Joel J Varghese |
Date: 17/03/2025 |
Work in progress | 67% Completed
APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed
Electrification|0% Completed
Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed
Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed
WELL ( 2 nos )|0% Completed
PUMP ROOM (5x5)|0% Completed
Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed
APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed
CHECK DAM AND SIDE PROTECTION WORKS|0% Completed
APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed
OVER HEAD WATER TANK (8x8)|0% Completed
Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed
POND (20x13)|0% Completed
Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed
Well works near check dam in progress
Joel J Varghese |
Date: 03/03/2025 |
Work in progress | 65% Completed
PUMP ROOM (5x5)|0% Completed
OVER HEAD WATER TANK (8x8)|0% Completed
POND (20x13)|0% Completed
Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed
CHECK DAM AND SIDE PROTECTION WORKS|0% Completed
Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed
APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed
APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed
Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed
APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed
Electrification|0% Completed
Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed
Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed
WELL ( 2 nos )|0% Completed
Check dam Abutment works completed Side protection 14 m u/s and d/s completed Well work started near the check dam
Joel J Varghese |
Date: 03/03/2025 |
Work in progress | 65% Completed
OVER HEAD WATER TANK (8x8)|0% Completed
POND (20x13)|0% Completed
Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed
CHECK DAM AND SIDE PROTECTION WORKS|0% Completed
Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed
APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed
APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed
Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed
APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed
Electrification|0% Completed
Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed
WELL ( 2 nos )|0% Completed
PUMP ROOM (5x5)|0% Completed
Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed
Check dam Abutment works completed Side protection 14 m u/s and d/s completed Well work started near the check dam
Joel J Varghese |
Date: 17/02/2025 |
Work in progress | 60% Completed
PUMP ROOM (5x5)|0% Completed
OVER HEAD WATER TANK (8x8)|0% Completed
POND (20x13)|0% Completed
Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed
CHECK DAM AND SIDE PROTECTION WORKS|0% Completed
Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed
APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed
APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed
Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed
APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed
Electrification|0% Completed
Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed
Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed
WELL ( 2 nos )|0% Completed
Physical progress is 60%. The pump room and overhead tank structure are completed, finishing works are pending. Check dam foundation and abutment are completed.DR retaining wall work in progress.
Joel J Varghese |
Date: 17/02/2025 |
Work in progress | 60% Completed
OVER HEAD WATER TANK (8x8)|0% Completed
POND (20x13)|0% Completed
Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed
CHECK DAM AND SIDE PROTECTION WORKS|0% Completed
Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed
APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed
APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed
Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed
APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed
Electrification|0% Completed
Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed
Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed
WELL ( 2 nos )|0% Completed
PUMP ROOM (5x5)|0% Completed
Physical progress is 60% . The pump room and overhead tank structure careare completed, finishing works are pending. Check dam foundation and abutment are completed.DR retaining wall work in progress.
Joel J Varghese |
Date: 17/02/2025 |
Work in progress | 60% Completed
OVER HEAD WATER TANK (8x8)|0% Completed
POND (20x13)|0% Completed
Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed
CHECK DAM AND SIDE PROTECTION WORKS|0% Completed
Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed
APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed
APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed
Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed
APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed
Electrification|0% Completed
Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed
Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed
WELL ( 2 nos )|0% Completed
PUMP ROOM (5x5)|0% Completed
Physical progress 60% .Pump room and over head tank structure completed,finishing works pending. Check dam foundation and abutment completed.DR retaining wall work in progress.
Joel J Varghese |
Date: 17/02/2025 |
Work in progress | 60% Completed
OVER HEAD WATER TANK (8x8)|0% Completed
POND (20x13)|0% Completed
Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed
CHECK DAM AND SIDE PROTECTION WORKS|0% Completed
Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed
APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed
APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed
Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed
APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed
Electrification|0% Completed
Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed
Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed
WELL ( 2 nos )|0% Completed
PUMP ROOM (5x5)|0% Completed
Physical progress 60% .Pump room and over head tank structure completed,finishing works pending. Check dam foundation and abutment completed.DR retaining wall work in progress.
