | 0% Completed

no work during last week.

Teenu Augustine
Date: 20/05/2024

Work in progress | 0% Completed

no work during last week.

Teenu Augustine
Date: 20/05/2024

Work in progress | 0% Completed

no work during last week.

Teenu Augustine
Date: 20/05/2024

Work in progress | 0% Completed

no work during last week.

Teenu Augustine
Date: 20/05/2024

Work in progress | 0% Completed

no work during last week.

Teenu Augustine
Date: 20/05/2024

Work in progress | 0% Completed

no work during last week.

Teenu Augustine
Date: 20/05/2024

Work in progress | 0% Completed

no work during last week.

Teenu Augustine
Date: 20/05/2024

Work in progress | 0% Completed

no work during last week.

Teenu Augustine
Date: 20/05/2024

Work in progress | 0% Completed

no work during last week.

Teenu Augustine
Date: 20/05/2024

Work in progress | 0% Completed

no work during last week.

Teenu Augustine
Date: 20/05/2024

Work in progress | 0% Completed

no work during last week.

Teenu Augustine
Date: 13/05/2024

Work in progress | 0% Completed

check dam works ongoing

Attached images

img img

Teenu Augustine
Date: 13/05/2024

Work in progress | 0% Completed

check dam works ongoing

Attached images

img img

Teenu Augustine
Date: 13/05/2024

Work in progress | 0% Completed

check dam works ongoing

Attached images

img img

Teenu Augustine
Date: 13/05/2024

Work in progress | 0% Completed

check dam works ongoing

Attached images

img img

Teenu Augustine
Date: 13/05/2024

Work in progress | 0% Completed

check dam works ongoing

Attached images

img img

Teenu Augustine
Date: 13/05/2024

Work in progress | 0% Completed

check dam works ongoing

Attached images

img img

Teenu Augustine
Date: 13/05/2024

Work in progress | 0% Completed

check dam works ongoing

Attached images

img img

Teenu Augustine
Date: 13/05/2024

Work in progress | 0% Completed

check dam works ongoing

Attached images

img img

Teenu Augustine
Date: 13/05/2024

Work in progress | 0% Completed

check dam works ongoing

Attached images

img img

Teenu Augustine
Date: 13/05/2024

Work in progress | 0% Completed

check dam works ongoing

Attached images

img img

Teenu Augustine
Date: 13/05/2024

Work in progress | 0% Completed

check dam works ongoing

Attached images

img img

Teenu Augustine
Date: 13/05/2024

Work in progress | 0% Completed

check dam works ongoing

Attached images

img img

Teenu Augustine
Date: 13/05/2024

Work in progress | 0% Completed

check dam works ongoing

Attached images

img img

Teenu Augustine
Date: 13/05/2024

Work in progress | 0% Completed

check dam works ongoing

Attached images

img img

Teenu Augustine
Date: 06/05/2024

Work in progress | 0% Completed

check dam and abutment superstructure works ongoing

Attached images

img img

Teenu Augustine
Date: 06/05/2024

Work in progress | 0% Completed

check dam and abutment superstructure works ongoing

Attached images

img img

Teenu Augustine
Date: 06/05/2024

Work in progress | 0% Completed

check dam and abutment superstructure works ongoing

Attached images

img img

Teenu Augustine
Date: 06/05/2024

Work in progress | 0% Completed

check dam and abutment superstructure works ongoing

Attached images

img img

Teenu Augustine
Date: 06/05/2024

Work in progress | 0% Completed

check dam and abutment superstructure works ongoing

Attached images

img img

Teenu Augustine
Date: 06/05/2024

Work in progress | 0% Completed

check dam and abutment superstructure works ongoing

Attached images

img img

Teenu Augustine
Date: 06/05/2024

Work in progress | 0% Completed

check dam and abutment superstructure works ongoing

Attached images

img img

Teenu Augustine
Date: 06/05/2024

Work in progress | 0% Completed

check dam and abutment superstructure works ongoing

Attached images

img img

Teenu Augustine
Date: 06/05/2024

Work in progress | 0% Completed

check dam and abutment superstructure works ongoing

Attached images

img img

Teenu Augustine
Date: 06/05/2024

Work in progress | 0% Completed

