Amal Padmu L P |
Date: 04/09/2023 |
Work in progress | 98% Completed
Electrification|0% Completed
Renovation of pond|18% Completed
Fertigation Room|78% Completed
Sump Tank|0% Completed
EB connection Pending
Amal Padmu L P |
Date: 10/07/2023 |
Amal Padmu L P |
Date: 03/07/2023 |
Work in progress | 95% Completed
Sump Tank|0% Completed
Renovation of pond|18% Completed
Fertigation Room|78% Completed
Electrification|0% Completed
pump installation pending
Amal Padmu L P |
Date: 26/06/2023 |
Amal Padmu L P |
Date: 19/06/2023 |
Work in progress | 95% Completed
Sump Tank|0% Completed
Renovation of pond|18% Completed
Fertigation Room|78% Completed
Electrification|0% Completed
pump installation is ongoing
Amal Padmu L P |
Date: 13/06/2023 |
Work in progress | 92% Completed
Sump Tank|0% Completed
Renovation of pond|18% Completed
Fertigation Room|78% Completed
Electrification|0% Completed
pump installation is ongoing
Amal Padmu L P |
Date: 05/06/2023 |
Amal Padmu L P |
Date: 29/05/2023 |
Amal Padmu L P |
Date: 22/05/2023 |
Work in progress | 90% Completed
Electrification|0% Completed
Renovation of pond|18% Completed
Fertigation Room|78% Completed
Sump Tank|0% Completed
pump installation are pending
Amal Padmu L P |
Date: 15/05/2023 |
Amal Padmu L P |
Date: 07/05/2023 |
Work in progress | 88% Completed
Sump Tank|0% Completed
Renovation of pond|18% Completed
Fertigation Room|78% Completed
Electrification|0% Completed
Electrical works and pump installation are pending
Amal Padmu L P |
Date: 02/05/2023 |
Work in progress | 85% Completed
Sump Tank|0% Completed
Renovation of pond|18% Completed
Fertigation Room|78% Completed
Electrification|0% Completed
Electrical works and pump installation are pending
Amal Padmu L P |
Date: 01/05/2023 |
Work in progress | 85% Completed
Sump Tank|0% Completed
Renovation of pond|18% Completed
Fertigation Room|78% Completed
Electrification|0% Completed
Electrical works are pending
Amal Padmu L P |
Date: 28/04/2023 |
Work in progress | 85% Completed
Sump Tank|0% Completed
Renovation of pond|18% Completed
Fertigation Room|78% Completed
Electrification|0% Completed
Electrical works are pending
Amal Padmu L P |
Date: 17/04/2023 |
Work in progress | 83% Completed
Sump Tank|0% Completed
Renovation of pond|18% Completed
Fertigation Room|78% Completed
Electrification|0% Completed
Electrical works are pending
Amal Padmu L P |
Date: 11/04/2023 |
Amal Padmu L P |
Date: 03/04/2023 |
Work in progress | 79% Completed
Sump Tank|0% Completed
Renovation of pond|18% Completed
Fertigation Room|78% Completed
Electrification|0% Completed
desiltation work is completed
Amal Padmu L P |
Date: 27/03/2023 |
Amal Padmu L P |
Date: 21/03/2023 |
Amal Padmu L P |
Date: 13/03/2023 |
Amal Padmu L P |
Date: 06/03/2023 |
Amal Padmu L P |
Date: 27/02/2023 |
Work in progress | 60% Completed
Sump Tank|0% Completed
Renovation of pond|18% Completed
Fertigation Room|78% Completed
Electrification|0% Completed
Construction of cc wall near pump house is ongoing
Amal Padmu L P |
Date: 20/02/2023 |
Amal Padmu L P |
Date: 13/02/2023 |
Amal Padmu L P |
Date: 06/02/2023 |
Work in progress | 48% Completed
Sump Tank|0% Completed
Renovation of pond|18% Completed
Fertigation Room|78% Completed
Electrification|0% Completed
Renovation work for existing pond is started.
Amal Padmu L P |
Date: 30/01/2023 |
Amal Padmu L P |
Date: 23/01/2023 |
Work in progress | 46% Completed
Sump Tank|0% Completed
Renovation of pond|18% Completed
Fertigation Room|78% Completed
Electrification|0% Completed
Informed contractor to complete the remaining works
Amal Padmu L P |
Date: 19/01/2023 |
Work in progress | 46% Completed
Sump Tank|0% Completed
Renovation of pond|18% Completed
Fertigation Room|78% Completed
Electrification|0% Completed
Informed contractor to complete the remaining works
Amal Padmu L P |
Date: 27/12/2022 |
Work in progress | 46% Completed
Fertigation Room|78% Completed
Renovation of pond|18% Completed
Sump Tank|0% Completed
Electrification|0% Completed
Informed contractor to complete the remaining works
GPS Cordinates
Latitude : 10.7359472
Longitude : 76.8445669
Accuracy : 20
Amal Padmu L P |
Date: 29/11/2022 |
Amal Padmu L P |
Date: 29/10/2022 |
Work in progress | 0% Completed
Sump Tank|0% Completed
Renovation of pond|18% Completed
Fertigation Room|78% Completed
Electrification|0% Completed
Foundation works-100% Structural works -100% Plastering -ongoing 60%
GPS Cordinates
Latitude : 10.7139063
Longitude : 76.8686728
Accuracy : 2900
Attached images
Amal Padmu L P |
Date: 25/10/2022 |
Amal Padmu L P |
Date: 18/10/2022 |
Amal Padmu L P |
Date: 17/10/2022 |
Amal Padmu L P |
Date: 10/10/2022 |
Amal Padmu L P |
Date: 01/10/2022 |
Amal Padmu L P |
Date: 26/09/2022 |
Amal Padmu L P |
Date: 26/09/2022 |