Teenu Augustine |
Date: 25/07/2024 |
Work in progress | 17% Completed
WELL ( 2 nos )|0% Completed
OVER HEAD WATER TANK (8x8)|0% Completed
POND (20x13)|0% Completed
PUMP ROOM (5x5)|0% Completed
Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed
CHECK DAM AND SIDE PROTECTION WORKS|0% Completed
Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed
APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed
APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed
Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed
APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed
Electrification|0% Completed
Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed
Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed
over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain
Teenu Augustine |
Date: 25/07/2024 |
Work in progress | 17% Completed
OVER HEAD WATER TANK (8x8)|0% Completed
POND (20x13)|0% Completed
Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed
CHECK DAM AND SIDE PROTECTION WORKS|0% Completed
Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed
APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed
APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed
Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed
APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed
Electrification|0% Completed
Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed
Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed
WELL ( 2 nos )|0% Completed
PUMP ROOM (5x5)|0% Completed
over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain
Teenu Augustine |
Date: 25/07/2024 |
Work in progress | 17% Completed
OVER HEAD WATER TANK (8x8)|0% Completed
POND (20x13)|0% Completed
Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed
CHECK DAM AND SIDE PROTECTION WORKS|0% Completed
Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed
APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed
APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed
Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed
APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed
Electrification|0% Completed
Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed
Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed
WELL ( 2 nos )|0% Completed
PUMP ROOM (5x5)|0% Completed
over head water tank - upto base slab completed. check dam - foundation works completed. now work hindering due to heavy rain
Teenu Augustine |
Date: 03/06/2024 |
Work in progress | 17% Completed
APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed
PUMP ROOM (5x5)|0% Completed
WELL ( 2 nos )|0% Completed
Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed
Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed
Electrification|0% Completed
APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed
Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed
APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed
Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed
CHECK DAM AND SIDE PROTECTION WORKS|0% Completed
Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed
POND (20x13)|0% Completed
OVER HEAD WATER TANK (8x8)|0% Completed
work delayed due to heavy rain
Teenu Augustine |
Date: 27/05/2024 |
Work in progress | 17% Completed
PUMP ROOM (5x5)|0% Completed
OVER HEAD WATER TANK (8x8)|0% Completed
POND (20x13)|0% Completed
Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed
CHECK DAM AND SIDE PROTECTION WORKS|0% Completed
Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed
APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed
APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed
Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed
APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed
Electrification|0% Completed
Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed
Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed
WELL ( 2 nos )|0% Completed
work delayed due to heavy rain
Teenu Augustine |
Date: 20/05/2024 |
Work in progress | 17% Completed
APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed
OVER HEAD WATER TANK (8x8)|0% Completed
POND (20x13)|0% Completed
Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed
CHECK DAM AND SIDE PROTECTION WORKS|0% Completed
Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed
APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed
Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed
APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed
Electrification|0% Completed
Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed
Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed
WELL ( 2 nos )|0% Completed
PUMP ROOM (5x5)|0% Completed
no work during last week.