check dam and abutment superstructure works ongoing

Attached images

img img

Teenu Augustine
Date: 06/05/2024

Work in progress | 0% Completed

check dam and abutment superstructure works ongoing

Attached images

img img

Teenu Augustine
Date: 06/05/2024

Work in progress | 0% Completed

check dam and abutment superstructure works ongoing

Attached images

img img

Teenu Augustine
Date: 06/05/2024

Work in progress | 0% Completed

check dam and abutment superstructure works ongoing

Attached images

img img

Teenu Augustine
Date: 06/05/2024

Work in progress | 0% Completed

check dam and abutment superstructure works ongoing

Attached images

img img

Teenu Augustine
Date: 29/04/2024

Work in progress | 0% Completed

check dam foundation works

Attached images

img img

Teenu Augustine
Date: 29/04/2024

Work in progress | 0% Completed

check dam foundation works

Attached images

img img

Teenu Augustine
Date: 29/04/2024

Work in progress | 0% Completed

check dam foundation works

Attached images

img img

Teenu Augustine
Date: 29/04/2024

Work in progress | 0% Completed

check dam foundation works

Attached images

img img

Teenu Augustine
Date: 29/04/2024

Work in progress | 0% Completed

check dam foundation works

Attached images

img img

Teenu Augustine
Date: 29/04/2024

Work in progress | 0% Completed

check dam foundation works

Attached images

img img

Teenu Augustine
Date: 29/04/2024

Work in progress | 0% Completed

check dam foundation works

Attached images

img img

Teenu Augustine
Date: 29/04/2024

Work in progress | 0% Completed

check dam foundation works

Attached images

img img

Teenu Augustine
Date: 29/04/2024

Work in progress | 0% Completed

check dam foundation works

Attached images

img img

Teenu Augustine
Date: 29/04/2024

Work in progress | 0% Completed

check dam foundation works

Attached images

img img

Teenu Augustine
Date: 29/04/2024

Work in progress | 0% Completed

check dam foundation works

Attached images

img img

Teenu Augustine
Date: 29/04/2024

Work in progress | 0% Completed

check dam foundation works

Attached images

img img

Teenu Augustine
Date: 29/04/2024

Work in progress | 0% Completed

check dam foundation works

Attached images

img img

Teenu Augustine
Date: 29/04/2024

Work in progress | 0% Completed

check dam foundation works

Attached images

img img

Teenu Augustine
Date: 22/04/2024

Work in progress | 0% Completed

check dam foundation works.

Attached images

img img

Teenu Augustine
Date: 22/04/2024

Work in progress | 0% Completed

check dam foundation works.

Attached images

img img

Teenu Augustine
Date: 22/04/2024

Work in progress | 0% Completed

check dam foundation works.

Attached images

img img

Teenu Augustine
Date: 22/04/2024

Work in progress | 0% Completed

check dam foundation works.

Attached images

img img

Teenu Augustine
Date: 22/04/2024

Work in progress | 0% Completed

check dam foundation works.

Attached images

img img

Teenu Augustine
Date: 22/04/2024

Work in progress | 0% Completed

check dam foundation works.

Attached images

img img

Teenu Augustine
Date: 22/04/2024

Work in progress | 0% Completed

check dam foundation works.

Attached images

img img

Teenu Augustine
Date: 22/04/2024

Work in progress | 0% Completed

check dam foundation works.

Attached images

img img

Teenu Augustine
Date: 22/04/2024

Work in progress | 0% Completed

check dam foundation works.

Attached images

img img

Teenu Augustine
Date: 22/04/2024

Work in progress | 0% Completed

check dam foundation works.

Attached images

img img

Teenu Augustine
Date: 22/04/2024

Work in progress | 0% Completed

check dam foundation works.

Attached images

img img

Teenu Augustine
Date: 22/04/2024

Work in progress | 0% Completed

check dam foundation works.

Attached images

img img

Teenu Augustine
Date: 22/04/2024

Work in progress | 0% Completed

check dam foundation works.

Attached images

img img

Teenu Augustine
Date: 22/04/2024

Work in progress | 0% Completed

check dam foundation works.

