MIDHUN DAS |
Date: 24/03/2025 |
Work in progress | 60% Completed
Electrification|0% Completed
Mainline Works|75% Completed
pump room|0% Completed
Pond|0% Completed
Automation & Head unit|0% Completed
submain works|65% Completed
micro irrigation part work in progress.
MIDHUN DAS |
Date: 17/03/2025 |
Work in progress | 50% Completed
submain works|65% Completed
Electrification|0% Completed
Mainline Works|75% Completed
pump room|0% Completed
Pond|0% Completed
Automation & Head unit|0% Completed
MICRO IRRIGATION PIPELINE WORKS IN PROGRESS
MIDHUN DAS |
Date: 10/03/2025 |
Work in progress | 50% Completed
submain works|65% Completed
Automation & Head unit|0% Completed
Pond|0% Completed
pump room|0% Completed
Mainline Works|75% Completed
Electrification|0% Completed
main line and sublone trenching and laying in progress
MIDHUN DAS |
Date: 10/03/2025 |
Work in progress | 50% Completed
submain works|65% Completed
Automation & Head unit|0% Completed
Pond|0% Completed
pump room|0% Completed
Mainline Works|75% Completed
Electrification|0% Completed
main line and sublone trenching and laying in progress
MIDHUN DAS |
Date: 24/02/2025 |
Work in progress | 50% Completed
submain works|65% Completed
Electrification|0% Completed
Mainline Works|75% Completed
pump room|0% Completed
Pond|0% Completed
Automation & Head unit|0% Completed
Main line and subline trenching and laying upto 35 acres completed.
MIDHUN DAS |
Date: 17/02/2025 |
Work in progress | 10% Completed
Automation & Head unit|0% Completed
Electrification|0% Completed
Mainline Works|75% Completed
pump room|0% Completed
Pond|0% Completed
submain works|65% Completed
pump room civil work completed upto plastering, mainline trenching and pipe laying work are progressing.