Teenu Augustine |
Date: 13/05/2024 |
Work in progress | 17% Completed
PUMP ROOM (5x5)|0% Completed
OVER HEAD WATER TANK (8x8)|0% Completed
POND (20x13)|0% Completed
Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed
CHECK DAM AND SIDE PROTECTION WORKS|0% Completed
Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed
APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed
APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed
Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed
APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed
Electrification|0% Completed
Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed
Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed
WELL ( 2 nos )|0% Completed
check dam works ongoing
Attached images
Teenu Augustine |
Date: 06/05/2024 |
Work in progress | 17% Completed
Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed
OVER HEAD WATER TANK (8x8)|0% Completed
POND (20x13)|0% Completed
Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed
CHECK DAM AND SIDE PROTECTION WORKS|0% Completed
Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed
APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed
PUMP ROOM (5x5)|0% Completed
APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed
Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed
APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed
Electrification|0% Completed
Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed
WELL ( 2 nos )|0% Completed
check dam and abutment superstructure works ongoing
Attached images
Teenu Augustine |
Date: 29/04/2024 |
Work in progress | 16% Completed
PUMP ROOM (5x5)|0% Completed
OVER HEAD WATER TANK (8x8)|0% Completed
POND (20x13)|0% Completed
Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed
CHECK DAM AND SIDE PROTECTION WORKS|0% Completed
Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed
APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed
APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed
Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed
APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed
Electrification|0% Completed
Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed
Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed
WELL ( 2 nos )|0% Completed
check dam foundation works
Attached images
Teenu Augustine |
Date: 22/04/2024 |
Work in progress | 15% Completed
PUMP ROOM (5x5)|0% Completed
OVER HEAD WATER TANK (8x8)|0% Completed
POND (20x13)|0% Completed
Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed
CHECK DAM AND SIDE PROTECTION WORKS|0% Completed
Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed
APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed
APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed
Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed
APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed
Electrification|0% Completed
Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed
Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed
WELL ( 2 nos )|0% Completed
check dam foundation works.
Attached images
Teenu Augustine |
Date: 15/04/2024 |
Work in progress | 15% Completed
WELL ( 2 nos )|0% Completed
OVER HEAD WATER TANK (8x8)|0% Completed
POND (20x13)|0% Completed
Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed
CHECK DAM AND SIDE PROTECTION WORKS|0% Completed
Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed
APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed
APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed
Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed
APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed
Electrification|0% Completed
Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed
Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed
PUMP ROOM (5x5)|0% Completed
check dam foundation works ongoing
Attached images
Teenu Augustine |
Date: 08/04/2024 |
Work in progress | 14% Completed
APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed
OVER HEAD WATER TANK (8x8)|0% Completed
POND (20x13)|0% Completed
Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed
CHECK DAM AND SIDE PROTECTION WORKS|0% Completed
Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed
APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed
Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed
APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed
Electrification|0% Completed
Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed
Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed
WELL ( 2 nos )|0% Completed
PUMP ROOM (5x5)|0% Completed
overhead water tank- beam at 3m - concreting completed check dam earthwork started
Attached images
Teenu Augustine |
Date: 01/04/2024 |
Work in progress | 12% Completed
WELL ( 2 nos )|0% Completed
OVER HEAD WATER TANK (8x8)|0% Completed
POND (20x13)|0% Completed
Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed
CHECK DAM AND SIDE PROTECTION WORKS|0% Completed
Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed
APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed
PUMP ROOM (5x5)|0% Completed
APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed
Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed
APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed
Electrification|0% Completed
Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed
Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed
overhead water tank- beam at 3m - steel and shuttering works ongoing
Attached images
Teenu Augustine |
Date: 25/03/2024 |
Work in progress | 10% Completed
PUMP ROOM (5x5)|0% Completed
OVER HEAD WATER TANK (8x8)|0% Completed
POND (20x13)|0% Completed
Appendix E- Mechanical Work - Supply and fixing hoisting mechanism|0% Completed
CHECK DAM AND SIDE PROTECTION WORKS|0% Completed
Appendix B- Mechanical Work - Supply of materials, fabrication, painting and erection of shutter size 0.75 X 0.75m|0% Completed
APPENDIX-G PROVIDING COMMUNITY MICRO IRRIGATION MAINLINE WORKS|0% Completed
APPENDIX-H PROVIDING COMMUNITY MICRO IRRIGATION AUTOMATION AND HEAD UNIT|0% Completed
Appendix A- Mechanical Work - Supply, Fabrication, Erection and assembling of embedded parts|0% Completed
APPENDIX-F PROVIDING COMMUNITY MICRO IRRIGATION SUBMAIN WORKS|0% Completed
Electrification|0% Completed
Appendix C- Mechanical Work - Supplying and fixing of rubber seal|0% Completed
Appendix D- Mechanical Work - Supply of materials, fabrication and erection of hoisting bridge|0% Completed
WELL ( 2 nos )|0% Completed
overhead water tank works ongoing
Attached images