Attached images

img img

Teenu Augustine
Date: 15/04/2024

Work in progress | 0% Completed

check dam foundation works ongoing

Attached images

img img

Teenu Augustine
Date: 15/04/2024

Work in progress | 0% Completed

check dam foundation works ongoing

Attached images

img img

Teenu Augustine
Date: 15/04/2024

Work in progress | 0% Completed

check dam foundation works ongoing

Attached images

img img

Teenu Augustine
Date: 15/04/2024

Work in progress | 0% Completed

check dam foundation works ongoing

Attached images

img img

Teenu Augustine
Date: 15/04/2024

Work in progress | 0% Completed

check dam foundation works ongoing

Attached images

img img

Teenu Augustine
Date: 15/04/2024

Work in progress | 0% Completed

check dam foundation works ongoing

Attached images

img img

Teenu Augustine
Date: 15/04/2024

Work in progress | 0% Completed

check dam foundation works ongoing

Attached images

img img

Teenu Augustine
Date: 15/04/2024

Work in progress | 0% Completed

check dam foundation works ongoing

Attached images

img img

Teenu Augustine
Date: 15/04/2024

Work in progress | 0% Completed

check dam foundation works ongoing

Attached images

img img

Teenu Augustine
Date: 15/04/2024

Work in progress | 0% Completed

check dam foundation works ongoing

Attached images

img img

Teenu Augustine
Date: 15/04/2024

Work in progress | 0% Completed

check dam foundation works ongoing

Attached images

img img

Teenu Augustine
Date: 15/04/2024

Work in progress | 0% Completed

check dam foundation works ongoing

Attached images

img img

Teenu Augustine
Date: 15/04/2024

Work in progress | 0% Completed

check dam foundation works ongoing

Attached images

img img

Teenu Augustine
Date: 15/04/2024

Work in progress | 0% Completed

check dam foundation works ongoing

Attached images

img img

Teenu Augustine
Date: 08/04/2024

Work in progress | 0% Completed

overhead water tank- beam at 3m - concreting completed check dam earthwork started

Attached images

img img

Teenu Augustine
Date: 08/04/2024

Work in progress | 0% Completed

overhead water tank- beam at 3m - concreting completed check dam earthwork started

Attached images

img img

Teenu Augustine
Date: 08/04/2024

Work in progress | 0% Completed

overhead water tank- beam at 3m - concreting completed check dam earthwork started

Attached images

img img

Teenu Augustine
Date: 08/04/2024

Work in progress | 0% Completed

overhead water tank- beam at 3m - concreting completed check dam earthwork started

Attached images

img img

Teenu Augustine
Date: 08/04/2024

Work in progress | 0% Completed

overhead water tank- beam at 3m - concreting completed check dam earthwork started

Attached images

img img

Teenu Augustine
Date: 08/04/2024

Work in progress | 0% Completed

overhead water tank- beam at 3m - concreting completed check dam earthwork started

Attached images

img img

Teenu Augustine
Date: 08/04/2024

Work in progress | 0% Completed

overhead water tank- beam at 3m - concreting completed check dam earthwork started

Attached images

img img

Teenu Augustine
Date: 08/04/2024

Work in progress | 0% Completed

overhead water tank- beam at 3m - concreting completed check dam earthwork started

Attached images

img img

Teenu Augustine
Date: 08/04/2024

Work in progress | 0% Completed

overhead water tank- beam at 3m - concreting completed check dam earthwork started

Attached images

img img

Teenu Augustine
Date: 08/04/2024

Work in progress | 0% Completed

overhead water tank- beam at 3m - concreting completed check dam earthwork started

Attached images

img img

Teenu Augustine
Date: 08/04/2024

Work in progress | 0% Completed

overhead water tank- beam at 3m - concreting completed check dam earthwork started

Attached images

img img

Teenu Augustine
Date: 08/04/2024

Work in progress | 0% Completed

overhead water tank- beam at 3m - concreting completed check dam earthwork started

Attached images

img img

Teenu Augustine
Date: 08/04/2024

Work in progress | 0% Completed

overhead water tank- beam at 3m - concreting completed check dam earthwork started

Attached images

img img

Teenu Augustine
Date: 08/04/2024

Work in progress | 0% Completed

overhead water tank- beam at 3m - concreting completed check dam earthwork started

Attached images

img img

Teenu Augustine
Date: 01/04/2024

Work in progress | 0% Completed

overhead water tank- beam at 3m - steel and shuttering works ongoing

Attached images

img img img

Teenu Augustine
Date: 01/04/2024

Work in progress | 0% Completed

overhead water tank- beam at 3m - steel and shuttering works ongoing

Attached images

img img img

Teenu Augustine
Date: 01/04/2024

Work in progress | 0% Completed

overhead water tank- beam at 3m - steel and shuttering works ongoing

Attached images

img img img

Teenu Augustine
Date: 01/04/2024

Work in progress | 0% Completed

overhead water tank- beam at 3m - steel and shuttering works ongoing

Attached images

img img img

Teenu Augustine
Date: 01/04/2024

Work in progress | 0% Completed

overhead water tank- beam at 3m - steel and shuttering works ongoing

Attached images

img img img

Teenu Augustine
Date: 01/04/2024

Work in progress | 0% Completed

overhead water tank- beam at 3m - steel and shuttering works ongoing

Attached images

img img img

Teenu Augustine
Date: 01/04/2024

Work in progress | 0% Completed

overhead water tank- beam at 3m - steel and shuttering works ongoing

Attached images

img img img

Teenu Augustine
Date: 01/04/2024

Work in progress | 0% Completed

overhead water tank- beam at 3m - steel and shuttering works ongoing

Attached images

img img img

Teenu Augustine
Date: 01/04/2024

Work in progress | 0% Completed

overhead water tank- beam at 3m - steel and shuttering works ongoing

Attached images

img img img

Teenu Augustine
Date: 01/04/2024

Work in progress | 0% Completed

overhead water tank- beam at 3m - steel and shuttering works ongoing

Attached images

img img img

Teenu Augustine
Date: 01/04/2024

Work in progress | 0% Completed

overhead water tank- beam at 3m - steel and shuttering works ongoing

Attached images

img img img

Teenu Augustine
Date: 01/04/2024

Work in progress | 0% Completed

overhead water tank- beam at 3m - steel and shuttering works ongoing

Attached images

img img img

Teenu Augustine
Date: 01/04/2024

Work in progress | 0% Completed

overhead water tank- beam at 3m - steel and shuttering works ongoing

Attached images

img img img

Teenu Augustine
Date: 01/04/2024

Work in progress | 0% Completed

overhead water tank- beam at 3m - steel and shuttering works ongoing

Attached images

img img img

Teenu Augustine
Date: 25/03/2024

Work in progress | 0% Completed

overhead water tank works ongoing

Attached images

img img img

Teenu Augustine
Date: 25/03/2024

Work in progress | 0% Completed

overhead water tank works ongoing

Attached images

img img img

Teenu Augustine
Date: 25/03/2024

Work in progress | 0% Completed

overhead water tank works ongoing

Attached images

img img img

Teenu Augustine
Date: 25/03/2024

Work in progress | 0% Completed

overhead water tank works ongoing

Attached images

img img img

Teenu Augustine
Date: 25/03/2024

Work in progress | 0% Completed

overhead water tank works ongoing

Attached images

img img img

Teenu Augustine
Date: 25/03/2024

Work in progress | 0% Completed

overhead water tank works ongoing

Attached images

img img img

Teenu Augustine
Date: 25/03/2024

Work in progress | 0% Completed

overhead water tank works ongoing

Attached images

img img img

Teenu Augustine
Date: 25/03/2024

Work in progress | 0% Completed

overhead water tank works ongoing

Attached images

img img img

Teenu Augustine
Date: 25/03/2024

Work in progress | 0% Completed

overhead water tank works ongoing

Attached images

img img img

Teenu Augustine
Date: 25/03/2024

Work in progress | 0% Completed

overhead water tank works ongoing

Attached images

img img img

Teenu Augustine
Date: 25/03/2024

Work in progress | 0% Completed

overhead water tank works ongoing

Attached images

img img img

Teenu Augustine
Date: 25/03/2024

Work in progress | 0% Completed

overhead water tank works ongoing

Attached images

img img img

Teenu Augustine
Date: 25/03/2024

Work in progress | 0% Completed

overhead water tank works ongoing

Attached images

img img img

Teenu Augustine
Date: 25/03/2024

Work in progress | 0% Completed

overhead water tank works ongoing

Attached images

img img img